Data center power: utilities, grid operators and on-site generation

Who powers each project, as published. 123 of 186 projects have a documented utility, grid operator, generation plan or permit; 16 include on-site or dedicated generation.

By grid operator (where documented): PJM 4 · ERCOT 3 · MISO 3 · NYISO 2 · none (off-grid) 1

ProjectUtility / gridOn-site generationBackup generators & air permitsUtility commission case
Fermi America Project Matador
Amarillo, Carson County, TX · 17 GW
Southwestern Public Service Company (Xcel Energy) →Natural gas (3 Siemens SGT6-5000F turbines, delivered Sept 2026), four proposed Westinghouse AP1000 reactors, and solar plus battery storage——
PORTS-Pike Technology Campus
Piketon, Pike County, OH · 10 GW
AEP Ohio (transmission partner) →
PJM
At least 9.2 GW of new natural gas generation plus 765 kV transmission lines and four substations——
Stratos Project
Box Elder County, UT · 9 GW
—Self-contained natural gas generation isolated from Utah's grid, with battery storage and a 3,000-acre, 500 MW solar array plannedNo Notice of Intent submitted to Utah DEQ as of May 4, 2026; an Approval Order is required before construction—
Monarch Compute Campus
Point Pleasant, Mason County, WV · 8 GW
—On-site gas-fired microgrid: 864 natural gas reciprocating engines (2.16 GW) plus 120 additional natural gas/diesel engines for emergency power, fire suppression and heating——
Comanche Circle
Tolar, Hood County, TX · 5 GW
—Privately funded on-site natural gas generation plus grid (ERCOT) connectionNRG withdrew its air permit application for the 2 GW gas-fired Tolar Power Center, which would have supplied Comanche Circle, on June 18, 2026—
GW Ranch
Fort Stockton, Pecos County, TX · 5 GW
—Private grid isolated from ERCOT: gas turbines plus 1.8 GW of battery storage and 750 MW of solar, fed by a planned 15-mile pipeline to Waha——
Meta Hyperion
Holly Ridge, Richland Parish, LA · 5 GW
Entergy Louisiana →Entergy gas generation: three combined-cycle plants (~3,000 MW) approved Aug. 2025, plus seven more gas plants, grid batteries and nuclear uprates proposed in 202631 emergency diesel-powered generators
LDEQ air permit amended to add 44 natural gas water boilers; the amendment was filed Jan. 14 and approved by the state June 6, per an August 2026 report
LPSC Docket U-37425 (three combined-cycle gas plants and transmission, approved Aug. 20, 2025)
LPSC Docket U-37882 (additional generation and transmission for the data center; set for Dec. 16, 2026 commission meeting)
Homer City Energy Campus
Homer City, Indiana County, PA · 4.4 GW
—On-site natural gas plant: seven GE 7HA.02 combined-cycle turbines plus up to ten aeroderivative simple-cycle turbines; gas supply from EQT via Texas Eastern and Eastern Gas Transmission pipelinesTen 2.5 MW (3,633 bhp) and two 1.0 MW (1,483 bhp) diesel emergency generator engines, plus one 399 bhp diesel fire water pump engine—
Project Camellia
Rincon, Effingham County, GA · 3.21 GW
Georgia Power →diesel backup only (on-site emergency diesel generators; no regular on-site generation anticipated)——
Project Thunderbird
Enid, Garfield County, OK · 2.75 GW
—3.3 GW
On-site natural gas-fueled generation, behind the meter, via partnership with a natural gas midstream energy provider
——
Project Tembo
Cheyenne, Laramie County, WY · 2.7 GW
—Tallgrass BFC Power / Cheyenne Power Hub natural gas plants plus Black Hills Energy resources and fuel cells
Two combined cycle power plants plus temporary and permanent aeroderivative turbines and a fuel cell yard (BFC Power and Cheyenne Power Hub)
——
Project Kilby
Pecos, Reeves County, TX · 2.67 GW
—2.67 GW
Co-located natural gas plant operating behind the meter, with the companies saying a grid connection could come later
TCEQ Air Quality Permit No. 181895, PSD permit PSDTX1684 and GHG PSD permit GHGPSDTX260 (Energy Forge One LLC; applications under review as of the June 10, 2026 public meeting notice)—
Project Jupiter
Santa Teresa, Doña Ana County, NM · 2.46 GW
—on-site microgrid with Bloom Energy fuel cells (replacing an earlier gas-turbine plan)NMED air quality permit application by Yucca Growth Infrastructure for a fuel cell power system; public hearing scheduled to begin Oct. 19, 2026; NMED decision due by Nov. 23 (as scheduled in July 2026)—
Quantum Frederick
Adamstown, Frederick County, MD · 2.4 GW
——Aligned Data Centers: 168 diesel emergency generators rated 3,000 kW each with SCR, plus four 1,000 kW generators
MDE permit-to-construct for Aligned's emergency generators issued effective Jan. 30, 2025
Maryland PSC Order No. 90830 (Mail Log No. 302893): Aligned's CPCN exemption request for backup generators; provisional authorization limited to 70 MW
Meta Maysville campus
Maysville, Mason County, KY · 2.2 GW
—Grid power under East Kentucky Power Cooperative's large-load rate structure; Meta says it will pay for upgrades and the electricity——
Project Tamarack
West Columbia, Mason County, WV · 2.16 GW
Appalachian Power (AEP) →Existing grid via existing Appalachian Power/AEP infrastructure at the property——
IREN Sweetwater data center campus
Sweetwater, Fisher County, TX · 2 GW
ERCOTERCOT grid; 345kV/138kV bulk substation at Sweetwater 1——
Project Horizon
Fort Stockton, Pecos County, TX · 2 GW
—On-site aero-derivative natural gas turbines with battery storage and grid interconnect, per Poolside
up to 1.2 GW initial
——
Project Phoenix
Shippingport, Beaver County, PA · 2 GW
—Its own dedicated onsite power instead of the local electrical grid
natural gas-fired on-site power
——
Joliet Technology Center
Joliet, Will County, IL · 1.8 GW
ComEd (developer-paid system upgrades) →
PJM
———
Paducah Site AI campus
Paducah, McCracken County, KY · 1.8 GW
—About 2 GW of new gas-fired generation and up to 2.6 GW of battery storage by NextEra; surplus to the regional grid. Big Rivers Electric Power Corporation (wholesale) and Jackson Purchase Energy Cooperative (retail) would serve the campus, with Paducah Power System as a community partner——
Project Cardinal Data Center Campus
Yorkville, Kendall County, IL · 1.8 GW
ComEd →———
xAI Colossus 2
Memphis, Shelby County, TN · 1.78 GW
—Gas turbines at former Duke Energy plant in Southaven, MS (41 permanent turbines permitted, 1.2 GW; 69 temporary turbines reported by July 2026)Mississippi Environmental Quality Permit Board approved xAI's permit for permanent turbines on March 10, 2026, with all six members present voting in favor—
Ridgeline Facility
Thomas, Tucker County, WV · 1.6 GW
—On-site natural gas / diesel combustion turbines with heat recovery steam generators (off-grid microgrid); three 10-million-gallon diesel storage tanksWVDEP permit R13-3713 classifies the facility as a synthetic minor source, with physical and operational limits to stay below PSD major thresholds—
T5 @ Chicago IV
Grayslake, Lake County, IL · 1.55 GW
ComEd →—diesel backup generation infrastructure—
Project Red Clay
Hayneville, Lowndes County, AL · 1.5 GW
Alabama Power →———
Vantage Frontier Campus
Albany, Shackelford County, TX · 1.4 GW
—onsite natural gas microgrid, per Epoch AI
Behind-the-meter gas microgrid using Jenbacher reciprocating engines
700 MW
——
Saline Township Stargate Data Center
Saline Township, Washtenaw County, MI · 1.38 GW
DTE Electric →
MISO
DTE existing resources plus 1,383 MW of DTE-owned battery storage14 diesel-fired emergency generators and 1 diesel fire water pump
EGLE air quality permit issued Jan. 13, 2026 for 14 diesel backup generators and one diesel firewater pump
MPSC Case No. U-21990
Port Washington (Lighthouse) Data Center Campus
Port Washington, Ozaukee County, WI · 1.3 GW
We Energies (transmission by American Transmission Co.) →Developer says 70% of campus power from solar, wind and battery storage, with renewable purchases matching the restWDNR minor source construction permit 25-MIN-094 and initial operation permit 24618528A-F01 issued June 12, 2026 for 45 diesel-fired emergency generators
45 diesel-fired emergency generators
PSCW docket 137-CE-229 (ATC Ozaukee County Distribution Interconnection Project)
PSCW docket 6630-TE-113 (We Energies very large customer tariff; decision of May 21, 2026, challenged by Oracle)
Project Arrowhead
Irwin County, GA · 1.25 GW
Georgia Power →———
Prometheus Hyperscale Evanston Campus
Evanston, Uinta County, WY · 1.25 GW
none (off-grid)natural gas (mostly); founder wants to add nuclear eventually
natural gas engines and turbines operated as a fully islanded microgrid
——
Fort Meade Hyperscale Data Center
Fort Meade, Polk County, FL · 1.2 GW
Duke Energy →———
Project Marvel
Bessemer, Jefferson County, AL · 1.2 GW
Alabama Power →———
Stargate Abilene
Abilene, Taylor County, TX · 1.2 GW
ERCOTNatural gas, wind and solar
360 MW
Gas turbines (10 built; developers seek 41 more)
62 backup diesel generators (18 more proposed)
TCEQ Electric Generating Unit Standard Permit, Registration 177263 (Abilene DC 1, LLC, Longhorn Data Center): modification to five Titan 350 simple-cycle turbines at 38 MW each (and five GE LM2500 turbines at 34.1 MW each)
—
Stargate Milam County
Burlington, Milam County, TX · 1.2 GW
—SB Energy plans new generation (and storage) to supply most of the campus's power——
QTS Cedar Rapids Data Center Campus
Cedar Rapids, Linn County, IA · 1.05 GW
Alliant Energy →Temporary modular, self-contained generator units for construction and commissioning, expected to operate less than six months——
Goodnight Campus
Claude, Armstrong County, TX · 1.03 GW
ERCOTERCOT grid; 265.5 MW Goodnight Wind Farm co-location; 933 MW of off-grid gas generation—PUCT Docket No. 59220 (SB 6 net metering application for Crusoe Load Two, a 260 MW data center, with Goodnight Wind)
Global AI Data Center
Windsor, Weld County, CO · 1 GW
Poudre Valley Rural Electric Association (35 MW committed) →———
Joule Energy and Data Center Campus
McCornick, Millard County, UT · 1 GW
—Off-grid natural gas: Caterpillar G3520K generator sets plus 1.1 GWh of battery storage——
Meta El Paso Data Center
El Paso, El Paso County, TX · 1 GW
El Paso Electric →El Paso Electric's proposed 366 MW McCloud gas plant ($473M, 813 Enchanted Rock modular generators) on 31 adjacent acres, dedicated to the data center—PUCT Docket 59076 (El Paso Electric McCloud Generation)
Meta Lebanon Data Center
Lebanon, Boone County, IN · 1 GW
—134 MW
temporary natural gas-fired generators (65 requested in permit application; company expects about 32)
Life Cycle Power submitted an IDEM air emissions permit application in February for gas-fired generators—
Meta Prometheus
New Albany, Franklin and Licking counties, OH · 1 GW
—Behind-the-meter gas: Socrates South and Socrates North (200 MW each, built by Williams subsidiary Will-Power), plus the 250 MW Socrates the Younger plant with 116 MW batteries (approved June 2026); Meta also cited ~440 MW of Ohio solar——
Project Boulder
Walterboro, Colleton County, SC · 1 GW
—Would use roughly half the capacity of the proposed Canadys Station gas plant——
Project Cannoli
Van Buren Township, Wayne County, MI · 1 GW
DTE Energy →DTE grid; Google-backed 1.6 GW of renewables and up to 480 MW of storage under 20-year contracts—MPSC Case U-22058
Stafford Technology Campus
Stafford County, VA · 1 GW
Dominion Energy →———
Natelli data center, U.S. 158
Vance County, NC · 900 MW
Duke Energy →———
Crossroads Technology Campus
Spotsylvania County, VA · 894 MW
Rappahannock Electric Cooperative (distribution); Dominion Energy (transmission) → →———
Viridian Data Center Campus (former GM/JATCO site)
Janesville, Rock County, WI · 800 MW
Alliant Energy →———
Lake Mariner
Somerset, Niagara County, NY · 750 MW
—About 90% hydropower from New York Power Authority, remainder NYSEG (s4); dual 345 kV transmission lines (s2)——
Project Mica
Kansas City, Clay County, MO · 700 MW
—Adjacent Nashua Power Station and onsite substations——
North Country Colocation Services Massena Expansion
Massena, St. Lawrence County, NY · 635 MW
NYISOHydroelectric power from the St. Lawrence River68—
CyrusOne Sangamon County Data Center
Waverly, Sangamon County, IL · 634 MW
Ameren Illinois / Rural Electric Convenience Cooperative → →Grid, with 420 diesel backup generators——
Amazon Becker Data Center
Becker, Sherburne County, MN · 600 MW
Xcel Energy →About 250 Tier 4 diesel backup generators (250 kW to 2.75 MW each) proposed—Minnesota PUC Docket No. PT7151/CN-24-435
Amazon Web Services Louisa County campuses
Louisa, Louisa County, VA · 600 MW
Rappahannock Electric Cooperative →———
CRG Festus Data Center
Festus, Jefferson County, MO · 600 MW
Ameren Missouri →———
Calvert Technology Center
Lusby, Calvert County, MD · 500 MW
—Power agreement with Constellation Energy (reported)——
Compass Statesville
Statesville, Iredell County, NC · 500 MW
Duke Energy →—40 backup generators per building—
Logan Prairie Data Center
Latham, Logan County, IL · 500 MW
Ameren →
MISO
———
Stream Data Centers STAMP Campus
Alabama, Genesee County, NY · 500 MW
—Direct connection to the 345kV bulk power system (company-stated)——
Tooele Valley data center (Burmester Road / I-80)
Tooele County, UT · 500 MW
—Developer holds a letter of intent for modular nuclear reactors on site, per ABC4; not confirmed as data center supply——
CyrusOne CHI-11 Data Center Campus
Yorkville, Kendall County, IL · 480 MW
ComEd →———
Polaris Forge 1
Ellendale, Dickey County, ND · 400 MW
Montana-Dakota Utilities →
MISO
Grid power, which the company and city describe as excess wind powerND DEQ Air Pollution Control Permit to Construct ACP-18296 v1.0 (synthetic minor) for the ELN Generation Plant, 9663 87th Ave. SE, Ellendale; posted by DEQ as a draft—
Fleet Data Centers TRIC campuses (South Valley and Peru Ridge)
Storey County, NV · 362 MW
NV Energy →Temporary private natural gas and diesel engine plants for 2–3 years, then NV Energy permanent serviceAir quality permit applications for both gas plants submitted to the Nevada Division of Environmental Protection (as of April 2026)PUCN Docket 26-04026 (South Valley, 144 MW) and Docket 26-04027 (Peru Ridge, 218 MW)
Hut 8 River Bend Campus
St. Francisville, West Feliciana Parish, LA · 330 MW
Entergy Louisiana →———
Imperial Data Center
Imperial, Imperial County, CA · 330 MW
—On-site substation, battery system, and natural gas generators for backup100 natural gas-powered backup emergency generators—
CloudHQ ORD Campus
Mount Prospect, Cook County, IL · 300 MW
ComEd (Commonwealth Edison) →———
CoreWeave Lancaster data center
Lancaster, Lancaster County, PA · 300 MW
——PA DEP air quality permit for emergency diesel generators at 216 Greenfield Road; draft approval published in the Pennsylvania Bulletin on November 15, 2025—
Google Botetourt County Data Center Campus
Botetourt County, VA · 300 MW
Appalachian Power →Power purchase agreement for the full output (79.3 MW) of the Rocky Forge Wind project——
Lake Hawkeye
Lansing, Tompkins County, NY · 300 MW
—Central New York grid, which the developer describes as predominantly zero-carbon with surplus available——
Nebius Vineland Data Center
Vineland, Cumberland County, NJ · 300 MW
—About 85% on-site natural gas generation (including Bloom Energy fuel cells; proposed 1.5-million-gallon LNG tank), remainder from Vineland Municipal Utilities and Atlantic City Electric
62 on-site generators, at least 45 observed operating in August 2026
NJDEP: no permits issued and no pending permit applications for power generators at the DataOne facility (August 2026)
Earlier application: 32 natural gas engines (five for backup) and six diesel emergency generators; second phase now proposes Bloom Energy fuel cells
—
New Hill Digital Campus
Apex, Wake County, NC · 300 MW
Duke Energy →—about 80 3-megawatt generators—
PowerCampus Dallas
Lancaster, Dallas County, TX · 300 MW
Oncor (private 300 MW substation) →———
Riverview Innovation & Technology Campus
Tonawanda, Erie County, NY · 300 MW
NYISO
National Grid →
———
xAI Colossus
Memphis, Shelby County, TN · 300 MW
Memphis Light, Gas and Water (MLGW) / TVA → →MLGW/TVA grid plus on-site gas turbines (15 permitted, 247.2 MW) and Tesla Megapacks——
Project Blue
Tucson, Pima County, AZ · 286 MW
Tucson Electric Power (TEP) →———
Golden Valley Technology Hub
Taft, Kern County, CA · 275 MW
—Surplus power from CRC's natural gas-fired Elk Hills Power Plant; grid as limited backup15 diesel generators of 2.5 MW each, plus batteries—
Core Scientific Denton Data Center
Denton, Denton County, TX · 260 MW
Denton Municipal Electric →—Backup generators and heat exchangers on an additional 2.1 leased acres—
Project Mila
Trenton, Butler County, OH · 250 MW
Duke Energy →———
QTS Fayetteville data center campus
Fayetteville, Fayette County, GA · 250 MW
Georgia Power →———
Prime Phoenix Campus
Avondale, AZ · 240 MW
—Dedicated on-site substation
250MW substation, Phase 1 commissioned
——
Meta Beaver Dam Data Center
Beaver Dam, Dodge County, WI · 220 MW
Alliant Energy →———
Compass Datacenters Goodyear Campus
Goodyear, Maricopa County, AZ · 212 MW
Arizona Public Service (APS) →Grid power through a Compass-owned 230kV substation and two 69kV substations, per 2019 planning documents——
WF Industrial Yaphank Data Center
Yaphank, Suffolk County, NY · 176.6 MW
LIPA (Long Island Power Authority) →———
QTS Richmond campus expansion (RIC4 and RIC5)
Sandston, Henrico County, VA · 110 MW
——370 diesel-fired emergency generators (DEQ application)
Application submitted to Virginia DEQ for 370 diesel-fired emergency generators
—
Utah Data Center
Bluffdale, Utah County, UT · 65 MW
—Dedicated 65 MW power substation——
Blueprint Taylor Data Center
Taylor, Williamson County, TX · 60 MW
Oncor →Electric grid, via an on-site electricity substationbackup power generators—
Deep Green Lansing data center
Lansing, Ingham County, MI · 24 MW
Lansing Board of Water and Light →16 MW
natural gas fuel cells
——
Amazon Web Services Madison County Mega Site campus
Canton, Madison County, MS · —
Entergy Mississippi →—Over 300 diesel generators at Canton (more than 700 across both Madison County campuses)
MDEQ permits issued for backup diesel generators, allowing up to 100 hours a year of maintenance and readiness testing
—
Amazon Web Services Richmond County data center campus
Hamlet, Richmond County, NC · —
Duke Energy →———
AVAIO Digital Leo
Little Rock, Pulaski County, AR · —
Entergy Arkansas →on-site power using on-site natural gas infrastructure (planned)——
AWS Fayette County Data Center Campus
Jeffersonville, Fayette County, OH · —
AES Ohio →Grid; transmission infrastructure for first phase to exceed $22 million (per OCC filing)——
AWS Project Green
New Florence, Montgomery County, MO · —
Ameren Missouri →Ameren Missouri grid; Amazon to pay full cost of electric serviceAmazon applied for a minor air construction permit under 10 CSR 10-6.060 (application cover letter dated March 14, 2026)
476 generators of 2.75 MW, 4 of 1.6 MW, 1 of 400 kW and 2 of 250 kW
—
AWS Wilmington data center
Wilmington, Clinton County, OH · —
AES Ohio →———
Balico data center campus and gas plant
Chatham, Pittsylvania County, VA · —
—On-site 3,500 MW natural gas power plant owned/operated by Balico, supplied via Mountain Valley Pipeline——
Falls Township Innovation Campus
Falls Township, Bucks County, PA · —
——72 diesel-fired emergency engines approved; 280 natural gas-fired backup generator engines (4,287 hp each) applied for
Five air and water discharge permits approved, including 72 diesel-fired emergency engines; separate application for 280 gas-fired engines drew 1,236 comments to DEP
—
Gateway Digital Campus
Villa Ridge, Franklin County, MO · —
Ameren Missouri →Ameren Missouri grid; developer says it will fund 100% of infrastructure and transmission upgrades needed to serve the site——
Google Chesterfield County data center campuses
Chesterfield County, VA · —
—Agreement to purchase 200 MW from Commonwealth Fusion Systems' planned Chesterfield fusion plant——
Google Fort Wayne data center
Fort Wayne, Allen County, IN · —
Indiana Michigan Power (I&M) →Grid (I&M) with a custom demand response program——
Google Hermantown Data Center
Hermantown, St. Louis County, MN · —
Minnesota Power →Minnesota Power to build 700 MW of new clean energy sources, including 300 MW of wind and 400 MW of battery storage——
Google Kansas City Data Center (Hunt Midwest Business Center)
Kansas City, Clay County, MO · —
Evergy →PPA with Ranger Power and DESRI for 400 MW of carbon-free energy capacity, new to the grid, from the Beavertail Solar farm——
Google Morgan County Data Center
Monrovia, Morgan County, IN · —
AES Indiana →———
Google West Memphis Data Center
West Memphis, Crittenden County, AR · —
Entergy Arkansas →Entergy Arkansas grid; Google to support a new 600MW solar project with a 350MW battery system in Jefferson County——
Howell Township Data Center
Howell, Livingston County, MI · —
DTE Energy →———
Meta Cheyenne Data Center
Cheyenne, Laramie County, WY · —
Cheyenne Light, Fuel & Power (Black Hills Energy) →Black Hills Energy grid, with new resources including renewables (company-stated)——
Meta Rosemount Data Center
Rosemount, Dakota County, MN · —
Xcel Energy →Supported by 100% renewable energy, per Meta——
Microsoft Fairwater
Mount Pleasant, Racine County, WI · —
We Energies →Microsoft says it will match fossil-fuel power with carbon-free energy; 250 MW solar project in Portage County under constructionWDNR construction permit application 24-MIN-238 and operation permit revision 25230249A-F03 (six new and two revised data centers); public hearing Dec. 2, 2024
40 emergency generators and two emergency fire pumps at the 1.3 million sq ft facility; 39 backup generators at the existing facility
—
Microsoft Fairwater Atlanta
Fayetteville, Fayette County, GA · —
—Utility grid only; no on-site generation or UPS, per Microsoft——
Microsoft Gaines Township data center
Caledonia, Kent County, MI · —
Consumers Energy →———
Pennsylvania Digital 1 (PAX-1)
Middlesex Township, Cumberland County, PA · —
PPL Electric Utilities →PPL Electric Utilities grid; 1.35 gigawatt peak energy demand with planned upgradesmore than 500 diesel generators—
Project Cherry Blossom
Frenchtown Township, Monroe County, MI · —
DTE →———
Project Cumulus
St. Charles, St. Charles County, MO · —
——Backup generators with about 1 million gallons of diesel fuel stored in 150 tanks—
Project Delta
Walnut Cove, Stokes County, NC · —
Duke Energy →Generators initially, then Duke Energy grid connection (developer plan)——
Project Flex
New Hudson, Oakland County, MI · —
DTE Energy (new substation required) →—Battery energy storage as primary backup for outages under 4 hours; packaged diesel generators in acoustic enclosures as secondary backup—
Project Galaxy (AWS Sidney data center)
Sidney, Shelby County, OH · —
AES Ohio →
PJM
———
Project Liberty
Marion, Marion County, SC · —
—Utility power could not be sourced within required timeframe——
Project Rainier (AWS New Carlisle campus)
New Carlisle, St. Joseph County, IN · —
Indiana Michigan Power (I&M) →———
Project Spalding
Spalding County, GA · —
—Proposed solar farm on the property——
QTS DeForest Data Center Campus
DeForest, Dane County, WI · —
—Draft agreement committed to drawing 45% of energy from renewable resources——
Salem Township Innovation Campus
Salem Township, Luzerne County, PA · —
PPL Electric Utilities (transmission and delivery); Talen Energy as retail power supplier →
PJM
Susquehanna nuclear plant via a 1,920-MW Talen Energy power purchase agreement running through 2042—FERC Docket ER24-2172 (amended Susquehanna interconnection service agreement)
Sentinel / Green Fig Data Center
Malvern, Chester County, PA · —
PECO (electric); Aqua (water) →—Diesel standby generators—
Spring Valley Technology Park
Loudoun County, VA · —
—Natural gas-powered hydrogen fuel cells with battery storage, plus three on-site substationsTier 4 generators enclosed on six sides (applicant commitment)—
Switch Big Beaver data center campus
Big Beaver, Beaver County, PA · —
FirstEnergy →—About 270 MW of total backup generator capacity, per filed documents as reported by DCD—
Valara Holdings High Performance Compute Center
Spartanburg, Spartanburg County, SC · —
—450 MW
natural gas generators and combustion turbines
Permitted for 24 natural gas generators (2,000 kW each); March 2026 request to SCDES for five 17-MW and six 54-MW combustion turbines—

Values are as stated in each project’s sources; open a project for citations and source excerpts. A dash means nothing was found in the sources reviewed, not that none exists. Arrows link to the utility’s page. Will data centers raise my electric bill? · All utilities