GW Ranch

Fort Stockton, Pecos County, TX

Also known as Pacifico Energy GW Ranch

ApprovedState air permit for up to 7.65 GW of gas generation issued January 2026; developer targets first power in the first half of 2027
  1. Rumored
  2. Proposed
  3. Approved
  4. Under construction
  5. Operating

GW Ranch is a planned off-grid gas, battery and solar power complex for hyperscale data centers on more than 8,000 acres in Pecos County, about 17 miles north of Fort Stockton. Texas regulators issued an air permit in January 2026 covering up to 7.65 GW of gas-fired generation, and developer Pacifico Energy says it aims to reach 5 GW by 2031. No tenant is named in the sources reviewed.

Site size
8,000 acres
"more than 8,000 acres"

Key facts

Size & schedule

Planned capacity5 GW [2]
developer goal for dedicated private-grid power by 2031, starting with 1 GW (Energy Tech)
Planned capacity7.65 GW [3]
gas-fired generation covered by the TCEQ air permit; a permit ceiling rather than a stated campus load, and described as the largest in the U.S. by the company
Phase 1 capacity1 GW [2]
developer plans to start with 1 GW (Energy Tech)
Site size8,000 acres [1]
"more than 8,000 acres"
Target completionFirst power expected in the first half of 2027 (developer), with a path to scale beyond 5 GW [1]

How big is that? Data center sizes compared with football fields and Central Park.

Power

Power supplyPrivate grid isolated from ERCOT: gas turbines plus 1.8 GW of battery storage and 750 MW of solar, fed by a planned 15-mile pipeline to Waha [3]

Water

CoolingClosed-loop cooling (company statement) [4]

Figures are as stated by the cited source. Where sources disagree, each figure is shown.

Water and power

Water

Not disclosed. No source reviewed gives a water figure for this site. The Census does not estimate one.

Power

Planned capacity5 GW [2]
Phase 1 capacity1 GW [2]
Power supplyPrivate grid isolated from ERCOT: gas turbines plus 1.8 GW of battery storage and 750 MW of solar, fed by a planned 15-mile pipeline to Waha [3]

Disclosed figures only, each as the cited source states it. Many are projections or permit limits, not metered use. How data center water and power use is measured, and every disclosed figure →

Timeline

  1. Texas Commission on Environmental Quality issues an air permit for up to 7.65 GW of gas generation, as announced by the developer [3]

  2. Local TV reports the permit and the developer's expectation of power in the first half of 2027 [1]

Issues raised

  • The Big Bend Sentinel notes that closed-loop cooling still needs large water volumes for the initial fill and periodic refills [4]
  • The permit size and 'largest' description come from the developer [1][3]

Issues are concerns and claims raised by the parties, officials or residents named in the cited sources. They are reported as attributed, not as findings by the Census.

Sources

  1. Texas approves "largest permitted data center campus" in the U.S.
    KCBD · Feb 1, 2026 · news
  2. Data Center-Focused GW Ranch Project Clears Texas Air Permitting Hurdle
    Energy Tech · Jan 28, 2026 · news
  3. Pacifico Energy Obtains Air Permit for GW Ranch Project in Texas
    Turbomachinery Magazine · Jan 28, 2026 · news
  4. Massive AI data center coming to Pecos County
    Big Bend Sentinel · Feb 4, 2026 · news

Cite this page

Last updated Oct 15, 2026. Figures may change as records are updated — include the date you retrieved them.

APAData Center Census. (2026). GW Ranch. Retrieved from https://datacentercensus.com/dc/gw-ranch-pecos-county-tx
MLA“GW Ranch.” Data Center Census, Oct 15, 2026, https://datacentercensus.com/dc/gw-ranch-pecos-county-tx.
Linkhttps://datacentercensus.com/dc/gw-ranch-pecos-county-tx

Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.