Data centers in Texas

The Census tracks 19 major data center projects in Texas, with 41.72 GW of planned capacity: 3 proposed, 4 approved, 8 under construction, 2 operating, 2 denied.

How many data centers are in Texas?

The Census tracks 19 major data center projects in Texas as of Nov 6, 2026: 3 proposed, 4 approved, 8 under construction, 2 operating, 2 denied. That covers major sourced projects, not every smaller facility. The largest by planned capacity is Fermi America Project Matador (17 GW). Latest change, at Stargate Abilene: Epoch AI estimates all 8 buildings (7-8 estimated) operational, for 824 MW of IT power (Epoch AI estimate) (Nov 1, 2026).

Projects tracked
19
Planned capacity, active projects
41.72GW
Under construction
8
Permanent jobs promised
1,580
RumoredProposedApprovedUnder constructionOperatingPausedCancelledDenied© OpenFreeMap © OpenStreetMap

Texas data center projects

ProjectStatusCapacityDeveloperLast update
Fermi America Project Matador
Amarillo, Carson County
Under construction 17 GW Fermi America Sep 22, 2026
Comanche Circle
Tolar, Hood County
Approved 5 GW Sailfish Investors Oct 13, 2026
GW Ranch
Fort Stockton, Pecos County
Proposed 5 GW Pacifico Energy Feb 1, 2026
Project Kilby
Pecos, Reeves County
Proposed 2.67 GW Microsoft, Chevron, Joulent LLC Jul 31, 2026
IREN Sweetwater data center campus
Sweetwater, Fisher County
Under construction 2 GW IREN Sep 8, 2026
Project Horizon
Fort Stockton, Pecos County
Proposed 2 GW Poolside Apr 2, 2026
Galaxy Helios
Afton, Dickens County
Under construction 1.6 GW Galaxy Digital Jul 22, 2026
Vantage Frontier Campus
Albany, Shackelford County
Under construction 1.4 GW Vantage Data Centers Sep 3, 2026
Stargate Abilene
Abilene, Taylor County
Operating 1.2 GW Crusoe, Oracle Nov 1, 2026
Stargate Milam County
Burlington, Milam County
Under construction 1.2 GW SB Energy, SoftBank Apr 22, 2026
Goodnight Campus
Claude, Armstrong County
Under construction 1.03 GW Crusoe Sep 2026
Meta El Paso Data Center
El Paso, El Paso County
Under construction 1 GW Meta Jul 28, 2026
Project Aggie
College Station, Brazos County
Denied 600 MW Priority Power Management Sep 11, 2025
PowerCampus Dallas
Lancaster, Dallas County
Under construction 300 MW Skybox Datacenters Jan 27, 2025
Core Scientific Denton Data Center
Denton, Denton County
Operating 260 MW CoreWeave, Core Scientific Jan 13, 2026
Blueprint Taylor Data Center
Taylor, Williamson County
Approved 60 MW Blueprint Projects Sep 17, 2026
Compass Datacenters Red Oak second campus
Red Oak, Ellis County
Approved — Compass Datacenters May 2026
Highlander SM One data center
San Marcos, Hays County
Denied — Highlander SM One Jun 16, 2026
Rowan Digital Infrastructure Temple Campus
Temple, Bell County
Approved — Rowan Digital Infrastructure Aug 12, 2026

Recent changes in Texas

  1. Stargate Abilene TX
    Epoch AI estimates all 8 buildings (7-8 estimated) operational, for 824 MW of IT power (Epoch AI estimate) Epoch AI
  2. Comanche Circle TX
    Commissioners vote 3-1 against a settlement offered by Sailfish Investors that would have shrunk the Hood County footprint from about 2,523 to about 1,375 acres, then unanimously deny the developer's appeal of the county's on-site permit decision Texas Public Radio
  3. Fermi America Project Matador TX
    Fermi and TensorWave amend their 222 MW lease to move the closing date from Sept. 30 to Oct. 31, 2026, while a lease guaranty is negotiated Fermi America (ACCESS Newswire)
  4. Fermi America Project Matador TX
    Three Siemens gas turbines arrive on site ABC 7 Amarillo
  5. Blueprint Taylor Data Center TX
    Texas Attorney General Ken Paxton launches an investigation into the land deal Office of the Attorney General of Texas
  6. Stargate Abilene TX
    On Oracle's Q1 FY2027 earnings call, its CEO said 6 of the 8 Abilene buildings, 618 MW or 75% of total capacity, had been delivered to the customer, and that Oracle delivered about 131,000 GPUs there in the quarter The Motley Fool
  7. Comanche Circle TX
    Hood County Commissioners Court postpones its discussion of the proposed data center projects, including Comanche Circle, to October 13 so a public hearing can be properly advertised NBC DFW
  8. IREN Sweetwater data center campus TX
    IREN says the 2 GW Sweetwater Hub was conditionally included in ERCOT's Batch Zero process as base load, with 300 MW under construction at Sweetwater 1 for Q4 2027 delivery IREN (GlobeNewswire)
  9. Vantage Frontier Campus TX
    Satellite imagery shows Buildings 1-5 shells complete and roofed Epoch AI
  10. Stargate Abilene TX
    Chamber panel addresses resident concerns over housing, power, water and noise KACU

About this count

This page counts the major projects the Census has researched and sourced: 19 as of Nov 6, 2026, including 2 cancelled or denied. It does not yet include every smaller colocation or enterprise facility, so the total number of buildings in Texas is higher. We add projects as they are announced or found in public filings.

Counties with tracked projects

Armstrong County · Bell County · Brazos County · Carson County · Dallas County · Denton County · Dickens County · El Paso County · Ellis County · Fisher County · Hays County · Hood County · Milam County · Pecos County · Reeves County · Shackelford County · Taylor County · Williamson County

Moratoriums

  1. Comanche Circle TX
    Commissioners reject six-month moratorium 3-2 KERA News
  2. Comanche Circle TX
    Commissioners reject second moratorium 3-2 and seek Attorney General opinion on authority KERA News

All 4 moratorium actions in Texas →

AI data centers in Texas

14 tracked projects here are counted as AI data centers: Core Scientific Denton Data Center (operating), Blueprint Taylor Data Center (approved), Fermi America Project Matador (under construction), Goodnight Campus (under construction), Highlander SM One data center (denied), IREN Sweetwater data center campus (under construction), Project Aggie (denied), Project Horizon (proposed), Stargate Abilene (operating), Stargate Milam County (under construction), Vantage Frontier Campus (under construction), Project Kilby (proposed), GW Ranch (proposed), Galaxy Helios (under construction). All AI data centers →

Data center rules in Texas

  • Texas: Senate Bill 6 (89th Legislature): large electrical loadsin effect

All local rules →

Utilities serving tracked projects in Texas

Southwestern Public Service (SPS) · El Paso Electric · Oncor · Denton Municipal Electric. Will data centers raise electric bills here? →

Follow Texas

RSS feed of Texas changes · Printable fact sheet · Embed this tracker · Projects near a ZIP code · Data center jobs near you

Texas data centers: common questions

How many data centers are in Texas?

The Census tracks 19 major data center projects in Texas as of Nov 6, 2026: 3 proposed, 4 approved, 8 under construction, 2 operating, 2 denied. This counts large projects the Census has researched and sourced, not every smaller colocation or enterprise facility, so the total number of data center buildings in Texas is higher.

What is the largest data center project in Texas?

By published planned capacity, the largest tracked project in Texas is Fermi America Project Matador in Amarillo, Carson County, TX, at 17 GW. Its status is under construction.

Are data centers being built in Texas right now?

Yes. 8 tracked projects are under construction in Texas: Fermi America Project Matador, IREN Sweetwater data center campus, Galaxy Helios, Vantage Frontier Campus, Stargate Milam County and 3 more.

How many jobs will data centers create in Texas?

6 tracked projects in Texas have a published permanent-jobs figure, adding up to 1,580 permanent jobs as announced. Announced jobs are promises, not guarantees; construction employment is typically much larger but temporary.

How many AI data centers are in Texas?

The Census counts 14 tracked projects in Texas as AI data centers, because their own sources describe them as built for AI: Core Scientific Denton Data Center (operating), Blueprint Taylor Data Center (approved), Fermi America Project Matador (under construction), Goodnight Campus (under construction), Highlander SM One data center (denied), IREN Sweetwater data center campus (under construction), Project Aggie (denied), Project Horizon (proposed), Stargate Abilene (operating), Stargate Milam County (under construction), Vantage Frontier Campus (under construction), Project Kilby (proposed), GW Ranch (proposed), Galaxy Helios (under construction). That is a floor; other campuses may run AI workloads without their sources saying so.

Are there data center moratoriums in Texas?

The Census moratorium tracker records 4 moratorium actions in 2 jurisdictions in Texas, most recently in Texas (Sep 21, 2026). Each one, with its source, is on the Texas moratorium page.

Answers are generated from the sourced project records above and update when a record changes. Open any project for its sources.

Texas data center report card

Texas data center report card: 19 tracked projects, 41.72 GW of published capacity, 8 under construction.

A square image of these figures, sized for Instagram, LinkedIn and slides. It is redrawn whenever a record changes, so the link always shows today’s numbers.

Download the image

Free to use with credit to Data Center Census (CC BY 4.0).

Cite this page

Last updated Nov 6, 2026. Figures may change as records are updated — include the date you retrieved them.

APAData Center Census. (2026). Data centers in Texas. Retrieved from https://datacentercensus.com/us/texas
MLA“Data centers in Texas.” Data Center Census, Nov 6, 2026, https://datacentercensus.com/us/texas.
Linkhttps://datacentercensus.com/us/texas

Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.