Crusoe is linked to 2 tracked projects in Texas, totaling 2.23 GW of planned capacity. Role: developer.

Ranked #18 of 59 developers by the published capacity of its tracked projects that are proposed, approved, under construction or operating, as developer or operator (2.23 GW). See the ranking →

ProjectStatusCapacityDeveloperLast update
Goodnight Campus
Claude, Armstrong County, TX
Under construction 1.03 GW Crusoe Sep 2026
Stargate Abilene
Abilene, Taylor County, TX
Operating 1.2 GW Crusoe, Oracle Nov 1, 2026

Latest Crusoe data center news

The newest dated changes at Crusoe’s tracked projects, each from the filing, notice or report linked beside it.

  1. Stargate Abilene TX
    Epoch AI estimates all 8 buildings (7-8 estimated) operational, for 824 MW of IT power (Epoch AI estimate) Epoch AI
  2. Stargate Abilene TX
    On Oracle's Q1 FY2027 earnings call, its CEO said 6 of the 8 Abilene buildings, 618 MW or 75% of total capacity, had been delivered to the customer, and that Oracle delivered about 131,000 GPUs there in the quarter The Motley Fool
  3. Stargate Abilene TX
    Chamber panel addresses resident concerns over housing, power, water and noise KACU
  4. Goodnight Campus TX
    At a Google and Crusoe community open house in Claude, Crusoe says the campus will include six buildings; KFDA reports Google is expected to receive the first buildings in early 2027, with construction wrapping up by the end of 2027 KFDA NewsChannel 10
  5. Goodnight Campus TX
    Filings with the Texas Department of Licensing and Regulation cover Buildings 3 and 4, each with an estimated construction cost of $500 million DatacenterDynamics
  6. Goodnight Campus TX
    PUCT approves net metering application in Docket No. 59220 for the co-located Armstrong County data center load, with ERCOT curtailment obligations White & Case LLP
  7. Stargate Abilene TX
    Buildings 3-4 become operational, bringing IT power to 412 MW at 4 buildings (Epoch AI estimate from satellite analysis) Epoch AI
  8. Stargate Abilene TX
    Lancium and Crusoe brief Abilene leaders; construction expected to run through Q1 2027 KTXS

This page lists projects in the Census where Crusoe is named as developer by a cited source. It is not a complete list of the company’s facilities, and this page is not affiliated with or endorsed by Crusoe.