Data center moratorium tracker
Local and state pauses on new data center projects: 121 actions across 27 states, including 111 adoptions, extensions and statewide orders, plus rejections and one court reversal. Each entry links to the notice or report it came from, with a verbatim excerpt. This is a verified subset of the pauses that exist, not a complete census; the list is current through Oct 26, 2026, the newest action date recorded.
- Moratorium actions
- 121
- States
- 27
- Adopted, extended or announced
- 111
- Rejected, lifted or set aside
- 7
Every tracked moratorium
| Jurisdiction | Action | Length | What the source says |
|---|---|---|---|
| City of Charlotte North Carolina · city |
Extended Oct 26, 2026 |
11 months until Oct 18, 2027 |
Halts approval of new data center permits; existing permits are unaffected. The council voted unanimously on October 26, 2026 to extend the 150-day pause adopted June 8, 2026, which was due to end November 5, 2026. WFAESource excerpt“Charlotte City Council voted Monday night to extend its data center moratorium by 11 months.” |
| City of Memphis Tennessee · city |
Adopted Oct 20, 2026 |
135 days | Pause on new data centers while the council drafts land-use standards; a separate year-long proposal failed on a 6-6 tie. FOX13 MemphisSource excerpt“the council passed a plan giving a 135-day pause on new data centers.” |
| City of Hayward California · city |
Adopted Oct 20, 2026 |
up to two years | Moratorium on new data center proposals in the city. Local News MattersSource excerpt“The Hayward City Council voted unanimously Tuesday to approve a moratorium on new data center proposals.” |
| City of Cleveland Ohio · city |
Extended Oct 19, 2026 |
about 3 months until Jan 29, 2027 |
Freezes zoning permits and occupancy certificates for new standalone data centers and expansions of existing ones; operating facilities can stay open. Ends January 29, 2027, or earlier if council enacts permanent rules. Vote count not reported in the cited article. Baxtel (citing ideastream)Source excerpt“Cleveland has given itself until the end of January to produce an ordinance.” |
| Lexington-Fayette Urban County Government Kentucky · city |
Extended Oct 8, 2026 |
about 12 months until Oct 31, 2027 |
County-wide hold on data center permits, development plans and rezonings. Adopted June 9, 2026 with an initial end date of October 31, 2026; the Urban County Council voted 11-0 on October 8, 2026 to extend it. Second readings on removing data processing centers as a principal use in several zones were set for October 22, 2026. Lexington-Fayette Urban County GovernmentSource excerpt“pauses permits, development plans, and zone changes related to data centers in Fayette County” |
| City of Indio California · city |
Extended Oct 7, 2026 |
— until Oct 16, 2027 |
Second and final extension allowed under state law; the pause on applications to build, convert or expand data centers (including AI computing and crypto-mining sites) now runs to October 16, 2027 while the city drafts permanent rules. NBC Palm SpringsSource excerpt“stops the city from accepting or approving applications to build, convert or expand data centers” |
| City and County of San Francisco California · city |
Adopted Oct 6, 2026 |
45 days | Citywide pause on new data centers, effective immediately. Reporting says it can be extended up to 22 months if the Planning Department's study finds significant impacts, or lead to permanent controls. The San Francisco StandardSource excerpt“The San Francisco Board of Supervisors on Tuesday unanimously approved a 45-day moratorium on data centers” |
| City of Raleigh North Carolina · city |
Adopted Oct 6, 2026 |
6 months until Apr 6, 2027 |
Council voted 7-1 for a six-month pause: no new data center site application can be approved and no construction can begin while the city develops standards for larger data centers. Spectrum News 1Source excerpt“No construction can begin, and no site application can be approved, through April 6.” |
| Beaufort County North Carolina · county |
Adopted Oct 5, 2026 |
1 year | Commissioners voted 6-1 for a one-year pause: the county will not accept, process or approve applications for establishing, building, expanding or operating a data center while it studies impacts and drafts a permanent zoning ordinance. No data center is currently proposed in the county. WITNSource excerpt“voted 6-1 for a one-year moratorium on data center development.” |
| Mesa County Colorado · county |
Adopted Sep 30, 2026 |
12 months | Pauses acceptance, processing and approval of land-use applications for data centers in unincorporated Mesa County while the county rewrites its land development code. KJCT 8Source excerpt“The moratorium temporarily halts the acceptance, processing and approval of land-use applications for any data centers in unincorporated Mesa County.” |
| Pima County Arizona · county |
Adopted Sep 23, 2026 |
120 days | Bars new data center development in unincorporated Pima County for developers who have not yet submitted permit applications; the county says the existing Project Blue campus is exempt because it already holds county land and permits. AZ LuminariaSource excerpt“In a desert community already confronting drought and rising temperatures, we as a county have a public health responsibility to understand those impacts before we approve any projects that could place significant new demands on our resources and our infrastructure” |
| Marshall County Iowa · county |
Adopted Sep 23, 2026 |
six months until Mar 23, 2027 |
Moratorium on applications for data centers, AI computing facilities, data mining facilities and cryptocurrency mining operations in unincorporated Marshall County. Times RepublicanSource excerpt“The change gives the county more flexibility to work through the process of drafting regulations through the Zoning Commission.” |
| City of Woodbury Minnesota · city |
Adopted Sep 23, 2026 |
up to one year | Blocks permits for new data centers and for expansion of existing high-volume infrastructure beyond what is already approved, while the city spends up to a year reviewing effects on the water supply, power demand, noise and its zoning code. The city planner said Woodbury has no active applications or conversations with data center developers. Woodbury News NetSource excerpt“giving the city up to a year to study water use, electricity demand, noise and possible zoning changes” |
| Kershaw County South Carolina · county |
Adopted Sep 22, 2026 |
one year | Temporary moratorium on data centers, cryptocurrency mining operations and data processing facilities. South Carolina Public RadioSource excerpt“Council voted unanimously to pass the final reading of the ordinance Tuesday night, thus enacting the one-year pause.” |
| Baltimore County Maryland · county |
Extended Sep 22, 2026 |
about one additional year until Dec 31, 2027 |
Extends the county's data center permit moratorium, originally due to expire January 2027, through the end of 2027. WYPRSource excerpt“There are lawyers and developers that think it's the right way to go, but in terms of residents that we represent, I haven't spoken to one.” |
| Tulare County California · county |
Extended Sep 22, 2026 |
10 months and 15 days | Extends the county's moratorium on new data center development in unincorporated Tulare County, first adopted for 45 days on August 18, 2026, while the county drafts a permanent zoning ordinance; the board also separately adopted a letter opposing data center construction in the county, 3-2. Porterville RecorderSource excerpt“The Tulare County Board of Supervisors extended its moratorium on new data center development Tuesday, giving county officials an additional 10 months and 15 days to consider potential regulations as residents continue to push for a permanent ban.” |
| City of North Port Florida · city |
Adopted Sep 22, 2026 |
18 months | Retroactive moratorium on accepting and approving new data center applications, passed 3-2 after a pending roughly 900,000-square-foot data center application was excluded from the halt on staff review (though not final approval) after the city attorney warned excluding it entirely could expose the city to a lawsuit. WWSB ABC7 / MySuncoastSource excerpt“Including the project in the moratorium could expose North Port to a lawsuit. The company could argue it was denied legal rights granted under the application process.” |
| City of North Mankato Minnesota · city |
Adopted Sep 21, 2026 |
12 months | Moratorium on new data centers in the city; none may be built while it is in effect. Mankato Free PressSource excerpt“The ordinance will last for 12 months, during which no new data centers will be allowed to be constructed in the city.” |
| City of Salem Oregon · city |
Adopted Sep 21, 2026 |
120 days until Jan 19, 2027 |
Moratorium on new data center development while a city task force studies how to regulate data centers. KATU verrus-oakline-mill-creek-salem-or Source excerpt“Salem councilors gave final approval to a 120-day moratorium on data center development Monday night” |
| Texas Texas · state |
Adopted Sep 21, 2026 |
— | Gov. Greg Abbott ordered the Texas Commission on Environmental Quality to stop approving environmental permits for data centers until ERCOT and the Texas Water Development Board complete their audits, broadening his August 2026 moratorium on grid-connection approvals to cover environmental permitting. The Texas TribuneSource excerpt“Data centers must pay their own way, protect our grid and water and complete the ERCOT and TWDB audits.” |
| Town of Massena New York · town |
Rejected Sep 16, 2026 |
— | Town board voted 3-2 against a proposed six-month moratorium on data center development. WWNY 7 NewsSource excerpt“The Massena town board voted against a six-month moratorium on data center development, moving the town closer to construction of a data center. The town board rejected the moratorium in a 3-2 vote.” |
| Vance County North Carolina · county |
Adopted Sep 14, 2026 |
60 days until Nov 13, 2026 |
Moratorium on data center development, ending Nov. 13 or when the county amends the data center requirements in its zoning ordinance. WIZS natelli-vance-county-nc Source excerpt“The Vance County Board of Commissioners voted 5-2 to put a 60-day moratorium in place for data center development.” |
| City of Woodburn Oregon · city |
Adopted Sep 14, 2026 |
120 days | Pauses new data center development while the city weighs strain on the power grid, drinking water and sewer capacity, road traffic, first responders, backup generators, noise, jobs and the supply of industrial land. Woodburn IndependentSource excerpt“The impact of a data center may extend beyond the building itself, increasing demand on electric service, water and wastewater, roads, emergency response resources, generators, noise, employment, and industrial land supply.” |
| Lake County Illinois · county |
Adopted Sep 8, 2026 |
eight months | Data centers in unincorporated Lake County. Lake County, IllinoisSource excerpt“The Lake County Board today approved an eight-month moratorium on data centers in unincorporated Lake County” |
| Woodford County Kentucky · county |
Adopted Sep 8, 2026 |
permanent | Fiscal Court unanimously banned the construction of data centers, landfills and large battery storage systems in the county, becoming the first Kentucky county to permanently ban data centers; no specific developer proposal was pending at the time. The county seat, Versailles, had separately adopted a temporary moratorium in July 2026. WUKY / Kentucky LanternSource excerpt“Our rolling pastures, our historic farms, our agriculture, are not just scenic views. They are the backbone of our economy.” |
| McDowell County North Carolina · county |
Adopted reported Sep 3, 2026 |
six months | Six-month moratorium on data centers, approved unanimously after a public hearing. WCAB NewsSource excerpt“After the public hearing closed, commissioners voted unanimously for the six-month moratorium.” |
| City of Miamisburg Ohio · city |
Adopted Sep 1, 2026 |
nine months | Moratorium halting data center development within the city. City of Miamisburg, OHSource excerpt“Miamisburg City Council members voted unanimously, 6-0, to impose a nine-month moratorium on the development of data centers in the city.” |
| Mendocino County California · county |
Adopted Sep 1, 2026 |
45 days until Oct 16, 2026 |
Urgency ordinance that prohibits new data centers anywhere in the county's unincorporated area. The Mendocino VoiceSource excerpt“Mendocino County supervisors voted 5-0 Tuesday to adopt an urgency ordinance barring any new data center in the unincorporated county” |
| Loudoun County Virginia · county |
Vote to draft a pause Sep 2026 |
— | Supervisors voted 7-1-1 to have staff prepare a resolution pausing data center applications for 12 months. DatacenterDynamicsSource excerpt“The county board of supervisors this week voted 7-1 on a motion to pause data center applications for 12 months.” |
| Spartanburg County South Carolina · county |
Adopted Sep 2026 |
one year | One-year freeze on new data centers, plus strict conditions on any facility that tries to build in the county. FOX CarolinaSource excerpt“Spartanburg County Council voted 5-1 Monday night to approve a one-year freeze on new data centers, adding strict conditions for any facilities attempting to build in the county.” |
| Lawrence County Illinois · county |
Adopted Sep 2026 |
two years | Two-year moratorium on data centers. WZDM Wisdom 92.1Source excerpt“The Lawrence County, Illinois Board voted Thursday to approve an ordinance for a two-year moratorium on data centers.” |
| Village of Pioneer Ohio · village |
Adopted Sep 2026 |
six months | Six-month moratorium on all data centers, adopted 6-0 after a developer proposed a 20-megawatt data center at the AquaBounty property; council can end it early. The Bryan TimesSource excerpt“Less than a week after a developer spoke to the village planning commission about putting in a data center, village council put a moratorium on all data centers for six months.” |
| Pierce Township Ohio · township |
Extended Sep 2026 |
— until May 31, 2027 |
Trustees extended the township's zoning moratorium for data center uses to May 31, 2027 while the zoning commission reviews the zoning code; they also said they are not considering a data center at any site in the township. FOX19 (WXIX)Source excerpt“Pierce Township trustees rule out data center, extend zoning moratorium” |
| City of Mattoon Illinois · city |
Adopted Sep 2026 |
renewed each year | New data center developments larger than 21,780 square feet in the city and the area up to 1.5 miles outside it where the city has zoning authority. Existing businesses can keep operating. Stays in place until the council changes or ends it. The article is dated September 3, 2026 and says the vote was Tuesday night. City of MattoonSource excerpt“The moratorium applies to any new data center developments larger than 21,780 square feet” |
| Imperial County California · county |
Extended reported Aug 28, 2026 |
ten months and fifteen days | Temporary moratorium extended for an additional ten months and fifteen days. County of ImperialSource excerpt“the Board extended the temporary moratorium for an additional ten months and fifteen days” |
| Imperial County California · county |
Set aside by court reported Aug 28, 2026 |
— | The Imperial County Superior Court ruled that the moratorium's supporting findings did not adequately cover every applicable state-law requirement and ordered that the moratorium be set aside. County of ImperialSource excerpt“The Imperial County Superior Court recently ruled that the findings supporting the moratorium did not sufficiently address all applicable requirements under state law and directed that the moratorium be set aside.” |
| City of Elkhart Indiana · city |
Adopted Aug 27, 2026 |
— | Moratorium on data centers and battery storage facilities. WNDUSource excerpt“The Elkhart City Council passed a moratorium on data centers and battery storage facilities at a special hearing on Thursday, August 27.” |
| Town of Cary North Carolina · town |
Adopted Aug 27, 2026 |
18 months | Data center development in the town. WRALSource excerpt“Town council on Aug. 27 unanimously approved an 18-month pause on data center development.” |
| City of Indianapolis Indiana · city |
Adopted Aug 19, 2026 |
— until 2027 |
Pause on data center projects through 2027 (commission vote 6-0 on language drafted by the City-County Council). Axios IndianapolisSource excerpt“The commission voted 6-0 in favor of language drafted earlier this month by the City-County Council to pause data projects through 2027.” |
| Spokane County Washington · county |
Adopted Aug 18, 2026 |
4 months until Dec 15, 2026 |
Pauses the county's intake and review of building permit applications for data centers in unincorporated Spokane County while the Planning Commission works through a zoning text amendment on data center rules. Spokane County Board of County CommissionersSource excerpt“Today, the Board of County Commissioners unanimously approved a fourmonth pause on the acceptance and processing of County building permits for data centers.” |
| Town of Beloit Wisconsin · town |
Vote to draft a pause Aug 17, 2026 |
12 months | Supervisors voted 4-0 on a resolution starting the process for a 12-month moratorium; a public hearing and an ordinance were still to come. Beloit Daily NewsSource excerpt“calling for a 12-month moratorium on data center projects” |
| Metropolitan Government of Nashville and Davidson County Tennessee · city |
Adopted reported Aug 11, 2026 |
— until Dec 1, 2026 |
Moratorium until Dec. 1, created alongside new regulations for data centers. Axios Nashville DC BLOX Grassmere Park Source excerpt“council imposed a moratorium until Dec. 1 and created new regulations for data centers.” |
| Edgecombe County North Carolina · county |
Adopted Aug 3, 2026 |
two years | Data centers in the county. WRALSource excerpt“On Aug. 3, the Board of Commissioners reversed course, approving a two-year moratorium on data centers.” |
| Montgomery County Maryland · county |
Extended Aug 2026 |
18 months | Extension of the county's pause on data centers from six months to 18 months. Maryland MattersSource excerpt“The Montgomery County Council voted recently to extend its current six-month pause on data centers to 18 months.” |
| Gregg Township Pennsylvania · township |
Adopted Aug 2026 |
— | Temporary moratorium on applications for data centers; per the headline, PNK's pending project is still on the table. NorthcentralPA.com PNK Group data center Source excerpt“Supervisors approved a temporary moratorium on applications for data centers at their meeting Thursday” |
| Anderson County South Carolina · county |
Adopted Aug 2026 |
six months | Six-month moratorium on data centers (final reading, per the headline). FOX CarolinaSource excerpt“Anderson County Council passed a six-month moratorium on data centers Tuesday night.” |
| Durham County North Carolina · county |
Adopted Aug 2026 |
nine months | Nine-month moratorium on new large-scale data centers. WUNCSource excerpt“Durham County commissioners voted 4-1 Monday night to adopt a nine-month moratorium on new large-scale data centers.” |
| Mercer County Kentucky · county |
Adopted Aug 2026 |
one year | One-year moratorium on all applications to build new data centers in the county's unincorporated areas. Louisville Public MediaSource excerpt“The Mercer County Fiscal Court passed an ordinance by a unanimous vote that morning for a one-year moratorium on any application to construct a new data center in unincorporated areas of the county.” |
| Texas Texas · state |
Announced Aug 2026 |
— | Gov. Greg Abbott announced a moratorium on data center approvals until regulatory agencies can audit data center proposals that seek to connect to the state's electric grid. The Texas TribuneSource excerpt“Amid growing public backlash to the rapid buildout of data centers across Texas, Gov. Greg Abbott on Monday announced a moratorium on the approval of data centers until regulatory agencies can audit proposed data centers seeking connection to the state's electric grid.” |
| Madison County Florida · county |
Adopted Jul 22, 2026 |
— | Pauses the county's acceptance, review, processing and approval of applications tied to data center construction, expansion or operation in the unincorporated county. One local news report describes the pause as one year; the ordinance text was not reviewed. WWALS Watershed CoalitionSource excerpt“Madison County BOCC passed the datacenter moratorium 4:0.” |
| Nodaway County Missouri · county |
Adopted Jul 21, 2026 |
6 months | Unincorporated areas of the county; bars building or operating data centers and supporting facilities such as substations, backup generators and water systems. KXCVSource excerpt“unanimously approve a six-month moratorium on building data centers” |
| Augusta-Richmond County Georgia · county |
Extension recommended reported Jul 20, 2026 |
— | The Augusta Planning Commission recommended a 60-day extension of the moratorium; WRDW reported on July 20, 2026 that commissioners had been unable to reach agreement at their last meeting. WRDWSource excerpt“The Augusta Planning Commission recommended extending the moratorium by 60 more days.” |
| Town of Brookhaven New York · town |
Adopted Jul 17, 2026 |
18 months until Jan 2028 |
Halts approval of new data centers town-wide while the Department of Planning, Environment and Land Management drafts zoning rules defining data center use, which is currently undefined in the town code. Adopted unanimously after a public hearing that ran nearly six hours. Fire Island NewsSource excerpt“ran nearly six hours” |
| City of Cleveland Ohio · city |
Adopted Jul 15, 2026 |
3 months | Pause on data centers in Cleveland while a working group develops recommendations. City Council vote was 14-1. Cleveland 19 NewsSource excerpt“Cleveland City Council approved a moratorium on data centers by a 14-to-1 vote Wednesday night.” |
| New York New York · state |
Adopted Jul 14, 2026 |
until the state completes a Generic Environmental Impact Statement | Executive Order No. 62 directs the Department of Environmental Conservation to hold in abeyance discretionary permits, approvals and licenses for construction or expansion of data centers that consume or can consume 50 MW or more, where the application was not complete before the order took effect. It reaches state DEC approvals, not local permits, and exempts facilities primarily used for manufacturing, research (including quantum and biomedical), education (including the Empire AI consortium) or medical care. Office of the Governor of New YorkSource excerpt“is not covered by this definition and thus not subject to this Executive Order” |
| Frederick County Maryland · county |
Adopted Jul 1, 2026 |
— until Dec 31, 2026 |
Order signed July 1 by County Executive Jessica Fitzwater halting new data center permitting or approvals for the rest of the year. Maryland MattersSource excerpt“County Executive Jessica Fitzwater signed an order July 1, pausing new data center permitting or approvals until the end of the year.” |
| Prince George's County Maryland · county |
Adopted Jul 2026 |
two years | Hyperscale data center development. WTOPSource excerpt“The Prince George's County Council passed a two-year moratorium on hyperscale data center development to give members more time to consider how the county will go about it in the future.” |
| Paulding County Georgia · county |
Adopted Jul 2026 |
— until Jan 1, 2027 |
Moratorium in effect until January 1, 2027. FOX 5 AtlantaSource excerpt“During Tuesday's board of commissioners meeting, commissioners unanimously approved the moratorium, which will be in effect until January 1, 2027.” |
| Village of Wrightstown Wisconsin · village |
Adopted Jul 2026 |
one year | Moratorium on data center projects in the village. NBC 26Source excerpt“The Village of Wrightstown passed a one-year moratorium on data center projects Tuesday night” |
| Greenwood County South Carolina · county |
Adopted Jul 2026 |
one year | One-year moratorium on data centers; 4-3 vote on third and final reading. FOX CarolinaSource excerpt“Councilmembers voted 4-3 on Tuesday on the third and final reading of the ordinance.” |
| Town of East Fishkill New York · town |
Adopted Jun 26, 2026 |
3 years until Jul 1, 2029 |
Blocks all data centers except those ancillary to an existing or permitted use and under 20 MW, or eligible for an Economic Development Special Permit. Passed unanimously; no data center application had ever been filed with the town. DatacenterDynamicsSource excerpt“ancillary to an existing or permitted use and less than 20MW or eligible for an Economic Development Special Permit” |
| Elmwood Township Michigan · township |
Adopted Jun 17, 2026 |
12 months | Data centers and cryptocurrency mining facilities (Resolution No. 2026.06.17.A). Tuscola TodaySource excerpt“Resolution No. 2026.06.17.A, imposing a 12-month temporary moratorium on data centers and cryptocurrency mining facilities.” |
| Coweta County Georgia · county |
Adopted Jun 16, 2026 |
180 days until Dec 23, 2026 |
Moratorium on accepting applications for permits, land use amendments, rezonings, conditional uses and variances, and on public hearings related to data centers, while the county reviews its data center ordinance; set to expire Dec. 23 or when the board adopts an ordinance amendment. The Newnan Times-HeraldSource excerpt“The Coweta County Board of Commissioners approved a 180-day data center moratorium to review the county's data center ordinance at its Tuesday night meeting.” |
| Cumberland County North Carolina · county |
Adopted Jun 15, 2026 |
six months until Dec 2026 |
Data centers in the county. WRALSource excerpt“Commissioners adopted a six-month data center moratorium on June 15, which will expire in December.” |
| Elbert County Georgia · county |
Adopted reported Jun 10, 2026 |
six months | Six-month moratorium on data center facilities approved by the Elbert County Board of Commissioners. The Elberton StarSource excerpt“Elbert County's Board of Commissioners (BOC) pumped the brakes on any future data center construction in Elbert County by approving a six-month moratorium on data center facilities.” |
| City of Seattle Washington · city |
Adopted Jun 9, 2026 |
one year | One-year emergency moratorium on applications for new data centers with more than 20 megavolt-amperes of electrical capacity; per GeekWire, the roughly 30 smaller data centers already operating in the city are exempt and may each expand by up to another 20 megavolt-amperes. GeekWire reported that it would take effect once Mayor Katie Wilson signs it. GeekWireSource excerpt“The Seattle City Council voted unanimously Tuesday to impose a one-year emergency moratorium on new large data centers inside the city limits, responding to concerns about the implications of AI for the city's power grid, water supply, utility rates, and economy.” |
| City of Indio California · city |
Adopted Jun 3, 2026 |
45 days | Urgency ordinance pausing applications for data center development citywide. NBC Palm SpringsSource excerpt“imposing a 45-day citywide moratorium on data center development applications” |
| Augusta-Richmond County Georgia · county |
Adopted Jun 2, 2026 |
49 days | Pause on new data centers to allow public input; WRDW reported that it does not apply to the QTS campus on Gordon Highway. WRDWSource excerpt“The Augusta Commission on Tuesday imposed a 49-day pause on new data centers, but it doesn't apply to the one that's stirring up controversy.” |
| St. Lawrence County New York · county |
Rejected Jun 1, 2026 |
— | The county did not adopt a moratorium. It passed a resolution affirming local authority over data center siting and urged its municipalities to consider moratoriums of their own. Rockefeller Institute of GovernmentSource excerpt“passed a resolution affirming local authority” |
| Carroll County Georgia · county |
Extended Jun 2026 |
100 days | Data center moratorium for unincorporated areas of the county, extended another 100 days. Times-GeorgianSource excerpt“The Carroll County Board of Commissioners on Tuesday voted to extend for another 100 days a data center moratorium for unincorporated areas of the county.” |
| Imperial County California · county |
Adopted Jun 2026 |
45 days | Temporary moratorium on data centers in the county. County of ImperialSource excerpt“In June 2026, the Imperial County Board of Supervisors adopted a 45-day temporary moratorium” |
| Box Elder County Utah · county |
Adopted Jun 2026 |
180 days | New data centers, plus power plants serving data centers, on the county's unincorporated land. Utah Public RadioSource excerpt“The commissioners unanimously passed an ordinance Wednesday that imposes a 180-day moratorium on new data centers and data center power plants on unincorporated land in Box Elder County.” |
| Butler County Ohio · county |
Adopted Jun 2026 |
six months | Six-month moratorium on data centers. WVXUSource excerpt“voted unanimously Tuesday to approve a six-month moratorium on data centers.” |
| City of Minneapolis Minnesota · city |
Adopted Jun 2026 |
five months | Pause on new data center development. CBS MinnesotaSource excerpt“Minneapolis City Council members approved a five-month pause on new data center development Thursday.” |
| City of Inver Grove Heights Minnesota · city |
Adopted Jun 2026 |
one year | New data center development within the city (interim ordinance). Limitless NewsSource excerpt“The Inver Grove Heights City Council voted 3-2 Friday to approve the third and final reading of a one-year interim ordinance establishing a moratorium on new data center development within the city.” |
| Dane County Wisconsin · county |
Adopted Jun 2026 |
— until Dec 2027 |
Pause until December 2027 on hyperscale data center applications for zoning permits. IsthmusSource excerpt“The Dane County Board unanimously approved a data center moratorium Thursday, pausing zoning permit applications for hyperscale data centers until December 2027.” |
| City of Charlotte North Carolina · city |
Adopted Jun 2026 |
150 days | Moratorium on data center construction (150 days, per the headline). Axios CharlotteSource excerpt“Charlotte City Council unanimously voted to enact the moratorium Monday night.” |
| Montgomery Township Ohio · township |
Adopted Jun 2026 |
two years | Two-year moratorium on building data centers in the township (per Ashland Source). Ashland SourceSource excerpt“The three-member board unanimously approved a two-year moratorium on the construction of data centers within Montgomery Township.” |
| DeKalb County Georgia · county |
Extended Jun 2026 |
100 days | New data center applications; extension keeps the pause in place through the end of September. CBS News AtlantaSource excerpt“DeKalb County commissioners have approved a 100-day extension of a moratorium on new data center applications, keeping the pause in place through the end of September.” |
| Jackson County Missouri · county |
Adopted Jun 2026 |
180 days | Six-month moratorium on data center applications (per the headline); passed with eight votes in favor and one excused. KCTV5Source excerpt“The legislature passed it on Monday with eight votes in favor and one excused.” |
| Logan County Illinois · county |
Adopted May 19, 2026 |
— | Moratorium approved 6-4 on May 19; per the headline, it was later declared invalid. Illinois TimesSource excerpt“Logan County Board members on May 19 voted 6-4 in favor of the moratorium” |
| Town of Lysander New York · town |
Adopted May 7, 2026 |
6 months | Pause on new data center applications adopted after a 124-acre site near Hencle Boulevard was marketed as a 300 MW data center site. More than 350 residents attended the meeting to oppose the project. Rockefeller Institute of GovernmentSource excerpt“more than 350 residents attended” |
| City of Durham North Carolina · city |
Adopted May 4, 2026 |
60 days | Data center planning and development. WRALSource excerpt“On May 4, city council members passed a 60-day moratorium on data center planning and development.” |
| Harnett County North Carolina · county |
Adopted May 4, 2026 |
12 months | Data centers in the county. WRALSource excerpt“The Board of Commissioners voted on May 4 to adopt a 12-month data center moratorium.” |
| Citrus County Florida · county |
Adopted May 1, 2026 |
one year | New data centers. Spectrum NewsSource excerpt“Despite the county enacting a one-year moratorium on new data centers on May 1, discussions are continuing on a data center proposal in Lecanto, which was initiated before the pause was instituted.” |
| Maine Maine · state |
Rejected Apr 29, 2026 |
— | The House voted 72-65 to override the veto of L.D. 307, short of the two-thirds needed, so the veto stands. Maine Morning StarSource excerpt“After Mills vetoed the bill Friday, the House of Representatives took up the legislation again, voting 72-65 on the bill, failing to secure two-thirds of lawmaker support needed to override the governor's action.” |
| Maine Maine · state |
Rejected Apr 24, 2026 |
— | Gov. Janet Mills vetoed L.D. 307, which would have created a Maine Data Center Coordination Council and placed a temporary limit on certain large data centers; she said she supports a temporary moratorium and would have signed the bill if it had exempted a project at the former Androscoggin Mill in Jay. Office of Governor Janet T. MillsSource excerpt“Governor Janet Mills today notified the Maine Legislature that she has vetoed L.D. 307, An Act to Establish the Maine Data Center Coordination Council and Place a Temporary Limitation on Certain Data Centers.” |
| Orange County North Carolina · county |
Adopted Apr 21, 2026 |
one year | Data center construction across the county. WRALSource excerpt“Commissioners voted unanimously on April 21 to establish a one-year pause on data center construction across the county.” |
| Providence Township Ohio · township |
Adopted Apr 15, 2026 |
12 months | Moratorium on the construction of data centers, using Waterville Township's moratorium language. Toledo Free PressSource excerpt“Before unanimously passing a 12-month moratorium on the construction of data centers, Providence Township trustees had little discussion – but several residents shared their thoughts prior to the April 15 vote.” |
| Town of Apex North Carolina · town |
Adopted Apr 2026 |
one year until Apr 27, 2027 |
Review or approval of applications for data centers (and associated uses like cryptocurrency mining) until April 27, 2027. INDY WeekSource excerpt“The moratorium prevents Apex from reviewing or approving applications for the development of data centers (along with associated uses like cryptocurrency mining) until April 27, 2027.” |
| Manitowoc County Wisconsin · county |
Adopted Apr 2026 |
18 months | Moratorium on data center permitting. WPRSource excerpt“the Manitowoc County Board unanimously approved an 18-month moratorium on data center permitting Tuesday night.” |
| Oklahoma City Oklahoma · city |
Adopted Apr 2026 |
— until Dec 31, 2026 |
Takes effect immediately and remains until Dec. 31, 2026, or earlier if zoning code amendments on data centers are approved. City of Oklahoma CitySource excerpt“The moratorium takes effect immediately and will remain in place until either December 31, 2026, or earlier if amendments to the City's Zoning Code regarding data centers are approved by City Council.” |
| City of Wixom Michigan · city |
Adopted Mar 24, 2026 |
six months | Resolution imposing a temporary moratorium on establishing, permitting, considering, approving, locating, constructing or installing any data centers in the city. City of WixomSource excerpt“On March 24, 2026, City Council approved a Resolution Imposing a Temporary Moratorium for a period of six (6) months on the establishing, permitting, consideration, approval, location, construction, and/or installation of any data centers in the City of Wixom.” |
| Henry Township Ohio · township |
Adopted reported Mar 13, 2026 |
— | Temporary moratorium on data centers, per the township fiscal officer. BG Independent NewsSource excerpt“Henry Township fiscal officer Matt Davis said his township adopted a moratorium.” |
| Weston Township Ohio · township |
Adopted reported Mar 13, 2026 |
— | Temporary moratorium on data centers, per a township trustee. BG Independent NewsSource excerpt“Weston Township Trustee Randy Tolles said his township also adopted a moratorium.” |
| Lyon Township Michigan · township |
Adopted Mar 2, 2026 |
— until Sep 8, 2026 |
Moratorium on the issuance of approvals and permits for data processing centers, retitled at adoption to add large land users; the adopting motion ran it through Sept. 8, 2026. Charter Township of LyonSource excerpt“extend the moratorium through September 8, 2026” |
| Carroll County Georgia · county |
Adopted Mar 2026 |
100 days | Permits related to data centers and other new technology. Times-GeorgianSource excerpt“The commissioners initially approved a 100-day moratorium on permits related to data centers and other new technology at the board's March 3 meeting.” |
| Fulton County Indiana · county |
Adopted Mar 2026 |
one year | Data center construction in the county, effective immediately. WNDUSource excerpt“Fulton County commissioners voted 2-1 on Monday night to approve a one-year moratorium on data center construction, effective immediately.” |
| Lake Township Ohio · township |
Adopted Mar 2026 |
one year | One-year moratorium, said to have been adopted in response to word that a possible data center site in the township was for sale. BG Independent NewsSource excerpt“Earlier this week, Lake Township officials adopted "a one-year moratorium," reportedly in response to information about a potential data center site for sale in the township.” |
| Plain Township Ohio · township |
Adopted Mar 2026 |
— | Temporary moratorium on data centers; a trustee said the township acted after residents voiced concerns the previous month. BG Independent NewsSource excerpt“Also this week, Plain and Portage townships adopted moratoriums.” |
| Portage Township Ohio · township |
Adopted Mar 2026 |
— | Temporary moratorium on data centers; a trustee said the township had been approached about a possible site for a data center or wind farm. BG Independent NewsSource excerpt“Also this week, Plain and Portage townships adopted moratoriums.” |
| Big Rapids Charter Township Michigan · township |
Adopted Feb 23, 2026 |
one year | Temporary moratorium on the permitting, approval, construction and installation of all data centers in the township, subject to extensions by resolution of six months or less, or until the township adopts data center regulations. Big Rapids Charter TownshipSource excerpt“The Township enacts a temporary moratorium on the permitting, consideration, approval, location, erection, construction, review, and/or installation of all Data Centers in the Township for one year, subject to six month or less extensions by resolution” |
| Monclova Township Ohio · township |
Adopted Feb 17, 2026 |
12 months | Resolution 02172026-01, adopted 3-0, temporarily bars approving, establishing or constructing any data center in the township. Monclova TownshipSource excerpt“Laux moved to approve Resolution 02172026-01, Imposing Temporary Moratorium on the Approval, Establishment, or Construction of any Data Center Within Monclova Township for a Period of 12 Months.” |
| Baltimore County Maryland · county |
Adopted Feb 3, 2026 |
one year until Jan 1, 2027 |
Blocks the county from issuing data center permits while the Planning Board studies environmental and economic impacts; triggered by a proposal to convert a vacant Social Security Administration building in Woodlawn into a data center. The Baltimore BannerSource excerpt“A year and a half ago, when someone said data center, what we thought in our minds did not include what we found out now: the impact on infrastructure, the impact on water, the impact on power.” |
| Lenox Township Michigan · township |
Adopted Feb 2, 2026 |
four months | Moratorium on new data center development, effective Feb. 2, 2026, with the option of one additional four-month extension. Charter Township of LenoxSource excerpt“The Township adopted a four-month moratorium, with the option for one additional four-month extension if necessary.” |
| Hood County Texas · county |
Rejected Feb 2026 |
six months | Proposed six-month moratorium covering new industrial permits, such as those for data centers and factories. KERA NewsSource excerpt“the six-month moratorium on new industrial permits, including data centers and factories, 3-2” |
| Hood County Texas · county |
Rejected Feb 2026 |
— | Proposal would have paused new large-scale development for a time so county leaders could study impacts on water, infrastructure and public health; per the headline, the county instead sought an attorney general's opinion on its authority. KERA NewsSource excerpt“temporarily halted new large-scale development while county leaders studied potential impacts on water, infrastructure and public health” |
| Solon Township Michigan · township |
Adopted Feb 2026 |
six months | Acceptance of any data center proposals by the township. FOX 17Source excerpt“prevent the township from accepting any data center proposals during that period” |
| Dearborn County Indiana · county |
Adopted Feb 2026 |
— | Processing of rezoning requests for data centers, commercial solar and battery storage facilities. WVXUSource excerpt“The Dearborn County Board of Commissioners voted Tuesday to approve a moratorium on the processing of rezoning applications for commercial solar, battery storage facilities and data centers.” |
| Freedom Township Ohio · township |
Adopted Jan 2026 |
— | Temporary moratorium on data centers; the township fiscal officer said trustees wanted time to research data center impacts and gather resident input. BG Independent NewsSource excerpt“Freedom Township officials adopted a moratorium in January.” |
| Town of Oneonta New York · town |
Adopted 2026 |
1 year | Twelve-month pause on data center construction, introduced in March 2026 after Eco-Yotta Inc. sought to rezone about 150 acres of farmland on County Road 9, with a public hearing on April 8, 2026. WBNGSource excerpt“12 months on construction of data centers” |
| Waterville Township Ohio · township |
Adopted Dec 17, 2025 |
12 months | Moratorium on issuing permits for data centers. Toledo Free PressSource excerpt“Citing concerns about the drain on the electrical grid and water supply, as well as the impact on quality of life, Waterville Township trustees voted unanimously on Dec. 17 to impose a 12-month moratorium on issuing permits for data centers.” |
| City of Waterville Ohio · city |
Adopted Dec 8, 2025 |
six months | Six-month moratorium on data centers, amended down from an originally proposed 12 months as a compromise. 13abc (WTVG)Source excerpt“Council members approved the amended measure in a unanimous vote on Dec. 8.” |
| Springfield Township (Oakland County) Michigan · township |
Adopted Dec 2025 |
180 days | Data center plans may not be accepted for review, considered, approved or otherwise allowed. GovTech (The Detroit News)Source excerpt“The Springfield Township Board of Trustees last month approved a 180-day moratorium that prohibits data center plans from being 'accepted for review, considered, approved, or otherwise allowed' during its duration.” |
| Howell Township Michigan · township |
Adopted Nov 2025 |
six months | Establishment and use of data centers. WHMISource excerpt“The Howell Township Board unanimously enacted six-month moratorium on the establishment and use of data centers” |
| Clayton County Georgia · county |
Adopted Sep 3, 2025 |
120 days until Dec 31, 2025 |
Moratorium on data centers until Dec. 31, 2025. Georgia Public BroadcastingSource excerpt“On Sept. 3, the Clayton County Board of Commissioners voted to impose a 120-day moratorium on data centers until Dec. 31.” |
| City of St. Charles Missouri · city |
Adopted Aug 2025 |
one year | Applications for new or expanded data centers. Spectrum NewsSource excerpt“During a special meeting Friday, the St. Charles City Council voted to implement a one-year moratorium on applications for new or expanded data centers.” |
| Oldham County Kentucky · county |
Adopted Jul 2025 |
150 days | Puts a 150-day hold on any application to construct a data center in the county. Louisville Public MediaSource excerpt“pauses any application to build a data center in the county for 150 days” |
| Town of Perth New York · town |
Adopted Jun 4, 2025 |
1 year | One-year pause adopted by the town board, with the supervisor citing concerns over energy usage. Rockefeller Institute of GovernmentSource excerpt“concerns over energy usage” |
| Coweta County Georgia · county |
Adopted May 2025 |
180 days | Moratorium adopted to evaluate the county's data center policies and zoning codes. The Atlanta Journal-ConstitutionSource excerpt“The Coweta County Board of Commissioners unanimously adopted a 180-day moratorium to evaluate its data center policies and zoning codes.” |
| Douglas County Georgia · county |
Adopted Mar 2025 |
90 days | 90-day moratorium on data centers. GovTech (The Atlanta Journal-Constitution)Source excerpt“A similar 90-day moratorium was adopted by Douglas County in March” |
Dates are the date of the vote or order where the source gives one; otherwise the entry shows when it was reported. Lengths, end dates and scope are shown only where the cited source states them. Expand any row for a verbatim excerpt from its source.
Moratorium actions by state
| State | Actions | Jurisdictions |
|---|---|---|
| Ohio | 17 | City of Cleveland · City of Miamisburg · Village of Pioneer · Pierce Township · City of Cleveland · Butler County · Montgomery Township · Providence Township · Henry Township · Weston Township · Lake Township · Plain Township · Portage Township · Monclova Township · Freedom Township · Waterville Township · City of Waterville |
| North Carolina | 14 | City of Charlotte · City of Raleigh · Beaufort County · Vance County · McDowell County · Town of Cary · Edgecombe County · Durham County · Cumberland County · City of Charlotte · City of Durham · Harnett County · Orange County · Town of Apex |
| Georgia | 11 | Augusta-Richmond County · Paulding County · Coweta County · Elbert County · Augusta-Richmond County · Carroll County · DeKalb County · Carroll County · Clayton County · Coweta County · Douglas County |
| California | 9 | City of Hayward · City of Indio · City and County of San Francisco · Tulare County · Mendocino County · Imperial County · Imperial County · City of Indio · Imperial County |
| Michigan | 8 | Elmwood Township · City of Wixom · Lyon Township · Big Rapids Charter Township · Lenox Township · Solon Township · Springfield Township (Oakland County) · Howell Township |
| New York | 8 | Town of Massena · Town of Brookhaven · New York · Town of East Fishkill · St. Lawrence County · Town of Lysander · Town of Oneonta · Town of Perth |
| Maryland | 5 | Baltimore County · Montgomery County · Frederick County · Prince George's County · Baltimore County |
| Illinois | 4 | Lake County · Lawrence County · City of Mattoon · Logan County |
| Indiana | 4 | City of Elkhart · City of Indianapolis · Fulton County · Dearborn County |
| Kentucky | 4 | Lexington-Fayette Urban County Government · Woodford County · Mercer County · Oldham County |
| Minnesota | 4 | City of Woodbury · City of North Mankato · City of Minneapolis · City of Inver Grove Heights |
| South Carolina | 4 | Kershaw County · Spartanburg County · Anderson County · Greenwood County |
| Texas | 4 | Texas · Texas · Hood County · Hood County |
| Wisconsin | 4 | Town of Beloit · Village of Wrightstown · Dane County · Manitowoc County |
| Florida | 3 | City of North Port · Madison County · Citrus County |
| Missouri | 3 | Nodaway County · Jackson County · City of St. Charles |
| Maine | 2 | Maine · Maine |
| Oregon | 2 | City of Salem · City of Woodburn |
| Tennessee | 2 | City of Memphis · Metropolitan Government of Nashville and Davidson County |
| Washington | 2 | Spokane County · City of Seattle |
| Arizona | 1 | Pima County |
| Colorado | 1 | Mesa County |
| Iowa | 1 | Marshall County |
| Oklahoma | 1 | Oklahoma City |
| Pennsylvania | 1 | Gregg Township |
| Utah | 1 | Box Elder County |
| Virginia | 1 | Loudoun County |
Moratorium actions tied to tracked projects
| Date | Action | Project |
|---|---|---|
| Sep 21, 2026 | Salem City Council adopts a 120-day moratorium on new data center projects, with the option to extend it by six months Salem Reporter | Oakline at Mill Creek Salem, OR |
| Sep 16, 2026 | Massena Town Board votes 3-2 against a proposed six-month moratorium on data center development WWNY 7 News | North Country Colocation Services Massena Expansion Massena, St. Lawrence County, NY |
| Sep 15, 2026 | The Augusta Commission approves rules governing new data centers, 6-5, ending the city’s almost three-month moratorium The Augusta Press | QTS Augusta Data Center Campus Augusta, Augusta-Richmond County, GA |
| Sep 14, 2026 | Statesville City Council unanimously approves a 180-day moratorium on new data centers in the city; WBTV reports it will not affect previously approved data centers WBTV | Compass Statesville Statesville, Iredell County, NC |
| Sep 14, 2026 | Vance County Board of Commissioners votes 5-2 to adopt a 60-day moratorium on data center development after two public hearings WIZS | Natelli data center, U.S. 158 Vance County, NC |
| Sep 14, 2026 | County Council unanimously adopts Digital Infrastructure Overlay District, partially repealing the moratorium Live 5 News (WCSC) | Project Boulder Walterboro, Colleton County, SC |
| Aug 28, 2026 | County says Superior Court found moratorium findings insufficient and ordered it withdrawn County of Imperial | Imperial Data Center Imperial, Imperial County, CA |
| Aug 27, 2026 | Palm Beach County commissioners vote 7-0 on first reading for a one-year moratorium on large-scale data centers (an anticipated monthly peak load of 50 megawatts or more), with a final vote set for Sept. 24 NewsRadio WIOD | Project Tango Loxahatchee, Palm Beach County, FL |
| Aug 17, 2026 | Town of Beloit board votes 4-0 on a resolution calling for a 12-month data center moratorium; a public hearing and an ordinance are still required Beloit Daily News | Project Cornmaze Beloit, Rock County, WI |
| Aug 11, 2026 | DC BLOX sues Metro in U.S. District Court for the Middle District of Tennessee over the moratorium Axios Nashville | DC BLOX Nashville Data Center Nashville, Davidson County, TN |
| Aug 10, 2026 | Plan Commission holds a major public hearing on the PNK proposal and votes 6-0 to begin drafting a 12-month data center moratorium that would not apply to this project WAOW | PNK Group Wisconsin Rapids Data Center Wisconsin Rapids, Wood County, WI |
| Aug 7, 2026 | BLE Landholdings withdraws its rezoning application at the City of Pacific level, days after Pacific's mayor signs a one-year moratorium on new data-center applications; officials note the site sits in unincorporated Franklin County, where a separate county rezoning case remains open Yahoo News (KSDK) | Meramec Valley Technology Park Pacific, Franklin County, MO |
| Aug 3, 2026 | Salem City Council unanimously votes to advance a data center development moratorium, with a Verrus application pending KATU | Oakline at Mill Creek Salem, OR |
| Jul 31, 2026 | Town of Beloit supervisors reject the cost reimbursement agreement with Panattoni and begin the process toward a 12-month data center moratorium, two days after the Town of Turtle took similar steps Beloit Daily News | Project Cornmaze Beloit, Rock County, WI |
| Jul 21, 2026 | Metro Council approves data center regulations and a moratorium on new permits through Dec. 1, 2026 NewsChannel 5 | DC BLOX Nashville Data Center Nashville, Davidson County, TN |
| Jul 17, 2026 | Brookhaven Town Board votes unanimously for an 18-month moratorium on data centers, running to early 2028 while the town writes zoning rules defining data center use News 12 Long Island | WF Industrial Yaphank Data Center Yaphank, Suffolk County, NY |
| Jul 16, 2026 | Brookhaven Town Board public hearing on the moratorium runs nearly six hours, with about 300 attending and some 60 speaking against data centers Fire Island News | WF Industrial Yaphank Data Center Yaphank, Suffolk County, NY |
| Jul 14, 2026 | Gov. Kathy Hochul signs executive order enacting a statewide moratorium on large-scale data centers, pausing permitting for up to a year The Batavian | Stream Data Centers STAMP Campus Alabama, Genesee County, NY |
| Jul 2026 | County Council approves a two-year moratorium on data center permitting and development The Diamondback | Brightseat Tech Park Landover, Prince George's County, MD |
| Jul 2026 | Palo passes a data center ordinance; Linn County, which recently began an 18-month data center moratorium, considers allowing data centers as accessories to nuclear plants Iowa Public Radio | Google Palo data center campus Palo, Linn County, IA |
| Jul 2026 | Moratorium extended ten months and fifteen days County of Imperial | Imperial Data Center Imperial, Imperial County, CA |
| Jul 2026 | County adopts six-month moratorium on data center development Live 5 News (WCSC) | Project Boulder Walterboro, Colleton County, SC |
| Jun 26, 2026 | East Fishkill Town Board unanimously passes a three-year data center moratorium running through July 1, 2029 DatacenterDynamics | Treetop East Fishkill Data Center East Fishkill, Dutchess County, NY |
| Jun 25, 2026 | The town moves toward a moratorium as developers float the possibility of a project News 12 Hudson Valley | Treetop East Fishkill Data Center East Fishkill, Dutchess County, NY |
| Jun 25, 2026 | The proposal draws opposition from residents and from Town Supervisor Dan Panico, who proposes an 18-month moratorium and says he has support from other Suffolk town supervisors News 12 Long Island | WF Industrial Yaphank Data Center Yaphank, Suffolk County, NY |
| Jun 18, 2026 | State's Attorney Bradley Hauge advises County Board members that proper procedures were not followed for the moratorium to be legally binding Illinois Times | Logan Prairie Data Center Latham, Logan County, IL |
| Jun 2, 2026 | Carroll County commissioners extend the moratorium another 100 days, 7-0 Times-Georgian | Avemore Data Park Villa Rica, Carroll County, GA |
| Jun 2026 | Butler County enacts a six-month data center moratorium covering Madison and five other townships WVXU | Amazon Web Services data center campus, Madison and St. Clair townships Butler County, OH |
| Jun 2026 | Board of Supervisors adopts 45-day data center moratorium; developer sues IID for water access County of Imperial | Imperial Data Center Imperial, Imperial County, CA |
| May 19, 2026 | Logan County Board votes 6-4 for a 12-month data center moratorium Illinois Times | Logan Prairie Data Center Latham, Logan County, IL |
| May 7, 2026 | Lysander Town Board adopts a six-month moratorium at a meeting more than 350 residents attend to oppose the project Rockefeller Institute of Government | Ranalli Lysander Data Center Lysander, Onondaga County, NY |
| May 1, 2026 | Citrus County enacts a one-year moratorium on new data centers; the pre-moratorium proposal remains under discussion Spectrum News | Holder Industrial Park Holder, Citrus County, FL |
| May 2026 | St. Clair Township enacts a 12-month moratorium on data centers WVXU | Amazon Web Services data center campus, Madison and St. Clair townships Butler County, OH |
| Apr 21, 2026 | Rosemount City Council unanimously adopts a one-year moratorium covering new data center developments Sun ThisWeek (hometownsource.com) | Meta Rosemount Data Center Rosemount, Dakota County, MN |
| Apr 21, 2026 | Township board unanimously approves first reading of a six-month moratorium on data center uses Frenchtown Charter Township | Project Cherry Blossom Frenchtown Township, Monroe County, MI |
| Apr 16, 2026 | Lysander Town Board work session and regular meeting; the board votes 4-0 to start drafting a data center moratorium after a petition passes 1,600 signatures Baldwinsville Messenger / Eagle News Online | Ranalli Lysander Data Center Lysander, Onondaga County, NY |
| Apr 8, 2026 | Public hearing on the moratorium; residents voice support for it WBNG | Eco-Yotta Oneonta Data Center Oneonta, Otsego County, NY |
| Apr 1, 2026 | Planning Commission holds public hearing on the proposed moratorium Frenchtown Charter Township | Project Cherry Blossom Frenchtown Township, Monroe County, MI |
| Apr 2026 | County Board does not extend the moratorium and sends the issue back to the zoning board pending a data center ordinance FOX Illinois | Logan Prairie Data Center Latham, Logan County, IL |
| Apr 2026 | Apex Town Council unanimously passes a 12-month moratorium on data centers INDY Week | New Hill Digital Campus Apex, Wake County, NC |
| Mar 25, 2026 | Planning Commission reworking regulations; moratorium remains in effect WAVE / WDRB | Project Lincoln Oldham County, KY |
| Mar 12, 2026 | Oneonta Town Board introduces a 12-month moratorium on data center construction and schedules a public hearing WBNG | Eco-Yotta Oneonta Data Center Oneonta, Otsego County, NY |
| Mar 10, 2026 | Township board approves a draft data center moratorium Planet Detroit | Project Cherry Blossom Frenchtown Township, Monroe County, MI |
| Mar 3, 2026 | Carroll County Board of Commissioners approves a 100-day moratorium on data center permits in unincorporated areas, 7-0 Times-Georgian | Avemore Data Park Villa Rica, Carroll County, GA |
| Mar 2026 | Township board adopts six-month moratorium on additional data center proposals WDIV ClickOnDetroit | Project Flex New Hudson, Oakland County, MI |
| Feb 24, 2026 | Logan County Board approves a 60-day data center moratorium Illinois Times | Logan Prairie Data Center Latham, Logan County, IL |
| Feb 23, 2026 | Senate Majority Leader Chase Blasi asks county for a three-year moratorium KWCH | West Sedgwick County data center land acquisitions Sedgwick County, KS |
| Feb 10, 2026 | Commissioners reject six-month moratorium 3-2 KERA News | Comanche Circle Tolar, Hood County, TX |
| Feb 2026 | Commissioners reject second moratorium 3-2 and seek Attorney General opinion on authority KERA News | Comanche Circle Tolar, Hood County, TX |
| Feb 2026 | Township Board unanimously approves a six-month moratorium on data center proposals FOX 17 West Michigan | Project Peninsula Cedar Springs, Kent County, MI |
| Jan 2026 | Township Planning Commission unanimously approves a 90-day moratorium on data center proposals FOX 17 West Michigan | Project Peninsula Cedar Springs, Kent County, MI |
| 2026 | Oneonta Town Board passes a one-year data center moratorium Spectrum News / NY State of Politics | Eco-Yotta Oneonta Data Center Oneonta, Otsego County, NY |
| Nov 20, 2025 | Howell Township Board unanimously adopts a six-month data center moratorium; it does not cover the pending rezoning request Michigan Advance | Howell Township Data Center Howell, Livingston County, MI |
| Nov 18, 2025 | Fiscal Court approves new moratorium lasting until regulations are approved The Oldham Era | Project Lincoln Oldham County, KY |
| Oct 21, 2025 | Commissioner Melissa Link calls for a data center moratorium after the denial WUGA | Old Elberton Road data center proposal Athens, Athens-Clarke County, GA |
| Aug 22, 2025 | City Council unanimously adopts one-year citywide moratorium on data center applications Spectrum News | Project Cumulus St. Charles, St. Charles County, MO |
| Jul 1, 2025 | Fiscal Court passes 150-day moratorium on data centers 4-2 with no exemptions; Deputy Judge-Executive Joe Ender fired over secret recording Louisville Public Media | Project Lincoln Oldham County, KY |
What is a data center moratorium?
The New York Department of State describes a land use moratorium as a local law that temporarily halts a landowner’s ability to get development approvals while the community considers changes to its plan or land use rules. In practice that means a council or board votes to stop the clock on new data center applications while staff write zoning standards, and the pause is usually written to expire on a set date or when new rules are adopted, whichever comes first.
Two things a moratorium generally does not do: it does not cancel approvals already granted, and it does not reach jurisdictions outside the adopting government — a county pause on unincorporated land leaves cities inside the county free to approve projects. Some entries in the table note an exclusion their source reports; check each entry’s source for others.
Permanent rules are tracked separately in the local data center rules tracker, and litigation in the lawsuit tracker.
Data center moratoriums: common questions
What is a data center moratorium?
A temporary pause, adopted by a city, county, township or state, on accepting or approving new data center applications. Local governments typically use one to buy time to write zoning rules on noise, water use, setbacks and power lines. A moratorium usually does not stop projects that were already approved.
How many places have paused data centers?
This tracker records 121 moratorium actions across 27 states, most of them county or city pauses adopted in 2025 and 2026. It lists actions we could confirm in a published notice or news report, so it is a floor, not a national census of every pause.
How long do data center moratoriums last?
Most run from 45 days to two years. Common lengths in this tracker are six months, 150 to 180 days and one year, and several have been extended once the first period ran out.
Can a moratorium be overturned?
Yes. In Imperial County, California, the Superior Court found that the county’s findings for the moratorium fell short of what state law requires, and ordered it set aside. Elsewhere, a developer has sued over a pause, and one county board was advised its moratorium was not legally binding because required procedures were not followed.
Know of a moratorium we’re missing? Email corrections@datacentercensus.com with a link to the official notice or a report. Statuses are as of each source’s date; check with the jurisdiction before relying on one.
Cite this page
Last updated Nov 6, 2026. Figures may change as records are updated — include the date you retrieved them.
| APA | Data Center Census. (2026). Data center moratorium tracker. Retrieved from https://datacentercensus.com/moratoriums |
|---|---|
| MLA | “Data center moratorium tracker.” Data Center Census, Nov 6, 2026, https://datacentercensus.com/moratoriums. |
| Link | https://datacentercensus.com/moratoriums |
Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.