Live count
AI data centers in the U.S.
A live count of major U.S. AI data center projects, from first proposal to operating campus. Each one links to the source that describes it as built for AI.
How many AI data centers are in the U.S.?
There is no official count of AI data centers. The Census counts 38 active AI data center projects in 18 states as of Sep 23, 2026: 10 operating, 18 under construction, 2 approved and 8 proposed. Another 5 were paused, cancelled or denied. A project is counted only when its own sources describe it as built for AI, so this is a floor, not a census of every AI facility.
- Active AI projects
- 38
- Operating
- 10
- Under construction
- 18
- Paused, cancelled or denied
- 5
Every tracked AI data center project
| Project | Status | Capacity | Companies | Why it counts |
|---|---|---|---|---|
| Stargate Abilene Abilene, Taylor County, TX |
1.2 GW | Crusoe, Oracle, OpenAI (tenant) | Named tenant: OpenAI. Headline: “Crusoe tops out final building at OpenAI Stargate data center campus in Abilene, Texas” DatacenterDynamics Nov 17, 2025 | |
| Meta Prometheus New Albany, Franklin and Licking counties, OH |
1 GW | Meta | Headline: “How Mark Zuckerberg Is Going to Power Meta's New AI Supercluster, Prometheus” Inc. Jul 15, 2025 | |
| Polaris Forge 1 Ellendale, Dickey County, ND |
1 GW | Applied Digital, CoreWeave (tenant) | Headline: “DCL: Applied Digital Answers Ellendale AI Data Center Questions on Roads and Water” KSJB AM 600 Jun 4, 2026 | |
| Lake Mariner Somerset, Niagara County, NY |
750 MW | TeraWulf, Fluidstack (tenant) | Headline: “TeraWulf Signs 200+ MW, 10-Year AI Hosting Agreements with Fluidstack” TeraWulf Aug 14, 2025 | |
| Core Scientific Denton Data Center Denton, Denton County, TX |
260 MW | CoreWeave, Core Scientific | Headline: “Denton approves $6.1 billion bitcoin mining to AI data center conversion” The Dallas Morning News Nov 20, 2024 | |
| xAI Colossus Memphis, Shelby County, TN |
250 MW | xAI | Developer: xAI. Headline: “xAI granted permits for 15 gas turbines at Memphis data center” DatacenterDynamics Jul 3, 2025 | |
| Amazon Web Services Madison County Mega Site campus Canton, Madison County, MS |
— | Amazon (AWS) | Headline: “Amazon's Canton AI Data Center Brings Dust, Noise and Pollution Fears for Neighbors” Mississippi Free Press Feb 13, 2026 | |
| Microsoft Fairwater Mount Pleasant, Racine County, WI |
— | Microsoft | Headline: “Made in Wisconsin: The world's most powerful AI datacenter” Microsoft On the Issues Sep 18, 2025 | |
| Microsoft Fairwater Atlanta Fayetteville, Fayette County, GA |
— | Microsoft | Headline: “Microsoft launches Atlanta Fairwater AI data center - two stories, no UPS or gen-sets” DatacenterDynamics Nov 12, 2025 | |
| Project Rainier (AWS New Carlisle campus) New Carlisle, St. Joseph County, IN |
— | Amazon (AWS), Anthropic (tenant) | Headline: “AWS activates Project Rainier: One of the world's largest AI compute clusters comes online” Amazon 2025 | |
| Fermi America Project Matador Amarillo, Carson County, TX |
Under construction | 17 GW | Fermi America, TensorWave (tenant) | Headline: “Gigawatt Scale Power for Next-Gen AI” Fermi America |
| PORTS-Pike Technology Campus Piketon, Pike County, OH |
Under construction | 10 GW | SB Energy, SoftBank, OpenAI (tenant) | Headline: “Southern Ohio community embraces world's largest AI data center” WKRC Local 12 Jun 18, 2026 |
| Monarch Compute Campus Point Pleasant, Mason County, WV |
Under construction | 8 GW | Nscale | First phase engineered for 1.35 GW of AI computing capacity (company-stated) Charleston Gazette-Mail Sep 3, 2026 |
| Meta Hyperion Holly Ridge, Richland Parish, LA |
Under construction | 5 GW | Meta | Headline: “Meta's $27 billion AI data center is transforming rural Louisiana” FOX 8 WVUE May 12, 2026 |
| Homer City Energy Campus Homer City, Indiana County, PA |
Under construction | 4.4 GW | Homer City Redevelopment | Source text: “…natural gas-powered data-centers designed to meet the growing artificial intelligence (AI) and high-performance computing (HPC) needs…” Homer City Redevelopment |
| Project Jupiter Santa Teresa, Doña Ana County, NM |
Under construction | 2.46 GW | STACK Infrastructure, Oracle (tenant), OpenAI (tenant) | Headline: “OpenAI, Oracle, and SoftBank expand Stargate with five new AI data center sites” OpenAI Sep 23, 2025 |
| IREN Sweetwater data center campus Sweetwater, Fisher County, TX |
Under construction | 2 GW | IREN | Headline: “Sweetwater Data Center | 2,000MW AI Campus in Texas” IREN |
| xAI Colossus 2 Memphis, Shelby County, TN |
Under construction | 1.78 GW | xAI | Developer: xAI. Headline: “xAI files permit for $659M expansion of Colossus 2 site” Action News 5 Mar 3, 2026 |
| Vantage Frontier Campus Albany, Shackelford County, TX |
Under construction | 1.4 GW | Vantage Data Centers, OpenAI (tenant), Oracle (tenant) | Headline: “Vantage Data Centers Unveils Plans for "Frontier," a $25B Mega-campus in Texas to Meet Unprecedented AI Demand” Vantage Data Centers Aug 19, 2025 |
| Saline Township Stargate Data Center Saline Township, Washtenaw County, MI |
Under construction | 1.38 GW | Related Digital, Oracle (tenant), OpenAI (tenant) | Named tenant: OpenAI. Headline: “Oracle, Related Digital, Blackstone, OpenAI, Walbridge and Governor Whitmer Celebrate Construction of Stargate Campus in Saline Township” Oracle Jun 1, 2026 |
| Stargate Milam County Burlington, Milam County, TX |
Under construction | 1.2 GW | SB Energy, SoftBank, OpenAI (tenant) | Headline: “OpenAI, Oracle, and SoftBank expand Stargate with five new AI data center sites” OpenAI Sep 23, 2025 |
| Goodnight Campus Claude, Armstrong County, TX |
Under construction | 1.03 GW | Crusoe, Google (tenant) | Headline: “Armstrong County AI data center project scaled back from original plan” KFDA NewsChannel 10 Oct 17, 2025 |
| Hut 8 River Bend Campus St. Francisville, West Feliciana Parish, LA |
Under construction | 330 MW | Hut 8, Fluidstack, Anthropic (tenant) | Headline: “Hut 8 Signs 15-Year, 245 MW AI Data Center Lease at River Bend Campus with Total Contract Value of $7.0 Billion” Hut 8 Dec 17, 2025 |
| CoreWeave Lancaster data center Lancaster, Lancaster County, PA |
Under construction | 300 MW | Chirisa Technology Parks, CoreWeave (tenant) | Headline: “CoreWeave Announces Multi-Billion Dollar Commitment to AI Infrastructure in Pennsylvania” CoreWeave Jul 15, 2025 |
| Nebius Vineland Data Center Vineland, Cumberland County, NJ |
Under construction | 300 MW | Nebius, DataOne, Microsoft (tenant) | Headline: “Vineland Residents Protest $17B Microsoft-Linked AI Data Center Project” SNJ Today Mar 31, 2026 |
| Meta Beaver Dam Data Center Beaver Dam, Dodge County, WI |
Under construction | 220 MW | Meta | Headline: “Meta's 30th Data Center: Delivering AI, Creating Community Benefits, and Supporting Wetlands Restoration” Meta Nov 12, 2025 |
| Amazon Web Services Richmond County data center campus Hamlet, Richmond County, NC |
Under construction | — | Amazon (AWS) | Headline: “Amazon to invest $10 billion into AI data centers in North Carolina” Axios Raleigh Jun 4, 2025 |
| Stargate Lordstown Lordstown, Trumbull County, OH |
Under construction | — | SoftBank, OpenAI (tenant) | Headline: “Lordstown part of mammoth $500 billion artificial intelligence data center project” WFMJ Sep 24, 2025 |
| Fort Meade Hyperscale Data Center Fort Meade, Polk County, FL |
Approved | 1.2 GW | Stonebridge | Headline: “Florida's commerce secretary comes out strongly against proposed AI data center” WUSF Apr 20, 2026 |
| Amazon Web Services Butts County data center campus Jackson, Butts County, GA |
Approved | — | Amazon (AWS) | Headline: “AWS plans to invest at least $11 billion in Georgia to expand infrastructure to support AI and cloud technologies” Amazon Jan 7, 2025 |
| Project Camellia Rincon, Effingham County, GA |
Proposed | 3.21 GW | OpenAI | Headline: “Building AI infrastructure with the Effingham County community” OpenAI Jul 22, 2026 |
| Project Horizon Fort Stockton, Pecos County, TX |
Proposed | 2 GW | Poolside | Headline: “Announcing Project Horizon: Why we're building a 2 gigawatt AI campus in Texas” Poolside Oct 15, 2025 |
| Lake Hawkeye Lansing, Tompkins County, NY |
Proposed | 300 MW | TeraWulf | Headline: “Tompkins County residents oppose AI data center on Cayuga Lake” WBNG Jan 28, 2026 |
| Golden Valley Technology Hub Taft, Kern County, CA |
Proposed | 275 MW | California Resources Corp. | Headline: “Massive AI data center proposed for Kern County's Elk Hills” 23ABC News (KERO) Jun 24, 2026 |
| Remington Site Data Center Ilion, Herkimer County, NY |
Proposed | 200 MW | Turin Hoefler Avenue LLC | Headline: “250,000-square-foot AI data center planned for Ilion's Remington Site C” WKTV |
| WF Industrial Yaphank Data Center Yaphank, Suffolk County, NY |
Proposed | 176.6 MW | WF Industrial (Wildflower Ltd) | Headline: “Proposed AI data center in Yaphank meets opposition from residents and town leaders” News 12 Long Island Jun 25, 2026 |
| Microsoft Gaines Township data center Caledonia, Kent County, MI |
Proposed | — | Microsoft | Headline: “Consumers Energy on Microsoft AI data center in Gaines Township ahead of public hearing” WWMT Apr 14, 2026 |
| Project Cherry Blossom Frenchtown Township, Monroe County, MI |
Proposed | — | Cloverleaf Infrastructure | Headline: “Monroe County community voices concerns over proposed AI data center” FOX 2 Detroit Nov 17, 2025 |
| Sentinel Grove Technology Park Fort Pierce, St. Lucie County, FL |
Paused | 1 GW | Timberline Real Estate Development | Headline: “Proposed 15 million square-foot AI data center in St. Lucie County faces pushback” WPTV Dec 10, 2025 |
| Imperial Data Center Imperial, Imperial County, CA |
Paused | 330 MW | Imperial Valley Computer Manufacturing | Headline: “'This data center will come.' The fight over California's largest AI development” inewsource Apr 5, 2026 |
| Project Aggie College Station, Brazos County, TX |
Denied | 600 MW | Priority Power Management | Headline: “College Station City Council unanimously rejects land sale for AI data center” KBTX Sep 12, 2025 |
| Highlander SM One data center San Marcos, Hays County, TX |
Denied | — | Highlander SM One | Headline: “San Marcos City Council votes 5-2 to deny AI data center proposal” CBS Austin Feb 18, 2026 |
| Project Tango Loxahatchee, Palm Beach County, FL |
Denied | — | WPB Logistics LLC | Headline: “DENIED: Palm Beach County Commissioners vote against the 'Project Tango' AI data center” WPTV Jul 15, 2026 |
Ordered by status, then by published capacity. Capacity is the planned total a developer or utility has published: often a full build-out target, and for some campuses the size of an on-site power plant, not what is running today. Open a project for the note on its figure. Status follows the Census definitions.
AI data centers by state
| State | Active | Operating | Building | Stopped |
|---|---|---|---|---|
| Texas | 8 | 2 | 5 | 2 |
| New York | 4 | 1 | 0 | 0 |
| Georgia | 3 | 1 | 0 | 0 |
| Michigan | 3 | 0 | 1 | 0 |
| Ohio | 3 | 1 | 2 | 0 |
| Louisiana | 2 | 0 | 2 | 0 |
| Pennsylvania | 2 | 0 | 2 | 0 |
| Tennessee | 2 | 1 | 1 | 0 |
| Wisconsin | 2 | 1 | 1 | 0 |
| Florida | 1 | 0 | 0 | 2 |
| California | 1 | 0 | 0 | 1 |
| Indiana | 1 | 1 | 0 | 0 |
| Mississippi | 1 | 1 | 0 | 0 |
| New Jersey | 1 | 0 | 1 | 0 |
| New Mexico | 1 | 0 | 1 | 0 |
| North Carolina | 1 | 0 | 1 | 0 |
| North Dakota | 1 | 1 | 0 | 0 |
| West Virginia | 1 | 0 | 1 | 0 |
Active counts operating, under construction, approved and proposed projects; stopped counts paused, cancelled and denied ones.
Who is behind them
| Company | AI projects | Developer or operator | Tenant |
|---|---|---|---|
| OpenAI | 8 | 1 | 7 |
| Amazon (AWS) | 4 | 4 | 0 |
| Microsoft | 4 | 3 | 1 |
| Oracle | 4 | 1 | 3 |
| CoreWeave | 3 | 1 | 2 |
| Meta | 3 | 3 | 0 |
| SoftBank | 3 | 3 | 0 |
| Anthropic | 2 | 0 | 2 |
| Crusoe | 2 | 2 | 0 |
| Fluidstack | 2 | 1 | 1 |
| SB Energy | 2 | 2 | 0 |
| TeraWulf | 2 | 2 | 0 |
| xAI | 2 | 2 | 0 |
Companies named on two or more tracked AI projects, as developer, operator or reported tenant. A project can list several companies.
How this count works
No government agency publishes a count of AI data centers, and there is no single definition. The International Energy Agency says a hyperscale, AI-focused data center can be 100 MW or more[1], and Executive Order 14318 defines a “Data Center Project” as a facility requiring more than 100 MW of new load dedicated to AI inference, training, simulation or synthetic data generation[2].
The Census counts a project as an AI data center only when its own record shows it: a cited source whose headline describes that project as AI, a dated fact or quoted passage from a cited source that does, or a developer or tenant whose business is building AI models (OpenAI, Anthropic or xAI), named in a cited headline. A headline about a region’s AI boom in general does not count. Each project’s evidence is in the table above, and the classification is published in the open data.
That makes this a floor. Many large cloud campuses run AI workloads without their sources saying so, and they are not counted until a source does. When a record gains that evidence, the count updates on the next build. Paused, cancelled and denied projects stay on the list so the record is complete, but they are not in the active count.
Reviewed but not counted
- QTS Fayetteville data center campus: Its AI evidence is the Microsoft Fairwater building on the campus, which the Census tracks as its own record (Microsoft Fairwater Atlanta). Counting both would count that building twice.
- Google Kansas City Data Center (Hunt Midwest Business Center): The only AI reference is a headline about Kansas City's data center boom in general, not this project.
- Project Mica: The only AI reference is a headline about Kansas City's data center boom in general, not this project.
- Eco-Yotta Oneonta Data Center: The only AI reference is a headline about the town's moratorium on AI data centers generally, not a description of this project.
- Viridian Data Center Campus (former GM/JATCO site): The headline ties the site's redevelopment interest to AI in general terms without describing this project's use.
- Global AI Data Center: AI appears only in the developer's company name; no cited source in the record states what the campus will run.
- Meta El Paso Data Center: The record's summary calls it an AI data center, but no cited headline, dated event or quoted passage in the record says so yet.
- Port Washington (Lighthouse) Data Center Campus: The record names OpenAI as a tenant, but no cited headline, dated event or quoted passage in the record says so yet.
- Project Tembo: The only AI description is the 2025 announcement by Crusoe and Tallgrass, who have since left the project; no cited source describes Google's current plan as AI.
Put this count on your site
The live count is available as a free widget for articles, council pages and newsletters. It updates itself when the record changes and credits the Census. Get the embed code →
Related: How many data centers are in the U.S.? · AI data center news · Largest projects · Companies
AI data centers: common questions
How many AI data centers are in the U.S.?
There is no official count of AI data centers. The Census counts 38 active AI data center projects in 18 states as of Sep 23, 2026: 10 operating, 18 under construction, 2 approved and 8 proposed. Another 5 were paused, cancelled or denied. A project is counted only when its own sources describe it as built for AI, so this is a floor, not a census of every AI facility.
How many AI data centers are operating in the U.S.?
10 tracked AI projects are operating: Stargate Abilene, Meta Prometheus, Polaris Forge 1, Lake Mariner, Core Scientific Denton Data Center, xAI Colossus, Amazon Web Services Madison County Mega Site campus, Microsoft Fairwater, Microsoft Fairwater Atlanta and Project Rainier (AWS New Carlisle campus). Another 18 are under construction.
Which state has the most AI data centers?
Texas has the most active AI data center projects in the Census, 8 (10 including 2 paused, cancelled or denied). 18 states have at least one active AI project.
What is the largest AI data center project in the U.S.?
By published planned capacity, the largest active AI project in the Census is Fermi America Project Matador in Amarillo, Carson County, TX, at 17 GW (the record notes: company says 17 GW private power campus (earlier announced as 11 GW); ~6 GW permitted). Its status is under construction. Published capacity figures are often full build-out targets, and for some campuses they describe on-site power generation rather than computing load.
What makes a data center an AI data center?
There is no single legal definition. The International Energy Agency says a hyperscale, AI-focused data center can be 100 MW or more, and a July 2025 executive order defines a “Data Center Project” as a facility requiring more than 100 MW of new load dedicated to AI. The Census counts a project as AI when its own sources describe it that way.
Which companies are behind the most AI data center projects?
OpenAI is named on 8 tracked AI projects, then Amazon (AWS), Microsoft and Oracle on 4 each, as developer, operator or reported tenant.
Sources
- Understanding the energy-AI nexus – Energy and AIInternational Energy Agency · 2025-04-10
Source excerpt
“A hyperscale, AI-focused data centre can have a capacity of 100 MW or more, consuming as much electricity annually as 100 000 households.”
- Accelerating Federal Permitting of Data Center InfrastructureThe White House · 2025-07-23
Source excerpt
“a facility that requires greater than 100 megawatts (MW) of new load dedicated to AI inference, training, simulation, or synthetic data generation. ... a Data Center Project or Covered Component Project for which the Project Sponsor has committed at least $500 million in capital expenditures as determined by the Secretary of Commerce”
Cite this page
Last updated Sep 23, 2026. Figures may change as records are updated — include the date you retrieved them.
| APA | Data Center Census. (2026). AI data centers in the U.S.. Retrieved from https://datacentercensus.com/ai-data-centers |
|---|---|
| MLA | “AI data centers in the U.S..” Data Center Census, Sep 23, 2026, https://datacentercensus.com/ai-data-centers. |
| Link | https://datacentercensus.com/ai-data-centers |
Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.