Oracle data centers: tracked projects and locations
Oracle is linked to 5 tracked projects in Wisconsin, New Mexico, Michigan, Texas, totaling 7.74 GW of planned capacity. Role: tenant and developer.
- Under construction 4
- Operating 1
Ranked #31 of 59 developers by the published capacity of its tracked projects that are proposed, approved, under construction or operating, as developer or operator (1.2 GW). See the ranking →
| Project | Status | Capacity | Developer | Last update |
|---|---|---|---|---|
| Port Washington (Lighthouse) Data Center Campus Port Washington, Ozaukee County, WI |
Under construction | 1.3 GW | Vantage Data Centers | Sep 14, 2026 |
| Project Jupiter Santa Teresa, Doña Ana County, NM |
Under construction | 2.46 GW | STACK Infrastructure | Sep 24, 2026 |
| Saline Township Stargate Data Center Saline Township, Washtenaw County, MI |
Under construction | 1.38 GW | Related Digital | Aug 10, 2026 |
| Stargate Abilene Abilene, Taylor County, TX |
1.2 GW | Crusoe, Oracle | Nov 1, 2026 | |
| Vantage Frontier Campus Albany, Shackelford County, TX |
Under construction | 1.4 GW | Vantage Data Centers | Sep 3, 2026 |
Latest Oracle data center news
The newest dated changes at Oracle’s tracked projects, each from the filing, notice or report linked beside it.
-
Stargate Abilene TX
Epoch AI estimates all 8 buildings (7-8 estimated) operational, for 824 MW of IT power (Epoch AI estimate) Epoch AI -
Project Jupiter NM
Oracle sends developer Blue Owl Capital a force-majeure notice after a natural-gas pipeline meant to supply the project's power is delayed to February 2027 following New Mexico State Land Office permit denials; both companies say it does not change their commitment to the project SiliconANGLE -
Port Washington (Lighthouse) Data Center Campus WI
ATC refiles its application for the grid upgrades serving the campus, dropping a Trenton-Saukville line segment and restarting the PSC's six-month review Wisconsin Watch -
Stargate Abilene TX
On Oracle's Q1 FY2027 earnings call, its CEO said 6 of the 8 Abilene buildings, 618 MW or 75% of total capacity, had been delivered to the customer, and that Oracle delivered about 131,000 GPUs there in the quarter The Motley Fool -
Project Jupiter NM
Attorney General Raúl Torrez files responses backing emergency petitions New Mexico Department of Justice -
Stargate Abilene TX
Chamber panel addresses resident concerns over housing, power, water and noise KACU
This page lists projects in the Census where Oracle is named as developer or a publicly reported tenant by a cited source. It is not a complete list of the company’s facilities, and this page is not affiliated with or endorsed by Oracle.