Company
Vantage Data Centers: tracked projects and locations
Vantage Data Centers is linked to 2 tracked projects in Wisconsin, Texas, totaling 2.7 GW of planned capacity. Role: developer.
- Under construction 2
Ranked #12 of 59 developers by the published capacity of its tracked projects that are proposed, approved, under construction or operating, as developer or operator (2.7 GW). See the ranking →
| Project | Status | Capacity | Developer | Last update |
|---|---|---|---|---|
| Port Washington (Lighthouse) Data Center Campus Port Washington, Ozaukee County, WI |
Under construction | 1.3 GW | Vantage Data Centers | Sep 14, 2026 |
| Vantage Frontier Campus Albany, Shackelford County, TX |
Under construction | 1.4 GW | Vantage Data Centers | Sep 3, 2026 |
Latest Vantage Data Centers data center news
The newest dated changes at Vantage Data Centers’s tracked projects, each from the filing, notice or report linked beside it.
-
Port Washington (Lighthouse) Data Center Campus WI
ATC refiles its application for the grid upgrades serving the campus, dropping a Trenton-Saukville line segment and restarting the PSC's six-month review Wisconsin Watch -
Port Washington (Lighthouse) Data Center Campus WI
Oracle moves to voluntarily drop its Ozaukee County Circuit Court lawsuit challenging the Wisconsin PSC's credit rating requirements for data center developers Wisconsin Watch -
Port Washington (Lighthouse) Data Center Campus WI
PSC requires ATC to restart its application for the $1.3B+ transmission line and five substations serving the campus Wisconsin Watch -
Port Washington (Lighthouse) Data Center Campus WI
Oracle credit rating falls to BBB-; PSC rejects We Energies request to reconsider collateral rules; Oracle challenges rules in Ozaukee County Circuit Court Milwaukee Neighborhood News Service -
Port Washington (Lighthouse) Data Center Campus WI
Oracle files petition in Ozaukee County Circuit Court seeking review of the PSC's data center tariff decision Ozaukee County Circuit Court (via WPR) -
Port Washington (Lighthouse) Data Center Campus WI
DNR issues air construction and operation permits for 45 diesel emergency generators Wisconsin Department of Natural Resources -
Port Washington (Lighthouse) Data Center Campus WI
DNR public hearing on air permit (comment period Mar. 3-Apr. 14) Wisconsin Department of Natural Resources
Company profile
| What it does | Vantage says it builds large-scale campuses ranging from 64MW to more than 1GW so customers can grow in place (company claim, website as of September 2026). [1] In a September 14, 2026 press release, Vantage calls itself a worldwide digital infrastructure provider for AI and cloud innovators, operating across North America, EMEA and Asia Pacific. [2] |
|---|---|
| Founded | Vantage Data Centers says on its company timeline that it launched in June 2010 with an investment from Silver Lake Partners, acquiring a former Intel data center in Santa Clara, California. [3] |
| Headquarters | The Denver Metro Chamber of Commerce member listing (member since 2026) says Vantage Data Centers was founded in 2010 and is headquartered in Denver, Colorado. [4] |
| Leadership | Vantage's leadership page lists Sureel Choksi as President & Chief Executive Officer (as of September 2026), serving in that role since 2013. [5] |
| Ownership | Vantage's company timeline says DigitalBridge acquired Vantage Data Centers in March 2017. [3] |
| Funding | Vantage's company timeline says that in June 2024 it completed a $9.2 billion equity investment, which DigitalBridge and Silver Lake led. [3] |
| Stated footprint | Vantage's homepage states figures of 3 continents, 50+ markets, 40+ campuses and 15GW+ of power (company claim, website as of September 2026). [1] |
| Website | Vantage Data Centers' official website is vantage-dc.com, per the boilerplate of its January 2024 press release. [6] |
- Vantage Data Centers (homepage) Vantage Data Centers, 2026-09
- Vantage Secures $2B Credit Facility, Expanding Financing to Support Growing Demand Vantage Data Centers, 2026-09-14
- About Us - Vantage Data Centers Vantage Data Centers, 2026-09
- Vantage Data Centers - Denver Metro Chamber of Commerce Denver Metro Chamber of Commerce, 2026
- Leadership - Vantage Data Centers Vantage Data Centers, 2026-09
- Vantage Data Centers Experienced Unprecedented Growth in 2023 Driven by AI and Cloud Demand Globally; Secured $10 Billion in Incremental Funding Business Wire (Vantage Data Centers press release), 2024-01-31
Company self-descriptions and stated figures are the company’s own claims, dated where the source gives a date.
This page lists projects in the Census where Vantage Data Centers is named as developer by a cited source. It is not a complete list of the company’s facilities, and this page is not affiliated with or endorsed by Vantage Data Centers.