Data Center Census Near me

Accuracy

Where we disagree with other trackers

We compared all 145 Census records against Compute Atlas, an open dataset of 2,166 US data center sites. We matched 132 of them. On 84 we agree; on 36 we disagree; and 12 carry a status their schema cannot express.

Nobody audits data center trackers. The next best thing is to check them against each other in public, so a reader can see where two sourced datasets diverge and judge for themselves.

This page is that check, run on Sep 22, 2026 against Compute Atlas, whose dataset is published under CC BY 4.0. A disagreement is not proof that either side is wrong — trackers update at different times, and a project can move between the day they looked and the day we did. Where we differ, our evidence is in the last column and the full source trail is on the project page.

Records matched
132
Agreement
70%
Disagreements
36
Statuses they can't express
12

Statuses their schema cannot express

The Census tracks 8 statuses; Compute Atlas tracks five. Three of ours — rumored, paused, denied — have no counterpart, so a project that was refused, stalled or is still only rumored has to be filed as something else. These 12 records are the clearest case for tracking them separately.

Census records whose status has no equivalent in the Compute Atlas schema.
ProjectCensus statusCompute AtlasWhy we say what we say
Amazon Becker Data Center
Becker, Sherburne County, MN
Paused Cancelled
as of Jul 25, 2026
Amazon suspended development in May 2025 and says it will keep the land; the site was still vacant as of September 2025.
Amazon Data Services King George campus (former Birchwood power plant site)
King George County, VA
Paused Proposed
as of Sep 21, 2026
County board withdrew from the performance agreement in January 2024; Amazon's vested-rights lawsuit against the county was set for trial September 28-29, 2026
Menomonie Data Center (Balloonist LLC)
Menomonie, Dunn County, WI
Paused Proposed
as of Jul 23, 2026
Mayor said in September 2025 the city will not negotiate a development agreement or TIF district at this time
Howell Township Data Center
Howell, Livingston County, MI
Paused Cancelled
as of Sep 9, 2026
Developers withdrew the rezoning request on Dec. 8, 2025; Planet Detroit reported they could resubmit after the township's six-month moratorium.
Imperial Data Center
Imperial, Imperial County, CA
Paused Proposed
as of Sep 21, 2026
Superior Court set aside the county's lot merger approval on 2026-09-09 and ordered CEQA review; developer plans to appeal
Old Bermuda Data Center
Chesterfield County, VA
Denied Proposed
as of Jul 26, 2026
Board of Zoning Appeals upheld denial of by-right development in June 2026; conditional use approval from the Board of Supervisors now required
Project Tango
Loxahatchee, Palm Beach County, FL
Denied Cancelled
as of Sep 21, 2026
Palm Beach County Commission denied additional approvals 5-1 without prejudice on July 15, 2026; prior 2016 entitlements remain
Sentinel / Green Fig Data Center
Malvern, Chester County, PA
Paused Under construction
as of Sep 21, 2026
Township stop-work order issued Aug. 26, 2026 pending Aqua water 'will serve' confirmation
Sentinel Grove Technology Park
Fort Pierce, St. Lucie County, FL
Paused Cancelled
as of Sep 10, 2026
Timberline announced a temporary pause after the planning board's 4-2 recommendation against; a county commissioner said in February 2026 the developer appears to have pulled back
Augusta Township Data Center (Thor Equities)
Augusta Township, Washtenaw County, MI
Denied Cancelled
as of Sep 9, 2026
Voters overturned the data center rezoning in the Aug. 4, 2026 referendum, per unofficial results
Tooele Valley data center (Burmester Road / I-80)
Tooele County, UT
Paused Proposed
as of Aug 25, 2026
Tooele County halted data center applications pending a new ordinance (planning commission Oct 2026, county council Nov 2026)
Treetop East Fishkill Data Center
East Fishkill, Dutchess County, NY
Rumored Proposed
as of Sep 9, 2026
No application was ever filed; the town adopted a three-year moratorium in June 2026 and says data centers are not a permitted use in its industrial zones

Straight disagreements

Both schemas can express these; we reached different conclusions.

Records where the two trackers assign different statuses.
ProjectCensus statusCompute AtlasWhy we say what we say
Amazon Hobart data center
Hobart, Lake County, IN
Approved Under construction
as of Aug 16, 2026
Common Council approved the tax abatement in January 2026 and a fill permit was approved in February 2026; residents have challenged the approvals in court
Avemore Data Park
Villa Rica, Carroll County, GA
Approved Proposed
as of Sep 10, 2026
Villa Rica approved annexation and rezoning in May 2025; residents' court petition challenging it was reported as filed. No Amazon involvement found in any source reviewed.
Amazon Web Services Butts County data center campus
Jackson, Butts County, GA
Approved Proposed
as of Aug 28, 2026
Local PILOT agreement amended November 2025; payments begin 2027
Amazon Web Services Madison County Mega Site campus
Canton, Madison County, MS
Operating Under construction
as of Sep 10, 2026
Five of an expected 15–17 buildings operating as of spring 2026; expansion announced April 2026
AWS Fayette County Data Center Campus
Jeffersonville, Fayette County, OH
Approved Under construction
as of Aug 5, 2026
Fayette County Commissioners approved a Community Reinvestment Area agreement with AWS
Project Galaxy (AWS Sidney data center)
Sidney, Shelby County, OH
Approved Under construction
as of Jul 7, 2026
Sidney City Council approved a 30-year, 100% tax abatement in October 2025; operations estimated to begin by Dec. 31, 2028
AWS Project Green
New Florence, Montgomery County, MO
Approved Under construction
as of Jul 7, 2026
Montgomery County approved a tax abatement and incentive program; a lawsuit by Preserve Montgomery County survived most of a motion to dismiss in September 2026
AWS Wilmington data center
Wilmington, Clinton County, OH
Approved Proposed
as of Sep 9, 2026
Site annexed by City Council Aug. 7, 2025; Ohio Supreme Court kept a citizen data center regulation initiative off the Nov. 3, 2026 ballot
Comanche Circle
Tolar, Hood County, TX
Approved Proposed
as of Aug 16, 2026
Concept plan approved without conditions 2026-06-09; next is site development plan review. County twice rejected data center moratoriums in Feb 2026
Compass Datacenters Red Oak second campus
Red Oak, Ellis County, TX
Approved Proposed
as of Jul 26, 2026
Red Oak City Council approved rezoning and a tax abatement 4-1 in May 2026 despite a planning board recommendation against it
Compass Statesville
Statesville, Iredell County, NC
Approved Proposed
as of Jul 26, 2026
Rezoning approved September 2025; exempt from Statesville's proposed 2026 data center moratorium
Core Scientific Denton Data Center
Denton, Denton County, TX
Operating Under construction
as of Aug 16, 2026
More than 16,000 GPUs deployed as of January 2026; facility expansion under construction as of April 2026
CoreWeave Lancaster data center
Lancaster, Lancaster County, PA
Under construction Proposed
as of Sep 12, 2026
First Greenfield Road building under construction; second building and Harrisburg Pike site still need approvals
CRG Festus Data Center
Festus, Jefferson County, MO
Approved Proposed
as of Aug 24, 2026
Development agreement approved March 2026; CRG unveiled scaled-back 4-building design June 2026; resident lawsuit pending
Farmington Technology Park
Farmington, Dakota County, MN
Approved Proposed
as of Sep 18, 2026
City approvals completed in 2024; on Sept. 16, 2026 the city reported that plaintiffs in both lawsuits against it had filed dismissals, pending final court direction.
Fleet Data Centers TRIC campuses (South Valley and Peru Ridge)
Storey County, NV
Proposed Under construction
as of Aug 14, 2026
PUCN approved two temporary private gas plants (360+ MW) on 2026-09-18; state air permits and Storey County approvals still required
Global AI Data Center
Windsor, Weld County, CO
Approved Under construction
as of Aug 26, 2026
Use by Special Review permit approved 5-0 on Sept. 9, 2026 with closed-loop cooling, noise and decommissioning-bond conditions
Golden Valley Technology Hub
Taft, Kern County, CA
Proposed Operational
as of Sep 21, 2026
Permits filed with Kern County June 2026; conditional use permit and environmental review pending. No annexation found
Google Kansas City Data Center (Hunt Midwest Business Center)
Kansas City, Clay County, MO
Under construction Operational
as of Sep 10, 2026
Construction continuing as of early 2026
Google Palo data center campus
Palo, Linn County, IA
Proposed Under construction
as of Aug 4, 2026
Google shifted from unincorporated Linn County toward annexation into Palo; Linn County declined in August 2026 to allow data centers in its EU-2 nuclear zoning district
Meta Prometheus
New Albany, Franklin and Licking counties, OH
Operating Under construction
as of Aug 8, 2026
Epoch AI lists the first building operating since Oct 2025 and 12 buildings (562 MW IT) operating as of Aug 2026; more buildings and on-site gas plants still under construction.
Muncy Data Center
Muncy Township, Lycoming County, PA
Proposed Permitted
as of Aug 17, 2026
Developer published notice of deemed conditional use approval; township contests it and adjoining residents have appealed
Nebius Vineland Data Center
Vineland, Cumberland County, NJ
Under construction Operational
as of Sep 21, 2026
City issued stop-construction orders on LNG tank and fuel cell work, Aug 2026
Perry Township Data Center
Canton, Stark County, OH
Approved Under construction
as of Aug 5, 2026
Stark County commissioners approved in June 2026 after township and Canton JEDD approvals
Pennsylvania Digital 1 (PAX-1)
Middlesex Township, Cumberland County, PA
Approved Under construction
as of Aug 2, 2026
Site-preparation permits granted; Phase 1-B final land development for the first six buildings approved September 2026
Polaris Forge 1
Ellendale, Dickey County, ND
Operating Under construction
as of Jul 26, 2026
Building 1 (100 MW) fully energized Nov 2025; Buildings 2–3 under construction/planned
Project Cannoli
Van Buren Township, Wayne County, MI
Approved Proposed
as of Sep 21, 2026
Township site plan and tax abatement approvals granted in 2026; DTE power contracts under contested-case review at the Michigan PSC
Project Delta
Walnut Cove, Stokes County, NC
Approved Proposed
as of Jul 6, 2026
Rezoning re-approved 3-2 on Sept. 14, 2026 after January approval was voided over notice defects; state permits not yet obtained as of January
Project Flex
New Hudson, Oakland County, MI
Approved Proposed
as of Sep 9, 2026
Conditional site plan approval Sept 2025; final site plan still under Planning Commission review
Project Marvel
Bessemer, Jefferson County, AL
Approved Proposed
as of Sep 9, 2026
Rezoning approved Nov. 2025 and expanded to 914 acres in April 2026; residents' rezoning lawsuit dismissed with prejudice June 22, 2026.
Project Tamarack
West Columbia, Mason County, WV
Approved Proposed
as of Sep 22, 2026
Certified by the West Virginia Department of Commerce as a high-impact data center; announced September 3, 2026
Ridgeline Facility
Thomas, Tucker County, WV
Approved Proposed
as of Sep 10, 2026
State air permit R13-3713 issued Aug 2025 and upheld by Air Quality Board Feb 2026; appeals court dismissed groups' appeals Aug 2026 for lack of jurisdiction, leaving a path to the WV Supreme Court
Fort Meade Hyperscale Data Center
Fort Meade, Polk County, FL
Approved Proposed
as of Sep 10, 2026
Developer agreement approved April 2026, contingent on a Southwest Florida Water Management District permit
T5 @ Chicago IV
Grayslake, Lake County, IL
Approved Under construction
as of Sep 12, 2026
Village issued first building permit Sept. 1, 2026; lawsuit challenging approvals pending
Viridian Data Center Campus (former GM/JATCO site)
Janesville, Rock County, WI
Cancelled Proposed
as of Aug 18, 2026
City council voted in June 2026 not to extend the letter of intent with Viridian
xAI Colossus 2
Memphis, Shelby County, TN
Under construction Operational
as of Sep 21, 2026
Partly in use training Grok while expansion continues; powered largely by gas turbines at a Southaven, MS plant subject to an NAACP Clean Air Act suit

How the comparison works

Records are matched on a shared distinctive word in the project or developer name and geographic proximity in the same state. Proximity alone is never enough: two unrelated data centers can sit a few hundred metres apart in one industrial park, and a mix-up there would produce a disagreement that is really our own error. 13 Census records found no confident match and are left out rather than guessed at.

Statuses are compared through a crosswalk: proposed ↔ Proposed, approved ↔ Permitted, under construction ↔ Under construction, operating ↔ Operational, cancelled ↔ Cancelled. The 84 agreements are not listed individually; the whole comparison, including them, is in reference.json.

Compute Atlas data retrieved Sep 22, 2026 and used under CC BY 4.0. Their dataset is their work, not ours; any error in the matching above is ours, not theirs.

Think one of these is wrong? Email [email protected] with a source and we will correct the record and say so.

Cite this page

Last updated Sep 22, 2026. Figures may change as records are updated — include the date you retrieved them.

APAData Center Census. (2026). Where we disagree with other trackers. Retrieved from https://datacentercensus.com/cross-check
MLA“Where we disagree with other trackers.” Data Center Census, Sep 22, 2026, https://datacentercensus.com/cross-check.
Linkhttps://datacentercensus.com/cross-check

Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.