Accuracy
Where we disagree with other trackers
We compared all 145 Census records against Compute Atlas, an open dataset of 2,166 US data center sites. We matched 132 of them. On 84 we agree; on 36 we disagree; and 12 carry a status their schema cannot express.
Nobody audits data center trackers. The next best thing is to check them against each other in public, so a reader can see where two sourced datasets diverge and judge for themselves.
This page is that check, run on Sep 22, 2026 against Compute Atlas, whose dataset is published under CC BY 4.0. A disagreement is not proof that either side is wrong — trackers update at different times, and a project can move between the day they looked and the day we did. Where we differ, our evidence is in the last column and the full source trail is on the project page.
- Records matched
- 132
- Agreement
- 70%
- Disagreements
- 36
- Statuses they can't express
- 12
Statuses their schema cannot express
The Census tracks 8 statuses; Compute Atlas tracks five. Three of ours — rumored, paused, denied — have no counterpart, so a project that was refused, stalled or is still only rumored has to be filed as something else. These 12 records are the clearest case for tracking them separately.
| Project | Census status | Compute Atlas | Why we say what we say |
|---|---|---|---|
| Amazon Becker Data Center Becker, Sherburne County, MN |
Paused | Cancelled as of Jul 25, 2026 |
Amazon suspended development in May 2025 and says it will keep the land; the site was still vacant as of September 2025. |
| Amazon Data Services King George campus (former Birchwood power plant site) King George County, VA |
Paused | Proposed as of Sep 21, 2026 |
County board withdrew from the performance agreement in January 2024; Amazon's vested-rights lawsuit against the county was set for trial September 28-29, 2026 |
| Menomonie Data Center (Balloonist LLC) Menomonie, Dunn County, WI |
Paused | Proposed as of Jul 23, 2026 |
Mayor said in September 2025 the city will not negotiate a development agreement or TIF district at this time |
| Howell Township Data Center Howell, Livingston County, MI |
Paused | Cancelled as of Sep 9, 2026 |
Developers withdrew the rezoning request on Dec. 8, 2025; Planet Detroit reported they could resubmit after the township's six-month moratorium. |
| Imperial Data Center Imperial, Imperial County, CA |
Paused | Proposed as of Sep 21, 2026 |
Superior Court set aside the county's lot merger approval on 2026-09-09 and ordered CEQA review; developer plans to appeal |
| Old Bermuda Data Center Chesterfield County, VA |
Denied | Proposed as of Jul 26, 2026 |
Board of Zoning Appeals upheld denial of by-right development in June 2026; conditional use approval from the Board of Supervisors now required |
| Project Tango Loxahatchee, Palm Beach County, FL |
Denied | Cancelled as of Sep 21, 2026 |
Palm Beach County Commission denied additional approvals 5-1 without prejudice on July 15, 2026; prior 2016 entitlements remain |
| Sentinel / Green Fig Data Center Malvern, Chester County, PA |
Paused | Under construction as of Sep 21, 2026 |
Township stop-work order issued Aug. 26, 2026 pending Aqua water 'will serve' confirmation |
| Sentinel Grove Technology Park Fort Pierce, St. Lucie County, FL |
Paused | Cancelled as of Sep 10, 2026 |
Timberline announced a temporary pause after the planning board's 4-2 recommendation against; a county commissioner said in February 2026 the developer appears to have pulled back |
| Augusta Township Data Center (Thor Equities) Augusta Township, Washtenaw County, MI |
Denied | Cancelled as of Sep 9, 2026 |
Voters overturned the data center rezoning in the Aug. 4, 2026 referendum, per unofficial results |
| Tooele Valley data center (Burmester Road / I-80) Tooele County, UT |
Paused | Proposed as of Aug 25, 2026 |
Tooele County halted data center applications pending a new ordinance (planning commission Oct 2026, county council Nov 2026) |
| Treetop East Fishkill Data Center East Fishkill, Dutchess County, NY |
Rumored | Proposed as of Sep 9, 2026 |
No application was ever filed; the town adopted a three-year moratorium in June 2026 and says data centers are not a permitted use in its industrial zones |
Straight disagreements
Both schemas can express these; we reached different conclusions.
| Project | Census status | Compute Atlas | Why we say what we say |
|---|---|---|---|
| Amazon Hobart data center Hobart, Lake County, IN |
Approved | Under construction as of Aug 16, 2026 |
Common Council approved the tax abatement in January 2026 and a fill permit was approved in February 2026; residents have challenged the approvals in court |
| Avemore Data Park Villa Rica, Carroll County, GA |
Approved | Proposed as of Sep 10, 2026 |
Villa Rica approved annexation and rezoning in May 2025; residents' court petition challenging it was reported as filed. No Amazon involvement found in any source reviewed. |
| Amazon Web Services Butts County data center campus Jackson, Butts County, GA |
Approved | Proposed as of Aug 28, 2026 |
Local PILOT agreement amended November 2025; payments begin 2027 |
| Amazon Web Services Madison County Mega Site campus Canton, Madison County, MS |
Under construction as of Sep 10, 2026 |
Five of an expected 15–17 buildings operating as of spring 2026; expansion announced April 2026 | |
| AWS Fayette County Data Center Campus Jeffersonville, Fayette County, OH |
Approved | Under construction as of Aug 5, 2026 |
Fayette County Commissioners approved a Community Reinvestment Area agreement with AWS |
| Project Galaxy (AWS Sidney data center) Sidney, Shelby County, OH |
Approved | Under construction as of Jul 7, 2026 |
Sidney City Council approved a 30-year, 100% tax abatement in October 2025; operations estimated to begin by Dec. 31, 2028 |
| AWS Project Green New Florence, Montgomery County, MO |
Approved | Under construction as of Jul 7, 2026 |
Montgomery County approved a tax abatement and incentive program; a lawsuit by Preserve Montgomery County survived most of a motion to dismiss in September 2026 |
| AWS Wilmington data center Wilmington, Clinton County, OH |
Approved | Proposed as of Sep 9, 2026 |
Site annexed by City Council Aug. 7, 2025; Ohio Supreme Court kept a citizen data center regulation initiative off the Nov. 3, 2026 ballot |
| Comanche Circle Tolar, Hood County, TX |
Approved | Proposed as of Aug 16, 2026 |
Concept plan approved without conditions 2026-06-09; next is site development plan review. County twice rejected data center moratoriums in Feb 2026 |
| Compass Datacenters Red Oak second campus Red Oak, Ellis County, TX |
Approved | Proposed as of Jul 26, 2026 |
Red Oak City Council approved rezoning and a tax abatement 4-1 in May 2026 despite a planning board recommendation against it |
| Compass Statesville Statesville, Iredell County, NC |
Approved | Proposed as of Jul 26, 2026 |
Rezoning approved September 2025; exempt from Statesville's proposed 2026 data center moratorium |
| Core Scientific Denton Data Center Denton, Denton County, TX |
Under construction as of Aug 16, 2026 |
More than 16,000 GPUs deployed as of January 2026; facility expansion under construction as of April 2026 | |
| CoreWeave Lancaster data center Lancaster, Lancaster County, PA |
Under construction | Proposed as of Sep 12, 2026 |
First Greenfield Road building under construction; second building and Harrisburg Pike site still need approvals |
| CRG Festus Data Center Festus, Jefferson County, MO |
Approved | Proposed as of Aug 24, 2026 |
Development agreement approved March 2026; CRG unveiled scaled-back 4-building design June 2026; resident lawsuit pending |
| Farmington Technology Park Farmington, Dakota County, MN |
Approved | Proposed as of Sep 18, 2026 |
City approvals completed in 2024; on Sept. 16, 2026 the city reported that plaintiffs in both lawsuits against it had filed dismissals, pending final court direction. |
| Fleet Data Centers TRIC campuses (South Valley and Peru Ridge) Storey County, NV |
Proposed | Under construction as of Aug 14, 2026 |
PUCN approved two temporary private gas plants (360+ MW) on 2026-09-18; state air permits and Storey County approvals still required |
| Global AI Data Center Windsor, Weld County, CO |
Approved | Under construction as of Aug 26, 2026 |
Use by Special Review permit approved 5-0 on Sept. 9, 2026 with closed-loop cooling, noise and decommissioning-bond conditions |
| Golden Valley Technology Hub Taft, Kern County, CA |
Proposed | Operational as of Sep 21, 2026 |
Permits filed with Kern County June 2026; conditional use permit and environmental review pending. No annexation found |
| Google Kansas City Data Center (Hunt Midwest Business Center) Kansas City, Clay County, MO |
Under construction | Operational as of Sep 10, 2026 |
Construction continuing as of early 2026 |
| Google Palo data center campus Palo, Linn County, IA |
Proposed | Under construction as of Aug 4, 2026 |
Google shifted from unincorporated Linn County toward annexation into Palo; Linn County declined in August 2026 to allow data centers in its EU-2 nuclear zoning district |
| Meta Prometheus New Albany, Franklin and Licking counties, OH |
Under construction as of Aug 8, 2026 |
Epoch AI lists the first building operating since Oct 2025 and 12 buildings (562 MW IT) operating as of Aug 2026; more buildings and on-site gas plants still under construction. | |
| Muncy Data Center Muncy Township, Lycoming County, PA |
Proposed | Permitted as of Aug 17, 2026 |
Developer published notice of deemed conditional use approval; township contests it and adjoining residents have appealed |
| Nebius Vineland Data Center Vineland, Cumberland County, NJ |
Under construction | Operational as of Sep 21, 2026 |
City issued stop-construction orders on LNG tank and fuel cell work, Aug 2026 |
| Perry Township Data Center Canton, Stark County, OH |
Approved | Under construction as of Aug 5, 2026 |
Stark County commissioners approved in June 2026 after township and Canton JEDD approvals |
| Pennsylvania Digital 1 (PAX-1) Middlesex Township, Cumberland County, PA |
Approved | Under construction as of Aug 2, 2026 |
Site-preparation permits granted; Phase 1-B final land development for the first six buildings approved September 2026 |
| Polaris Forge 1 Ellendale, Dickey County, ND |
Under construction as of Jul 26, 2026 |
Building 1 (100 MW) fully energized Nov 2025; Buildings 2–3 under construction/planned | |
| Project Cannoli Van Buren Township, Wayne County, MI |
Approved | Proposed as of Sep 21, 2026 |
Township site plan and tax abatement approvals granted in 2026; DTE power contracts under contested-case review at the Michigan PSC |
| Project Delta Walnut Cove, Stokes County, NC |
Approved | Proposed as of Jul 6, 2026 |
Rezoning re-approved 3-2 on Sept. 14, 2026 after January approval was voided over notice defects; state permits not yet obtained as of January |
| Project Flex New Hudson, Oakland County, MI |
Approved | Proposed as of Sep 9, 2026 |
Conditional site plan approval Sept 2025; final site plan still under Planning Commission review |
| Project Marvel Bessemer, Jefferson County, AL |
Approved | Proposed as of Sep 9, 2026 |
Rezoning approved Nov. 2025 and expanded to 914 acres in April 2026; residents' rezoning lawsuit dismissed with prejudice June 22, 2026. |
| Project Tamarack West Columbia, Mason County, WV |
Approved | Proposed as of Sep 22, 2026 |
Certified by the West Virginia Department of Commerce as a high-impact data center; announced September 3, 2026 |
| Ridgeline Facility Thomas, Tucker County, WV |
Approved | Proposed as of Sep 10, 2026 |
State air permit R13-3713 issued Aug 2025 and upheld by Air Quality Board Feb 2026; appeals court dismissed groups' appeals Aug 2026 for lack of jurisdiction, leaving a path to the WV Supreme Court |
| Fort Meade Hyperscale Data Center Fort Meade, Polk County, FL |
Approved | Proposed as of Sep 10, 2026 |
Developer agreement approved April 2026, contingent on a Southwest Florida Water Management District permit |
| T5 @ Chicago IV Grayslake, Lake County, IL |
Approved | Under construction as of Sep 12, 2026 |
Village issued first building permit Sept. 1, 2026; lawsuit challenging approvals pending |
| Viridian Data Center Campus (former GM/JATCO site) Janesville, Rock County, WI |
Cancelled | Proposed as of Aug 18, 2026 |
City council voted in June 2026 not to extend the letter of intent with Viridian |
| xAI Colossus 2 Memphis, Shelby County, TN |
Under construction | Operational as of Sep 21, 2026 |
Partly in use training Grok while expansion continues; powered largely by gas turbines at a Southaven, MS plant subject to an NAACP Clean Air Act suit |
How the comparison works
Records are matched on a shared distinctive word in the project or developer name and geographic proximity in the same state. Proximity alone is never enough: two unrelated data centers can sit a few hundred metres apart in one industrial park, and a mix-up there would produce a disagreement that is really our own error. 13 Census records found no confident match and are left out rather than guessed at.
Statuses are compared through a crosswalk: proposed ↔ Proposed, approved ↔ Permitted, under construction ↔ Under construction, operating ↔ Operational, cancelled ↔ Cancelled. The 84 agreements are not listed individually; the whole comparison, including them, is in reference.json.
Compute Atlas data retrieved Sep 22, 2026 and used under CC BY 4.0. Their dataset is their work, not ours; any error in the matching above is ours, not theirs.
Think one of these is wrong? Email [email protected] with a source and we will correct the record and say so.
Cite this page
Last updated Sep 22, 2026. Figures may change as records are updated — include the date you retrieved them.
| APA | Data Center Census. (2026). Where we disagree with other trackers. Retrieved from https://datacentercensus.com/cross-check |
|---|---|
| MLA | “Where we disagree with other trackers.” Data Center Census, Sep 22, 2026, https://datacentercensus.com/cross-check. |
| Link | https://datacentercensus.com/cross-check |
Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.