Data Center Census Near me

Augusta Township Data Center (Thor Equities)

Augusta Township, Washtenaw County, MIDeveloper: Thor Equities

Also known as Augusta Township hyperscale data center

DeniedVoters overturned the data center rezoning in the Aug. 4, 2026 referendum, per unofficial results
  1. Rumored
  2. Proposed
  3. Approved
  4. Under construction
  5. Operating
Denied

New York City-based developer Thor Equities proposed a $1-billion hyperscale data center in Augusta Township, and the township board voted unanimously on July 22, 2025 to conditionally rezone 522 acres for it. Residents forced a referendum, and in the Aug. 4, 2026 vote unofficial results showed 2,314 voters, or 89.5%, opposed the rezoning. The vote, if certified, leaves the properties zoned agricultural residential.

Stated investment
$1 billion

Key facts

Size & schedule

Site size522 acres [1]
acreage conditionally rezoned by the township board
Source excerpt
“The Augusta Township board voted unanimously in favor of conditionally rezoning 522 acres for a data center proposed by New York City-based developer Thor Equities July 22, 2025.”
Site size822 acres [3]
total property size as reported in October 2025
Source excerpt
“a data center was proposed for an 822-acre property largely in Augusta Township”
Buildingsat least 5 [3]
Source excerpt
“it would include at least five large buildings on what is currently farmland and wetlands”
Stated investment$1 billion [1]
Source excerpt
“Augusta Township residents will vote on the rezoning of land for a proposed $1-billion hyperscale data center in the Aug. 4 primary”

Water

Water use1,000,000 gal/day [3]
reported as a possible figure ("may consume")
Source excerpt
“The center may consume 1 million gallons of water daily”

Local decisions & site

Deciding voteReferendum Aug. 4, 2026: 2,314 (89.5%) opposed the rezoning, 269 (10.4%) supported it (unofficial) [2]
Source excerpt
“Unofficial results showed 2,314 voters, or 89.5%, opposed the rezoning, while 269, or 10.4%, supported it.”
ZoningSeven parcels rezoned from agricultural residential to general industrial; rezoning overturned by referendum [2]
Source excerpt
“The Augusta Township Board of Trustees had approved rezoning seven parcels from agricultural residential to general industrial.”

Figures are as stated by the cited source. Where sources disagree, each figure is shown.

Timeline

  1. Planning commission recommends denying the rezoning [1]

  2. Township board votes unanimously to conditionally rezone 522 acres for the data center [1]

  3. Residents turn in 957 signatures to put the rezoning on the ballot (561 required) [3]

  4. Voters overturn the rezoning in a referendum, per unofficial results [2]

Issues raised

  • Residents who circulated petitions said the project's power demands could affect utility rates and reliability and bring noise and air pollution [1]
  • The township clerk said the project would generate millions in taxes annually and bring water and sewer lines to parts of the township that lack them [1]
  • Residents have submitted petitions seeking to recall all seven township trustees [2]
  • Township trustees voted to rezone the property from agricultural to industrial before residents forced a referendum [4]

Sources

  1. Augusta Township data center battle reaches the ballot next month
    Planet Detroit · Jul 18, 2026 · news
  2. Weekly Data Center Watch: Augusta Voters Overturn Data Center Rezoning
    The Sun Times News · Aug 6, 2026 · news
  3. Tiny Michigan town hopes to stop data center with ballot initiative
    Bridge Michigan · Oct 14, 2025 · news
  4. Augusta Township voters to decide fate of data center rezoning
    WEMU · Jul 22, 2026 · news