Deep Green, in partnership with the Lansing Board of Water and Light, sought permission to build a 24-megawatt, $120 million data center at Cedar and Kalamazoo streets in downtown Lansing, with 16 megawatts to come from on-site fuel cells and waste heat to be supplied to the utility. The company withdrew its conditional rezoning request on April 6, 2026, and the council president said the proposal will not move forward.
Key facts
Size & schedule
| Planned capacity | 24 MW [1]Source excerpt“Developer Deep Green, in a partnership with Lansing's publicly owned utility, the Board of Water and Light, is seeking permission from the city to build a 24-megawatt data center at the corner of Cedar Street and Kalamazoo Street.” |
|---|---|
| Floor area | 25,000 sq ft [3]Source excerpt“two-story, 25,000-square-foot data center on four lots on Kalamazoo Street between Cedar and Larch streets” |
| Stated investment | $120 million [3]Source excerpt“For the $120 million project to have moved forward, five of eight council members needed to vote yes on a conditional rezoning.” |
How big is that? Data center sizes compared with football fields and Central Park.
Power
| Utility | Lansing Board of Water and Light [1] Utility pages: Lansing Board of Water & Light · data centers and bills Source excerpt“The facility would draw eight megawatts of its power from the Board of Water and Light's existing energy supply.” |
|---|---|
| On-site generation | 16 MW [1]Source excerpt“The remaining 16 megawatts would be generated through on-site fuel cells.” |
| On-site generation type | natural gas fuel cells [3]Source excerpt“two-thirds of the power for the 24-megawatt data center would come from natural gas fuel cells that would be built on site” |
Water
| Water use | less than 500,000 gallons per year [1] annual figure stated by the CEO; no daily figure given Source excerpt“CEO Mark Lee told the Lansing City Council at its Feb. 9 meeting that the facility would use less than 500,000 gallons of water annually” |
|---|
Money & incentives
| Payments / community benefits | Up to $120,000 per year to the Board of Water and Light's Pennies for Power Program [1] |
|---|
Figures are as stated by the cited source. Where sources disagree, each figure is shown.
Water and power
Water
- less than 500,000 gallons per year [1]Projection or estimate. Annual use as stated by the company CEO to the city council.As of Feb 23, 2026 · Demystifying Deep Green's proposed data center near downtown Lansing
Disclosed figures only, each as the cited source states it. Many are projections or permit limits, not metered use. How data center water and power use is measured, and every disclosed figure →
Timeline
Issues raised
- Neighbors at the February 2026 hearing raised concerns about limited community input before rezoning [2]
- The company planned to capture waste heat and feed it back into Lansing's energy system [2]
- Council President Peter Spadafore said the downtown proposal will not move forward [5]
Issues are concerns and claims raised by the parties, officials or residents named in the cited sources. They are reported as attributed, not as findings by the Census.
Sources
- Demystifying Deep Green's proposed data center near downtown LansingMichigan Advance · Feb 23, 2026 · news
- Deep Green data center proposal faces pushback at Lansing City CouncilWILX · Feb 9, 2026 · news
- Deep Green withdraws rezoning request for data center. What we knowLansing State Journal (via AOL) · Apr 6, 2026 · news
- Deep Green Data Center Advances in LansingLansing Regional Chamber of Commerce · Mar 4, 2026 · other
- Company behind Downtown Lansing data center project withdraws application, officials sayWILX · Apr 6, 2026 · news
Cite this page
Last updated Sep 23, 2026. Figures may change as records are updated — include the date you retrieved them.
| APA | Data Center Census. (2026). Deep Green Lansing data center. Retrieved from https://datacentercensus.com/dc/deep-green-downtown-lansing-mi |
|---|---|
| MLA | “Deep Green Lansing data center.” Data Center Census, Sep 23, 2026, https://datacentercensus.com/dc/deep-green-downtown-lansing-mi. |
| Link | https://datacentercensus.com/dc/deep-green-downtown-lansing-mi |
Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.