Data Center Census Near me

Viridian Data Center Campus (former GM/JATCO site)

Janesville, Rock County, WIDeveloper: Viridian

CancelledCity council voted in June 2026 not to extend the letter of intent with Viridian
  1. Rumored
  2. Proposed
  3. Approved
  4. Under construction
  5. Operating

Colorado-based Viridian proposed buying and cleaning up the former General Motors assembly plant site in Janesville, Wisconsin, and converting it into an 11-building, 800-megawatt data center campus with an investment of over $8 billion. The city council approved a letter of intent 5-2 in November 2025, but in June 2026 the council voted not to extend it, taking the data center off the table.

Planned capacity
800 MW[1]
Stated investment
Over $8 billion[1]
over $8 billion, per Viridian
Site size
250 acres[1]
roughly 250-acre site
Permanent jobs (promised)
600
roughly 600, per Viridian estimates

Key facts

Size & schedule

Planned capacity800 MW [1]
Source excerpt
“The project is expected to need up to 800 megawatts of power.”
Site size250 acres [1]
roughly 250-acre site
Source excerpt
“The letter of intent, with Colorado-based Viridian Acquisitions LLC, is the first step towards a project going up on the roughly 250-acre site.”
Buildings11 [2]
Source excerpt
“The site would then be converted to an 11-building, 800 megawatt data center campus.”
Stated investmentOver $8 billion [1]
over $8 billion, per Viridian
Source excerpt
“Erik Zitek, the director of development for Viridian, said the total investment in the campus would be over $8 billion.”
Permanent jobs (promised)600 [2]
roughly 600, per Viridian estimates
Source excerpt
“The project has won the backing of the local chapter of the International Brotherhood of Electrical Workers thanks to Viridian's estimates that it would create roughly 600 permanent jobs, as well as 13,000 jobs during construction.”
Construction jobs1,200 [1]
Viridian estimate, as reported by WPR
Source excerpt
“He said the project could create 1,200 construction jobs and the campus could employ 600 people.”

How big is that? Data center sizes compared with football fields and Central Park.

Power

UtilityAlliant Energy [2]
new substation with Alliant and American Transmission Company, per proposal
Source excerpt
“Viridian and its development partner, Virginia-based Abbleby Strategy Group, would work with Alliant Energy and American Transmission Company to develop a new electrical substation for grid interconnection”

Local decisions & site

Deciding voteJanesville City Council approved the letter of intent 5-2 (November 2025) [1]
Source excerpt
“The council voted 5-2 to approve the letter of intent.”

Figures are as stated by the cited source. Where sources disagree, each figure is shown.

Water and power

Water

Not disclosed. No source reviewed gives a water figure for this site. The Census does not estimate one.

Power

Planned capacity800 MW [1]
UtilityAlliant Energy [2]

Disclosed figures only, each as the cited source states it. Many are projections or permit limits, not metered use. How data center water and power use is measured, and every disclosed figure →

Timeline

  1. City of Janesville begins discussions with Viridian Partners on redeveloping the former GM site [3]

  2. Janesville City Council approves a letter of intent with Viridian 5-2 [1]

  3. City Council places a citizen initiative requiring voter approval for projects over $450 million at the GM/JATCO site on the Nov. 3, 2026 ballot [4]

  4. City Council votes not to extend the letter of intent with Viridian [5]

Issues raised

  • The site requires remediation of contaminated soil, a cleanup estimated at $30 million [2]
  • A citizen initiative on the Nov. 3, 2026 ballot would require voter approval for development over $450 million on undeveloped portions of the GM/JATCO site [4]

Issues are concerns and claims raised by the parties, officials or residents named in the cited sources. They are reported as attributed, not as findings by the Census.

Sources

  1. Janesville moves forward with data center plans for abandoned GM site
    WPR · Nov 11, 2025 · news
  2. No one wanted to redevelop this polluted property. Then came AI.
    E&E News by POLITICO · Mar 30, 2026 · news
  3. Records: City of Janesville, developer launched talks on GM site data center in mid-2024
    The Gazette (gazettextra.com) · May 14, 2026 · news
  4. Janesville, Wisconsin, voters to decide Nov. 3, 2026, initiative requiring approval for development projects exceeding $450 million at GM/JATCO site, such as proposed data center
    Ballotpedia News · Feb 12, 2026 · news
  5. Janesville seeks public input on former GM/JATCO site redevelopment
    WMTV 15 News · Jun 26, 2026 · news

Cite this page

Last updated Sep 22, 2026. Figures may change as records are updated — include the date you retrieved them.

APAData Center Census. (2026). Viridian Data Center Campus (former GM/JATCO site). Retrieved from https://datacentercensus.com/dc/viridian-gm-site-janesville-wi
MLA“Viridian Data Center Campus (former GM/JATCO site).” Data Center Census, Sep 22, 2026, https://datacentercensus.com/dc/viridian-gm-site-janesville-wi.
Linkhttps://datacentercensus.com/dc/viridian-gm-site-janesville-wi

Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.