Viridian is linked to 1 tracked project in Wisconsin, totaling 800 MW of planned capacity. Role: developer.
- Cancelled 1
| Project | Status | Capacity | Developer | Last update |
|---|---|---|---|---|
| Viridian Data Center Campus (former GM/JATCO site) Janesville, Rock County, WI |
Cancelled | 800 MW | Viridian | Jun 2026 |
Recent changes
-
Viridian Data Center Campus (former GM/JATCO site) WI
City Council votes not to extend the letter of intent with Viridian WMTV 15 News -
Viridian Data Center Campus (former GM/JATCO site) WI
City Council places a citizen initiative requiring voter approval for projects over $450 million at the GM/JATCO site on the Nov. 3, 2026 ballot Ballotpedia News -
Viridian Data Center Campus (former GM/JATCO site) WI
Janesville City Council approves a letter of intent with Viridian 5-2 WPR -
Viridian Data Center Campus (former GM/JATCO site) WI
City of Janesville begins discussions with Viridian Partners on redeveloping the former GM site The Gazette (gazettextra.com)
This page lists projects in the Census where Viridian is named as developer by a cited source. It is not a complete list of the company’s facilities.