Polaris Forge 1
Ellendale, Dickey County, NDDeveloper: Applied Digital
Also known as Applied Digital Ellendale campus
- Rumored
- Proposed
- Approved
- Under construction
- Operating
Follow this project
New dated changes arrive in your feed reader or calendar. No account, no email address, no tracking.
- RSS feed for any feed reader
- Atom feed
- Hearings calendar (.ics, subscribes in Apple, Google or Outlook Calendar)
Applied Digital's AI data center campus in Ellendale, North Dakota, with 400 MW of critical IT load fully leased to CoreWeave under 15-year agreements, on a site that began in 2023 as a cryptocurrency hosting facility. The first 100 MW building was fully ready for service in November 2025; a 150 MW second building and 150 MW third building are slated for 2026 and 2027. Applied Digital says the campus could scale to 1 GW. Applied Digital says it delivered the first 75 MW phase of Building 2 on June 30, 2026, bringing live capacity to 175 MW, and that note proceeds will fund a fourth, 150 MW building.
Key facts
Size & schedule
| Planned capacity | Designed to scale to 1 GW over time (company) [2] a stated long-term potential; 400 MW of critical IT load is contracted and 175 MW was live as of June 30, 2026 |
|---|---|
| IT load | 400 MW [1] critical IT load, fully contracted to CoreWeave |
| Phase 1 capacity | 100 MW [1] Building 1 |
| Buildings | 3 [2] 100 MW, 150 MW and 150 MW buildings; in July 2026 Applied Digital said bond proceeds will fund a fourth, 150 MW building [11] |
| Target completion | Full capacity mid-to-late 2027 [5] |
Power
| Utility | Montana-Dakota Utilities [4] Utility pages: Montana-Dakota Utilities · data centers and bills |
|---|---|
| Grid operator | MISO [9] stated for the Applied Digital Ellendale load when the PSC approved the MDU electric service agreement in 2023 Source excerpt“The Applied Digital load will be purchased from the Midcontinent Independent System Operator (MISO) market and will not impact Montana-Dakota customers' power supply.” |
| Power supply | Grid power, which the company and city describe as excess wind power [5] |
| Air permit | ND DEQ Air Pollution Control Permit to Construct ACP-18296 v1.0 (synthetic minor) for the ELN Generation Plant, 9663 87th Ave. SE, Ellendale; posted by DEQ as a draft [10] application dated December 4, 2024, with June 28, 2025 modeling support Source excerpt“Permit Number: ACP-18296 v1.0 Permit Description: Synthetic Minor Source Name & Location: ELN Generation Plant 9663 87th Ave. SE Ellendale, ND 58436” |
Water
| Cooling | closed-loop recirculating water; company calls it waterless cooling [6] |
|---|
Figures are as stated by the cited source. Where sources disagree, each figure is shown.
Water and power
Water
Not disclosed. No source reviewed gives a water figure for this site. The Census does not estimate one.
Disclosed figures only, each as the cited source states it. Many are projections or permit limits, not metered use. How data center water and power use is measured, and every disclosed figure →
Community concerns
Concerns are listed as the cited public sources report them (meeting minutes, dockets, filed cases, official statements and news). They are raised, not validated, and a response is shown beside a concern only where a source reports one. All community concerns →
Electricity rates
- Concern was noted that data centers nearby may raise residential electricity bills.
Raised by: news report · Mar 6, 2026 · Source: KFYR-TVResponse from Applied Digital: The company's CEO said the utility must share revenue back to ratepayers, and the article reports bill rebates of about $70 per year. Mar 6, 2026 · Source: KFYR-TV
Electric bills and your utility →
Traffic and construction
- A Dickey County commissioner described road stability and safety problems on county roads tied to construction traffic, and several roads were closed for repair.
Raised by: elected official (Dickey County Commission) · Apr 21, 2026 · Source: KFGOResponse from Applied Digital: Applied Digital said it is funding about six million dollars in road paving, with work on Highway 11 expected that summer. Jun 4, 2026 · Source: KSJB AM 600
Something missing or wrong? Ask for a review. Posts on social media are never used as sources.
Timeline
Construction begins at the Ellendale campus [3]
North Dakota Public Service Commission unanimously approves Montana-Dakota Utilities' electric service agreement to serve Applied Digital's data center near Ellendale [9]
Applied Digital petitions to annex the data center into the city of Ellendale [7]
Applied Digital signs 250 MW of 15-year leases with CoreWeave (~$7 billion) [3]
CoreWeave signs additional 150 MW lease, bringing Polaris Forge 1 to 400 MW [2]
Phase I of Building 1 reaches ready for service [1]
Phase II ready for service; Building 1 fully energized at 100 MW [1]
Dickey County closes several roads damaged by construction traffic [8]
Applied Digital says it delivered Phase 1 of Building 2 (75 MW), bringing live capacity at the campus to 175 MW [11]
Applied Digital says proceeds of a senior secured notes offering will fund construction of a fourth building (150 MW) at Polaris Forge 1 [11]
Issues raised
- Construction traffic has damaged county roads, leading to closures; repairs funded jointly by state grant, city, county and Applied Digital [8]
- Rents in Ellendale have roughly doubled and some lower-income families have moved, per South Dakota Searchlight [4]
- Residents report an audible hum from the site's first (crypto) facility within about a mile [4]
- Montana-Dakota Utilities customers have received rate credits tied to the data center load [4][5]
Issues are concerns and claims raised by the parties, officials or residents named in the cited sources. They are reported as attributed, not as findings by the Census.
Sources
- Applied Digital Completes Phase II Ready for Service at Polaris Forge 1, Fully Energizing First 100 MW BuildingApplied Digital · Nov 24, 2025 · company
- Applied Digital Finalizes Additional 150MW Lease with CoreWeave in North DakotaApplied Digital · Aug 29, 2025 · company
- Applied Digital signs 250MW agreement with CoreWeave for capacity at Ellendale campus, North DakotaDatacenterDynamics · Jun 2, 2025 · news
- North Dakota town serves as an example of the promise and perils of data centers for South DakotaSouth Dakota Searchlight · Jan 30, 2026 · news
- Ellendale acts as test case for data centersKFYR-TV · Mar 6, 2026 · news
- DCL: Applied Digital Answers Ellendale AI Data Center Questions on Roads and WaterKSJB AM 600 · Jun 4, 2026 · news
- Data center requests annexation into EllendaleNorth Dakota Monitor · Dec 10, 2024 · news
- Vehicles tied to AI data center construction causing severe road damage in Dickey CountyKFGO · Apr 21, 2026 · news
- MDU Resources Subsidiary Receives Regulatory Approval to Serve Large Data Center Electric LoadMDU Resources (PR Newswire) · Jun 6, 2023 · company
- Air Pollution Control Permit to Construct ACP-18296 v1.0 (draft)North Dakota Department of Environmental Quality · government
- Applied Digital Reports Fiscal Fourth Quarter and Full Year 2026 ResultsApplied Digital · Jul 27, 2026 · company
Cite this page
Last updated Sep 23, 2026. Figures may change as records are updated — include the date you retrieved them.
| APA | Data Center Census. (2026). Polaris Forge 1. Retrieved from https://datacentercensus.com/dc/polaris-forge-1-ellendale-nd |
|---|---|
| MLA | “Polaris Forge 1.” Data Center Census, Sep 23, 2026, https://datacentercensus.com/dc/polaris-forge-1-ellendale-nd. |
| Link | https://datacentercensus.com/dc/polaris-forge-1-ellendale-nd |
Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.