CoreWeave data centers: tracked projects and locations

CoreWeave is linked to 4 tracked projects in Texas, Pennsylvania, North Dakota, totaling 2.56 GW of planned capacity. Role: developer and tenant.

Ranked #55 of 59 developers by the published capacity of its tracked projects that are proposed, approved, under construction or operating, as developer or operator (260 MW). See the ranking →

ProjectStatusCapacityDeveloperLast update
Core Scientific Denton Data Center
Denton, Denton County, TX
Operating 260 MW CoreWeave, Core Scientific Jan 13, 2026
CoreWeave Lancaster data center
Lancaster, Lancaster County, PA
Under construction 300 MW Chirisa Technology Parks Sep 21, 2026
Galaxy Helios
Afton, Dickens County, TX
Under construction 1.6 GW Galaxy Digital Jul 22, 2026
Polaris Forge 1
Ellendale, Dickey County, ND
Operating 400 MW Applied Digital Jul 27, 2026

Latest CoreWeave data center news

The newest dated changes at CoreWeave’s tracked projects, each from the filing, notice or report linked beside it.

  1. CoreWeave Lancaster data center PA
    Judge grants the developers' emergency motion to stay the zoning hearing on the residents' group appeal of the second Greenfield Road building LancasterOnline
  2. CoreWeave Lancaster data center PA
    Residents' group appeals planning commission's conditional preliminary approval of a second Greenfield Road data center LancasterOnline
  3. Polaris Forge 1 ND
    Applied Digital says proceeds of a senior secured notes offering will fund construction of a fourth building (150 MW) at Polaris Forge 1 Applied Digital
  4. Galaxy Helios TX
    Galaxy subsidiary Galaxy Helios Data Centers II offers $3.507 billion of senior secured notes to fund two buildings with eight data halls TheEnergyMag
  5. Polaris Forge 1 ND
    Applied Digital says it delivered Phase 1 of Building 2 (75 MW), bringing live capacity at the campus to 175 MW Applied Digital
  6. Polaris Forge 1 ND
    Dickey County closes several roads damaged by construction traffic KFGO
  7. Galaxy Helios TX
    Permits show about $3.5 billion for Phase 2 buildings Helios 2, 3 and 4 KTSM 9 News
  8. CoreWeave Lancaster data center PA
    Report that lenders passed on construction financing; CoreWeave says project is fully funded and moving forward LancasterOnline

This page lists projects in the Census where CoreWeave is named as developer or a publicly reported tenant by a cited source. It is not a complete list of the company’s facilities, and this page is not affiliated with or endorsed by CoreWeave.