Stafford Technology Campus

Stafford County, VADeveloper: STACK Infrastructure

Under constructionFirst building topped out in May 2026; rezoning approved September 2024
  1. Rumored
  2. Proposed
  3. Approved
  4. Under construction
  5. Operating

Stafford Technology Campus is Stafford County's largest approved data center project, on about 504 acres on both sides of Eskimo Hill Road near the Rappahannock Regional Landfill, planned at approximately 5.5 million square feet with 23 buildings and six substations. The Board of Supervisors approved the rezoning 6-1 in September 2024, and the rezoned property was sold for $302.3 million to an entity representing Stack Infrastructure. County figures now list the campus at 5.8 million square feet and 20 buildings. Stack held a topping-out ceremony for the first building in May 2026, and the Fredericksburg Free Press reports that Stack is partnering with Amazon Web Services on the project.

Planned capacity
1 GW[8]
1 gigawatt, as reported
Site size
504 acres[2]

Key facts

Size & schedule

Planned capacity1 GW [8]
1 gigawatt, as reported
Source excerpt
“will be able to draw and distribute 1 gigawatt of electrical power”
Site size504 acres [2]
Source excerpt
“The board voted to allow 504 acres on both sides of Eskimo Hill Road to be rezoned from agricultural to light industrial”
Floor area5.5 million sq ft [2]
as approved in 2024
Source excerpt
“The campus itself is estimated at approximately 5.5 million square feet.”
Floor area5.8 million sq ft [4]
county 'Approved Data Center Sites' table
Source excerpt
“Stafford Technology Campus | 5,800,000 | 20”
Buildings23 [2]
as approved in 2024
Source excerpt
“a data center campus with 23 buildings and six electric substations”
Buildings20 [4]
county 'Approved Data Center Sites' table
Source excerpt
“Stafford Technology Campus | 5,800,000 | 20”
Construction jobs1,000 [9]
company statement: over 1,000 at peak
Source excerpt
“over 1,000 construction jobs during peak development”

How big is that? Data center sizes compared with football fields and Central Park.

Power

UtilityDominion Energy [9]
company statement: six 300 MW substations
Source excerpt
“six 300MW substations supplied by Dominion Energy”

Water

Water sourceReclaimed (purple pipe) water [9]
company statement, for permanent industrial cooling
Source excerpt
“re-claimed (purple pipe) water system for permanent industrial cooling”

Money & incentives

Payments / community benefitsDeveloper agreed to fund $58 million in county capital improvement projects, including water and sewer infrastructure [2]
Source excerpt
“The developer, Peterson Cos., has also agreed to fund $58 million in capital improvement projects for the county”

Local decisions & site

Deciding voteStafford Board of Supervisors approved rezoning 6-1 (September 2024) [2]
Source excerpt
“In a 6-to-1 vote, the supervisors approved the county's largest data center project to date.”
ZoningRezoned from agricultural to light industrial [2]
Source excerpt
“rezoned from agricultural to light industrial with the intent that the property become a data center campus”

Figures are as stated by the cited source. Where sources disagree, each figure is shown.

Water and power

Water

Not disclosed. No source reviewed gives a water figure for this site. The Census does not estimate one.

Power

Planned capacity1 GW [8]
UtilityDominion Energy [9]

Disclosed figures only, each as the cited source states it. Many are projections or permit limits, not metered use. How data center water and power use is measured, and every disclosed figure →

Timeline

  1. Supervisors defer vote on the rezoning after a late proffer statement [1]

  2. Board of Supervisors approves the rezoning 6-1 [2]

  3. Stafford Technology LC sells the roughly 500-acre property for $302.3 million to an entity representing Stack Infrastructure [3]

  4. Board of Supervisors unanimously grandfathers the campus and four other projects under pre-October 2025 rules [5]

  5. Stack holds a topping-out ceremony for the first building on the campus [6]

Issues raised

  • Supervisors cited energy use, road improvements and water usage as concerns [1]
  • The lone dissenting supervisor raised concerns about project phasing and the use of potable water before a water reuse system is built [2]

Issues are concerns and claims raised by the parties, officials or residents named in the cited sources. They are reported as attributed, not as findings by the Census.

Sources

  1. Stafford supervisors defer vote on Stafford Technology Campus
    Fredericksburg Free Press · Aug 21, 2024 · news
  2. A big deal: Stafford's largest data center gets green light
    Fredericksburg Free Press · Sep 19, 2024 · news
  3. Biz Beat Roundup: $302M land sale closes in Stafford
    Fredericksburg Free Press · Feb 5, 2025 · news
  4. Data Centers
    Stafford County · government
  5. Stafford supervisors grandfather five data center projects that predate new regulations
    Fredericksburg Free Press · Dec 4, 2025 · news
  6. Biz Beat Roundup: Fredericksburg Regional Alliance gets new name, brand
    Fredericksburg Free Press · May 13, 2026 · news
  7. Stack tops out first building at 1GW data center campus in Stafford County, Virginia
    DatacenterDynamics · May 26, 2026 · news
  8. 'You have to talk neighbor-to-neighbor about this:' League of Women Voters holds community conversation on data centers
    Fredericksburg Free Press · Sep 22, 2026 · news
  9. STACK Infrastructure Announces Landmark 1+GW Stafford Technology Campus in Northern Virginia
    STACK Infrastructure · Jan 16, 2025 · company

Cite this page

Last updated Sep 24, 2026. Figures may change as records are updated — include the date you retrieved them.

APAData Center Census. (2026). Stafford Technology Campus. Retrieved from https://datacentercensus.com/dc/stafford-technology-campus-stafford-county-va
MLA“Stafford Technology Campus.” Data Center Census, Sep 24, 2026, https://datacentercensus.com/dc/stafford-technology-campus-stafford-county-va.
Linkhttps://datacentercensus.com/dc/stafford-technology-campus-stafford-county-va

Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.