Crossroads Technology Campus
Spotsylvania County, VA
Also known as SUP26-0003
ProposedPlanning Commission recommended approval 4-2 in September 2026; Board of Supervisors decision pending
- Rumored
- Proposed
- Approved
- Under construction
- Operating
Crossroads Technology Campus is a proposed data center campus of about 555 acres in Spotsylvania County's Lee Hill District, with seven 100-megawatt data center buildings totaling about 2.1 million square feet and three substation sites. The applicant is RCK Digital Crossroads LLC, and an attorney for the developers said Amazon is the end user. The Planning Commission voted 4-2 to recommend approval of the special use permit in September 2026 over resident objections.
- Site size
- 555.05 acres
- Water use
- 1,000,000 gal/day
- reuse water for cooling
Key facts
Size & schedule
| Planned capacity | 894 MW [2] estimated electric load on utility information form Source excerpt“Estimated Electric Load (MW): 894MW” |
|---|---|
| Site size | 555.05 acres [1]Source excerpt“consisting of approximately 555.05 acres” |
| Floor area | 2.1 million sq ft [1]Source excerpt“approximately 2.1 million square-feet of data center buildings” |
| Buildings | 7 [1]Source excerpt“seven 100-megawatt data center buildings” |
Power
| Utility | Rappahannock Electric Cooperative (distribution); Dominion Energy (transmission) [2]Source excerpt“Anticipated Transmission Voltage: 230kV. The transmission provider for the Project Location is: Dominion Energy.” |
|---|
Water
| Water use | 1,000,000 gal/day [1] reuse water for cooling Source excerpt“1 million gallons of reuse water per day” |
|---|---|
| Water source | Reuse water; potable water not to be used for cooling [1]Source excerpt“potable water will not be used” |
Local decisions & site
| Zoning | Special use permit (SUP26-0003) [4]Source excerpt“SUP26-0003 Crossroads Technology Campus” |
|---|---|
| Parcel / address | Tax Map Parcels 37-A-20, 37-A-21 and 37-A-17D [1]Source excerpt“Tax Map Parcels 37-A-20, 37-A-21, and 37-A-17D” |
| Nearest homes or schools | Minimum 400-foot building setback from residentially zoned properties and 300-foot vegetated buffer (conditions) [3]Source excerpt“a minimum 400-foot building setback from residentially zoned properties” |
Figures are as stated by the cited source. Where sources disagree, each figure is shown.
Timeline
Issues raised
Sources
- SUP26-0003 Crossroads Technology Campus: 5th Submission NarrativeSpotsylvania County · Aug 26, 2026 · government
- REC High Energy Use Facility (HEUF) Utility Information Form – Crossroads Technology CampusSpotsylvania County · Aug 7, 2026 · government
- Spotsylvania Planning Commission recommends approval of 555-acre data center campusFredericksburg Free Press · Sep 17, 2026 · news
- Data Center FAQsSpotsylvania County · government
- At a Crossroads: Spotsylvania residents pack meetings this week to challenge data center projectFredericksburg Free Press · Jul 16, 2026 · news