Amazon (AWS) is linked to 19 tracked projects in Minnesota, Indiana, Georgia, Maryland, Mississippi, Pennsylvania, Ohio, Virginia, Missouri, North Carolina, totaling 1.74 GW of planned capacity. Role: developer and tenant.

Ranked #41 of 59 developers by the published capacity of its tracked projects that are proposed, approved, under construction or operating, as developer or operator (600 MW). See the ranking →

ProjectStatusCapacityDeveloperLast update
Amazon Becker Data Center
Becker, Sherburne County, MN
Paused 600 MW Amazon (AWS) May 23, 2025
Amazon Hobart data center
Hobart, Lake County, IN
Approved — Amazon (AWS) Feb 2026
Amazon Web Services Butts County data center campus
Jackson, Butts County, GA
Approved — Amazon (AWS) 2027
Calvert Technology Center
Lusby, Calvert County, MD
Cancelled 500 MW Amazon (AWS) Aug 4, 2026
Amazon Web Services Madison County Mega Site campus
Canton, Madison County, MS
Operating — Amazon (AWS) Aug 17, 2026
Falls Township Innovation Campus
Falls Township, Bucks County, PA
Under construction — Amazon (AWS) Aug 2026
AWS Fayette County Data Center Campus
Jeffersonville, Fayette County, OH
Approved — Amazon (AWS) Jan 10, 2025
Amazon Data Services King George campus (former Birchwood power plant site)
King George County, VA
Paused — Amazon (AWS) Aug 26, 2026
Amazon Web Services Louisa County campuses
Louisa, Louisa County, VA
Under construction 600 MW Amazon (AWS) Aug 1, 2026
Amazon Web Services data center campus, Madison and St. Clair townships
Butler County, OH
Proposed — Amazon (AWS) Nov 3, 2026
Project Galaxy (AWS Sidney data center)
Sidney, Shelby County, OH
Approved — Amazon (AWS) Mar 5, 2026
AWS Project Green
New Florence, Montgomery County, MO
Approved — Amazon (AWS) Sep 18, 2026
Amazon Web Services Richmond County data center campus
Hamlet, Richmond County, NC
Under construction — Amazon (AWS) Nov 2026
Salem Township Innovation Campus
Salem Township, Luzerne County, PA
Under construction — Amazon (AWS) Oct 2025
Amazon Web Services Warrenton Data Center
Warrenton, Fauquier County, VA
Approved — Amazon (AWS) Jul 30, 2026
AWS Wilmington data center
Wilmington, Clinton County, OH
Approved — Amazon (AWS) Sep 18, 2026
Crossroads Technology Campus
Spotsylvania County, VA
Proposed 894 MW RCK Digital Crossroads LLC Sep 16, 2026
Project Rainier (AWS New Carlisle campus)
New Carlisle, St. Joseph County, IN
Operating — Amazon (AWS) Sep 22, 2026
Project Mila
Trenton, Butler County, OH
Under construction 250 MW Prologis Nov 3, 2026

Latest Amazon (AWS) data center news

The newest dated changes at Amazon (AWS)’s tracked projects, each from the filing, notice or report linked beside it.

  1. Amazon Web Services Butts County data center campus GA
    PILOT payments to county, schools and development authority scheduled to begin Jackson Progress-Argus
  2. Amazon Web Services data center campus, Madison and St. Clair townships OH
    Trenton voters pass Issue 17, barring data centers over 25 MW in city limits, with about 80% (unofficial results, not yet certified); WVXU says it blocks plans for Trenton to annex land for a 1,000 MW Amazon data center WVXU
  3. Project Mila OH
    Trenton voters pass Issue 17, a charter amendment barring data centers over 25 MW, with about 80% of the vote (unofficial Butler County Board of Elections results, not yet certified). WVXU says it puts the 250 MW Prologis facility into question; Prologis told WCPO the result does not affect its project, and whether the project has vested rights is unsettled. Work so far is site work WVXU
  4. Amazon Web Services data center campus, Madison and St. Clair townships OH
    AWS holds a community meeting at Edgewood Middle School in Trenton; residents ask about water, workforce, power and backup generators FOX19
  5. Project Rainier (AWS New Carlisle campus) IN
    St. Joseph County Council advances, on a 6-3 vote, a resolution that would bar new hyperscale data centers from the county ABC57
  6. AWS Project Green MO
    Cole County Circuit Judge Cotton Walker denies most of the motion to dismiss and finds the group has standing KBIA / Columbia Missourian
  7. AWS Wilmington data center OH
    Supreme Court of Ohio rules the initiative cannot appear on the Nov. 3 ballot Court News Ohio