Salem Township Innovation Campus
Salem Township, Luzerne County, PADeveloper: Amazon (AWS)
Also known as Cumulus data center campus, Amazon Susquehanna campus
- Rumored
- Proposed
- Approved
- Under construction
- Operating
Follow this project
New dated changes arrive in your feed reader or calendar. No account, no email address, no tracking.
- RSS feed for any feed reader
- Atom feed
- Hearings calendar (.ics, subscribes in Apple, Google or Outlook Calendar)
Amazon is building a campus on 1,200 acres next to the Susquehanna Steam Electric Station nuclear plant. Amazon expects the campus to hold 20 data centers and support about 1,000 permanent jobs when fully built. Talen Energy has a 1,920-MW power purchase agreement with AWS running through 2042. Construction started in October 2025.
- Site size
- 1,200 acres[1]
- Permanent jobs (promised)
- 1,000
- approximately
Key facts
Size & schedule
| Site size | 1,200 acres [1]Source excerpt“1,200 acres” |
|---|---|
| Buildings | 20 [1] data centers anticipated at full build-out Source excerpt“When fully constructed, Amazon anticipates that the campus will contain 20 data centers” |
| Stated investment | At least $20 billion, Amazon's statewide Pennsylvania commitment [1] statewide commitment that also covers the Falls Township campus, not this campus alone Source excerpt“Amazon is planning to invest at least $20 billion” |
| Permanent jobs (promised) | 1,000 [1] approximately Source excerpt“support approximately 1,000 permanent jobs” |
How big is that? Data center sizes compared with football fields and Central Park.
Power
| Utility | PPL Electric Utilities (transmission and delivery); Talen Energy as retail power supplier [4] Utility pages: PPL Electric Utilities · data centers and bills Source excerpt“Talen will act as the retail power supplier to AWS, and PPL Electric Utilities will be responsible for transmission and delivery.” |
|---|---|
| Grid operator | PJM [6]Source excerpt“Chairman Phillips' Dissent in PJM's Susquehanna Co-Location Proposal, ER24-2172” |
| Power supply | Susquehanna nuclear plant via a 1,920-MW Talen Energy power purchase agreement running through 2042 [4]Source excerpt“Talen Energy has entered into a 1,920-MW power purchase agreement with Amazon Web Services to supply data centers in Pennsylvania from the independent power producer's majority-owned Susquehanna nuclear power plant.” |
| Utility commission case | FERC Docket ER24-2172 (amended Susquehanna interconnection service agreement) [6]Source excerpt“Chairman Phillips' Dissent in PJM's Susquehanna Co-Location Proposal, ER24-2172” |
Water
| Water source | Susquehanna River, via Talen Energy's existing infrastructure and withdrawal docket [1]Source excerpt“Amazon is working alongside Talen Energy to source water Talen's existing infrastructure and withdrawal docket from the Susquehanna River” |
|---|---|
| Cooling | Outside-air cooling most of the year; water-based cooling less than 2% of the year [1]Source excerpt“Amazon expects to use outside cooling for most of the year and only use water-based cooling for less than 2% of the year” |
Figures are as stated by the cited source. Where sources disagree, each figure is shown.
Water and power
Water
Not disclosed. No source reviewed gives a water figure for this site. The Census does not estimate one.
Disclosed figures only, each as the cited source states it. Many are projections or permit limits, not metered use. How data center water and power use is measured, and every disclosed figure →
Timeline
Amazon pays Talen Energy $650 million for its Cumulus data center campus [3]
FERC rejects an amended interconnection agreement that would have raised the behind-the-meter connection to 480 MW from 300 MW [5]
Amazon announces at least $20 billion for data center complexes in Pennsylvania, including the Salem Township site [2]
Talen and AWS sign a 1,920-MW PPA; the existing 300-MW co-location arrangement moves to a front-of-the-meter framework [4]
Construction starts [1]
Sources
- Salem Township Innovation Campus - Amazon Innovation Campuses in PennsylvaniaAmazon · Sep 8, 2026 · company
- Amazon will spend $20 billion to build two data centers in PennsylvaniaThe Philadelphia Inquirer · Jun 9, 2025 · news
- Developers tout impacts of 3 data center campuses; Zoning meeting set for Wednesday on 4-3 Glenbrook Group projectTimes Leader · Aug 22, 2026 · news
- Talen to sell Amazon 1.9 GW from Susquehanna nuclear plantUtility Dive · Jun 11, 2025 · news
- FERC rejects interconnection pact for Talen-Amazon data center deal at nuclear plantUtility Dive · Nov 4, 2024 · news
- Chairman Phillips' Dissent in PJM's Susquehanna Co-Location Proposal, ER24-2172Federal Energy Regulatory Commission · Nov 1, 2024 · government
Cite this page
Last updated Sep 23, 2026. Figures may change as records are updated — include the date you retrieved them.
| APA | Data Center Census. (2026). Salem Township Innovation Campus. Retrieved from https://datacentercensus.com/dc/aws-salem-township-susquehanna-pa |
|---|---|
| MLA | “Salem Township Innovation Campus.” Data Center Census, Sep 23, 2026, https://datacentercensus.com/dc/aws-salem-township-susquehanna-pa. |
| Link | https://datacentercensus.com/dc/aws-salem-township-susquehanna-pa |
Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.