STACK Infrastructure is linked to 1 tracked project in New Mexico, totaling 2.46 GW of planned capacity. Role: developer.

ProjectStatusCapacityDeveloperLast update
Project Jupiter
Santa Teresa, Doña Ana County, NM
Under construction 2.46 GW STACK Infrastructure Sep 17, 2026

Recent changes

  1. Project Jupiter NM
    NM Supreme Court denies petitions and lifts stay KVIA
  2. Project Jupiter NM
    Attorney General Raúl Torrez files responses backing emergency petitions New Mexico Department of Justice
  3. Project Jupiter NM
    NM Supreme Court stays air-permit proceeding and well drilling KVIA
  4. Project Jupiter NM
    Oracle says Bloom fuel cells will power campus; ~700 New Mexicans working onsite Oracle
  5. Project Jupiter NM
    County Commission orders review of developer statements, including on closed-loop cooling and water Doña Ana County
  6. Project Jupiter NM
    OpenAI and Oracle name Doña Ana County a Stargate site OpenAI
  7. Project Jupiter NM
    Doña Ana County Commission approves industrial revenue bonds Doña Ana County