ProposedMarketed as a 300 MW data center site; the Town of Lysander adopted a six-month moratorium in May 2026
  1. Rumored
  2. Proposed
  3. Approved
  4. Under construction
  5. Operating

Ranalli Super DC, LLC has marketed a 124-acre vacant industrial-zoned property near Hencle Boulevard and Oswego Road in the Town of Lysander as a 300-megawatt data center site, listed for sale at $40 million. No end user has been named. A citizens' petition against it gathered more than 1,500 signatures, and after a town board work session on April 18, 2026, the board voted 5-0 to have the town attorney draft a moratorium. Lysander adopted a six-month moratorium on May 7, 2026, at a meeting more than 350 residents attended.

Planned capacity
300 MW
as marketed in the property listing
Site size
124 acres
vacant, industrial-zoned property

Key facts

Size & schedule

Planned capacity300 MW [1]
as marketed in the property listing
Source excerpt
“300 MW Data Center Site”
Site size124 acres [1]
vacant, industrial-zoned property
Source excerpt
“124-acre vacant, industrial-zoned property”

Local decisions & site

ZoningIndustrial; town adopted a six-month moratorium on new data center applications on May 7, 2026 [2]
Parcel / addressNear the intersection of Hencle Boulevard and Oswego Road, Town of Lysander [1]

Figures are as stated by the cited source. Where sources disagree, each figure is shown.

Timeline

  1. Lysander Town Board work session and regular meeting; the board votes 5-0 to authorize the town attorney to begin drafting a data center moratorium after a petition gathers more than 1,500 signatures [1]

  2. Lysander Town Board adopts a six-month moratorium at a meeting more than 350 residents attend to oppose the project [2]

  3. Gov. Kathy Hochul signs Executive Order No. 62, pausing state DEC permits for data centers of 50 MW or more [3]

Issues raised

  • The site is marketed as a 300 MW data center site, but no developer has filed an application and no end user has been named [1]
  • The group Citizens Against Lysander Data Center cited the project's scale, its proximity to the Three Rivers Wildlife Management Area, water consumption, noise and pollution [1]
  • Town Supervisor Kevin Rode said the board shares community concerns about a data center [1]
  • Lysander's six-month moratorium was one of several adopted by central New York towns in 2026 [2]

Sources

  1. Possible massive data center in Lysander faces community opposition, town attorney to draft moratorium
    Baldwinsville Messenger / Eagle News Online · Apr 20, 2026 · news
  2. Updates on the Cloud: More Moratoriums on Data Centers
    Rockefeller Institute of Government · Jun 10, 2026 · other
  3. Executive Order No. 62: Establishing a Temporary Moratorium on Data Centers in New York
    Office of the Governor of New York · Jul 14, 2026 · government

Cite this page

Last updated Sep 22, 2026. Figures may change as records are updated — include the date you retrieved them.

APAData Center Census. (2026). Ranalli Lysander Data Center. Retrieved from https://datacentercensus.com/dc/ranalli-lysander-ny
MLA“Ranalli Lysander Data Center.” Data Center Census, Sep 22, 2026, https://datacentercensus.com/dc/ranalli-lysander-ny.
Linkhttps://datacentercensus.com/dc/ranalli-lysander-ny

Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.