Data Center Census Near me

Lake Mariner

Somerset, Niagara County, NYDeveloper: TeraWulf

Also known as TeraWulf Lake Mariner

Operating102 MW of AI capacity online July 2026; 336 MW (CB-4, CB-5) under construction
  1. Rumored
  2. Proposed
  3. Approved
  4. Under construction
  5. Operating

TeraWulf's data center campus on the site of a former coal-fired power plant in Somerset, Niagara County, New York, which began with bitcoin mining and is expanding into AI hosting for Fluidstack, with Google backstopping part of Fluidstack's lease obligations. TeraWulf reported 102 MW of revenue-generating AI capacity online in July 2026, with 336 MW more under construction in buildings CB-4 and CB-5. Power comes mainly from New York Power Authority hydropower plus NYSEG.

Key facts

Size & schedule

Planned capacity750 MW [4]
total power allocated from NYSEG and NYPA, per Niagara Gazette [4]; Techzine [8] says the campus is designed for up to 750 MW at full buildout
Planned capacity750 MW [8]
campus designed to support up to this power demand at full buildout
Source excerpt
“up to 750 MW of power demand at full buildout”
IT load360 MW [2]
Fluidstack total contracted critical IT at Lake Mariner after the CB-5 lease; release says approximately 360 MW
Source excerpt
“increases to approximately 360 MW”
IT load102 MW [3]
revenue-generating critical IT capacity online at Lake Mariner after CB-3 delivery in early July 2026 (81 MW as of June 30, 2026)
Source excerpt
“102 MW of revenue-generating critical IT capacity online at Lake Mariner”
IT load336 MW [3]
additional critical IT capacity under construction across CB-4 and CB-5 (second set of IT MW; the 360 MW Fluidstack figure above is contracted)
Source excerpt
“additional 336 MW across CB-4 and CB-5”
Site size410 acres [4]
total parcel; the 61-acre expansion sits in the northeast corner of it
Buildings2 [3]
CB-4 and CB-5 under construction (CB-3 delivered July 2026)
Source excerpt
“additional 336 MW across CB-4 and CB-5”
Permanent jobs (promised)150 [4]
potential full-time workforce with AI buildings, up from 52
Target completionCB-4 phased delivery H2 2026; CB-5 early 2027 [3]

How big is that? Data center sizes compared with football fields and Central Park.

Power

Power supplyAbout 90% hydropower from New York Power Authority, remainder NYSEG [4]; dual 345 kV transmission lines [2] [4]
Source excerpt
“dual 345 kV transmission lines”

Water

Coolingclosed-loop water cooling [1]

Money & incentives

Tax incentivesNew York State internet data center sales tax exemption; Niagara County disputes Lake Mariner's eligibility and has authorized legal action [7]
Source excerpt
“The Legislature is concerned this decades-old exemption is being wrongly claimed by internet data centers like Lake Mariner in the Town of Somerset, costing state and local governments millions in tax dollars.”

Local decisions & site

ZoningPlanned Unit Development district amendment, site plan, SEQR review and special use permit [4]
Source excerpt
“a special joint planning board and town board meeting would be held on Thursday night for approving an amendment to the Planned Unit Development district where the data centers are located, a site plan, SEQR review, and a special use permit.”

Figures are as stated by the cited source. Where sources disagree, each figure is shown.

Water and power

Water

Not disclosed. No source reviewed gives a water figure for this site. The Census does not estimate one.

Power

Planned capacity750 MW [4]
IT load360 MW [2]
Power supplyAbout 90% hydropower from New York Power Authority, remainder NYSEG (s4); dual 345 kV transmission lines (s2) [4]

Disclosed figures only, each as the cited source states it. Many are projections or permit limits, not metered use. How data center water and power use is measured, and every disclosed figure →

Timeline

  1. TeraWulf plans AI buildings; Niagara County Planning Board review and town hearing scheduled [5]

  2. TeraWulf signs 200+ MW, 10-year hosting agreements with Fluidstack; Google backstops $1.8 billion [1]

  3. Fluidstack adds 160 MW CB-5 lease; Google backstop rises to about $3.2 billion [2]

  4. Somerset Planning Board and Town Board unanimously approve expansion on 61 acres [4]

  5. CB-3 delivered, bringing AI capacity online to 102 MW [3]

Issues raised

  • A nearby resident reports noise disrupting sleep; some criticize adjacent solar expansion [6]
  • Local Assemblyman Paul Bologna supports the project as good for Niagara County [6]

Issues are concerns and claims raised by the parties, officials or residents named in the cited sources. They are reported as attributed, not as findings by the Census.

Sources

  1. TeraWulf Signs 200+ MW, 10-Year AI Hosting Agreements with Fluidstack
    TeraWulf · Aug 14, 2025 · company
  2. TeraWulf Announces Fluidstack Expansion with 160 MW CB-5 Lease at Lake Mariner
    TeraWulf · Aug 18, 2025 · company
  3. TeraWulf Reports Second Quarter 2026 Results
    TeraWulf · Aug 5, 2026 · company
  4. Lake Mariner campus adding more AI data center capacity
    Niagara Gazette (via Yahoo Finance) · Oct 25, 2025 · news
  5. New Somerset, N.Y., Data Center Buildings Would House AI
    Lockport Union-Sun & Journal (via GovTech) · Oct 8, 2024 · news
  6. Proposed data centers dividing New Yorkers
    Spectrum News State of Politics · Jul 7, 2026 · news
  7. Niagara County Legislature Calls on Hochul to Audit Internet Sales Tax Exemption
    Niagara County (via EIN Presswire) · Aug 6, 2026 · government
  8. Schneider Electric delivers AI infrastructure for TeraWulf campus set to reach 750 MW
    Techzine · May 26, 2026 · news

Cite this page

Last updated Nov 5, 2026. Figures may change as records are updated — include the date you retrieved them.

APAData Center Census. (2026). Lake Mariner. Retrieved from https://datacentercensus.com/dc/lake-mariner-somerset-ny
MLA“Lake Mariner.” Data Center Census, Nov 5, 2026, https://datacentercensus.com/dc/lake-mariner-somerset-ny.
Linkhttps://datacentercensus.com/dc/lake-mariner-somerset-ny

Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.