TeraWulf is linked to 2 tracked projects in New York, totaling 1.05 GW of planned capacity. Role: developer.
- Proposed 1
- Operating 1
Ranked #35 of 59 developers by the published capacity of its tracked projects that are proposed, approved, under construction or operating, as developer or operator (1.05 GW). See the ranking →
| Project | Status | Capacity | Developer | Last update |
|---|---|---|---|---|
| Lake Mariner Somerset, Niagara County, NY |
750 MW | TeraWulf | Jul 2026 | |
| Lake Hawkeye Lansing, Tompkins County, NY |
Proposed | 300 MW | TeraWulf | Aug 4, 2026 |
Latest TeraWulf data center news
The newest dated changes at TeraWulf’s tracked projects, each from the filing, notice or report linked beside it.
-
Lake Hawkeye NY
Statewide reporting describes the project as facing legal challenges, with the town planning board requesting additional work Spectrum News / NY State of Politics -
Lake Hawkeye NY
Gov. Kathy Hochul signs Executive Order No. 62, pausing state DEC permits for data centers of 50 MW or more Office of the Governor of New York -
Lake Hawkeye NY
Tompkins County Legislature votes 14-1, with one recusal, to urge the DEC to reject the water withdrawal permit application and require a new application with environmental review Ithaca Times -
Lake Hawkeye NY
Town of Lansing Zoning Board of Appeals determines that a data center fits the permitted land use at the site Ithaca Times -
Lake Hawkeye NY
Tensions over the proposal grow in Tompkins County as opponents threaten litigation The Cornell Daily Sun -
Lake Mariner NY
Somerset Planning Board and Town Board unanimously approve expansion on 61 acres Niagara Gazette (via Yahoo Finance)
This page lists projects in the Census where TeraWulf is named as developer by a cited source. It is not a complete list of the company’s facilities, and this page is not affiliated with or endorsed by TeraWulf.