Red Oak, Ellis County, TX
Compass Datacenters Red Oak second campus
ApprovedRed Oak City Council approved rezoning and a tax abatement 4-1 in May 2026 despite a planning board recommendation against it
- Rumored
- Proposed
- Approved
- Under construction
- Operating
Compass Datacenters has proposed a second Red Oak campus on nearly 830 acres of agricultural land. Council members voted 4-1 to rezone the land to planned development for a 'high tech industrial park' and 4-1 to grant a tax abatement, after the planning and zoning board voted 3-2 on April 27 not to recommend the rezoning. Residents raised concerns about noise, strain on the power grid and the site's proximity to schools.
Key facts
Size & schedule
| Site size | 830 acres [1] nearly 830 acres Source excerpt“Council members voted 4-1 for rezoning nearly 830 acres from agricultural district to planned development for a 'high tech industrial park.'” |
|---|
Water
| Water source | Not city water for cooling (per city leaders) [2]Source excerpt“it would not draw on city water for cooling the center” |
|---|---|
| Cooling | closed-loop [1] city manager said the system would require 10 million gallons of water annually Source excerpt“City Manager Todd Fuller explained the center will use a closed-loop cooling system, which would require 10-million gallons of water annually.” |
Money & incentives
| Tax incentives | $2.82 million tax abatement over the next decade [3]Source excerpt“The council approved a $2.82 million tax abatement over the next decade” |
|---|---|
| Tax abatement value | $2.8 million [3]Source excerpt“The council approved a $2.82 million tax abatement over the next decade” |
Local decisions & site
| Deciding vote | Red Oak City Council approved rezoning 4-1 (Franklin, Flannery, Miller, Lightfoot for; Smith against) and a tax abatement 4-1 [1]Source excerpt“Council members Mayor Pro Tem Willie Franklin Jr., Sean Flannery, Ricardo Miller and Tim Lightfoot voted in favor of the rezoning, and Jeffery Smith voted against it.” |
|---|---|
| Zoning | Rezoned from agricultural district to planned development for a 'high tech industrial park' [1]Source excerpt“Council members voted 4-1 for rezoning nearly 830 acres from agricultural district to planned development for a 'high tech industrial park.'” |
Figures are as stated by the cited source. Where sources disagree, each figure is shown.
Timeline
Issues raised
- Residents raised concerns about noise, potential strain on the power grid and proximity to schools [2]
- Residents cited noise, pollution and declining property values [4]
- The developer says the project will result in $72 million in electric grid reinforcements [3]
- It will be the sixth data center campus in Red Oak [4][5]
Sources
- Red Oak rezones land for data center campus despite protestsEllis County Press · news
- Red Oak approves 800-acre data center project despite resident protestsFOX 4 Dallas-Fort Worth · May 11, 2026 · news
- New Red Oak Data Center Project Meets Community PushbackDallas Observer · news
- Red Oak City Council approves another data center in North Texas amid backlash from communityCBS News Texas · May 12, 2026 · news
- Oppose? Expand? Votes in 2 North Texas communities highlight a divide over data center growthKERA News · May 12, 2026 · news