Vantage Frontier Campus
Albany, Shackelford County, TX[1]Developer: Vantage Data Centers[1][6]
Also known as Stargate Shackelford County
- Rumored
- Proposed
- Approved
- Under construction
- Operating
Follow this project
New dated changes arrive in your feed reader or calendar. No account, no email address, no tracking.
- RSS feed for any feed reader
- Atom feed
- Hearings calendar (.ics, subscribes in Apple, Google or Outlook Calendar)
Frontier is Vantage Data Centers' planned 1.4 GW, 10-building, $25 billion campus on about 1,200 acres at Highways 604 and 351 in Shackelford County. OpenAI and Oracle named it a Stargate site in September 2025. The county approved a reinvestment zone and a tax abatement arrangement in July 2025, and Vantage held a groundbreaking in December 2025. As of September 2026 the buildings are still under construction.
Key facts
Size & schedule
| Planned capacity | 1.4 GW [1] |
|---|---|
| Site size | 1,200 acres [1] |
| Site size | 700 acres [8] Oracle fact sheet figure; conflicts with the 1,200 acres in the record Source excerpt“The campus will be home to 10 buildings on 700 acres totaling 3.7 million square feet.” |
| Floor area | 3.7 million sq ft [1] |
| Buildings | 10 data centers [1] |
| Stated investment | $25 billion [1] company says 'over $25 billion' |
| Permanent jobs (promised) | 250 [2] $25M annual payroll |
| Construction jobs | 6,500 workers [2] up to 6,500 at peak |
| Target completion | Vantage: first building 2H 2026; Epoch AI projects first building Aug 2027 and completion Nov 2028 [6] |
How big is that? Data center sizes compared with football fields and Central Park.
Power
| Power supply | onsite natural gas microgrid, per Epoch AI [7] |
|---|---|
| On-site generation | 700 MW [9] 210 gas generators, as reported citing Business Insider and TCEQ filings Source excerpt“210 industrial gas generators at the Shackelford County site, with a combined capacity of 700 megawatts” |
| On-site generation type | Behind-the-meter gas microgrid using Jenbacher reciprocating engines [8]Source excerpt“The data centers are powered by an onsite, behind-the-meter, gas-powered microgrid utilizing Jenbacher reciprocating engines.” |
Water
| Cooling | air and liquid cooling; closed-loop chiller design [5] |
|---|
Money & incentives
| Tax incentives | Reinvestment Zone 2025-1; Vantage to pay $10M a year for 10 years in place of property taxes [2] |
|---|---|
| Abatement term | 10 years [2] Ten-year arrangement of $10 million annual payments in lieu of property taxes Source excerpt“it will make $10 million in annual payments to the county in lieu of property taxes” |
| Payments / community benefits | As many as 10 college scholarships a year for Shackelford County students over the life of the project, in addition to $10 million annual payments in lieu of taxes [2]Source excerpt“Up to 10 college scholarships per year for Shackelford County students, continuing for the life of the project.” |
Local decisions & site
| Deciding vote | Shackelford County Commissioners unanimously approved the project on July 21, 2025 [3]Source excerpt“On July 21st, the Shackleford County Commissioners gave unanimous approval for the project.” |
|---|
Figures are as stated by the cited source. Where sources disagree, each figure is shown.
Water and power
Water
Not disclosed. No source reviewed gives a water figure for this site. The Census does not estimate one.
Disclosed figures only, each as the cited source states it. Many are projections or permit limits, not metered use. How data center water and power use is measured, and every disclosed figure →
Timeline
Shackelford County Commissioners unanimously approve reinvestment zone and accept Vantage abatement application [2]
Land clearing begins, per Epoch AI [6]
Vantage announces $25B Frontier campus [1]
OpenAI and Oracle name Shackelford County a Stargate site [4]
Vantage holds groundbreaking ceremony [5]
Steel framing begins, per Epoch AI [6]
Satellite imagery shows Buildings 1-5 shells complete and roofed [6]
Sources
- Vantage Data Centers Unveils Plans for "Frontier," a $25B Mega-campus in Texas to Meet Unprecedented AI DemandVantage Data Centers · Aug 19, 2025 · company
- Data center plans move forward in Shackelford CountyThe Albany News · Jul 24, 2025 · news
- Albany businesses brace for change as data center construction set to boost local economyKTXS · Aug 1, 2025 · news
- OpenAI, Oracle, and SoftBank expand Stargate with five new AI data center sitesOpenAI · Sep 23, 2025 · company
- Vantage breaks ground on Texas gigawatt data center campus for OpenAIDCD · Dec 15, 2025 · news
- OpenAI Stargate Shackelford | AI Data CentersEpoch AI · Sep 21, 2026 · other
- OpenAI Stargate: where the US sites standEpoch AI · Apr 20, 2026 · other
- Oracle Fact Sheet: Stargate Data CentersOracle (posted by Office of Rep. Jodey Arrington) · Sep 23, 2025 · company
- Oracle and OpenAI's New Off-Grid Data Center in Texas to Run on 700MW Natural Gas MicrogridConstruction Owners · Oct 24, 2025 · news
Cite this page
Last updated Sep 22, 2026. Figures may change as records are updated — include the date you retrieved them.
| APA | Data Center Census. (2026). Vantage Frontier Campus. Retrieved from https://datacentercensus.com/dc/vantage-frontier-shackelford-county-tx |
|---|---|
| MLA | “Vantage Frontier Campus.” Data Center Census, Sep 22, 2026, https://datacentercensus.com/dc/vantage-frontier-shackelford-county-tx. |
| Link | https://datacentercensus.com/dc/vantage-frontier-shackelford-county-tx |
Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.