El Paso, El Paso County, TX
Meta El Paso Data Center
- Rumored
- Proposed
- Approved
- Under construction
- Operating
Meta is building a 1 GW AI data center on about 1,000 acres in Northeast El Paso, north of Stan Roberts Sr. Avenue and west of US 54. The stated investment rose from $1.5 billion in 2025 to more than $10 billion in March 2026, and a July 2026 venture put total development costs at about $14 billion. El Paso Electric has proposed a dedicated 366 MW gas plant (McCloud) next to the site, which environmental justice groups and residents oppose.
Key facts
Size & schedule
| Planned capacity | 1 GW [6] 1 GW of compute capacity |
|---|---|
| Site size | 1,000 acres [1] |
| Floor area | 1.2 million sq ft [2] nearly 1.2 million sq ft, per October 2025 announcement |
| Stated investment | $14 billion [6] approx. total development cost under Meta-BlackRock venture; earlier stated as $1.5B (2025) and >$10B (Mar 2026) |
| Permanent jobs (promised) | 300 [6] city incentive requires at least 50 |
| Construction jobs | 4,000 workers [6] peak; 2,300+ onsite as of July 2026 |
| Target completion | Capacity starts coming online in 2028; McCloud plant expected in 2027 [6] |
Power
| Utility | El Paso Electric [3] |
|---|---|
| Power supply | El Paso Electric's proposed 366 MW McCloud gas plant ($473M, 813 Enchanted Rock modular generators) on 31 adjacent acres, dedicated to the data center [3] |
| Utility commission case | PUCT Docket 59076 (El Paso Electric McCloud Generation) [7]Source excerpt“El Paso Electric McCloud Generation (Docket 59076): PUC Staff submitted direct testimony and engineering analysis on the 366 MW natural gas facility for data center service” |
Water
| Water use | 2,500,000 gal/day [1] maximum at full build-out; tiers at 100,000, 750,000 and 1.5M gpd average |
|---|
Money & incentives
| Tax incentives | Chapter 380 agreement: 80% city property tax rebate, ~$110M for Phase 1 (15 yrs), up to $550M across all phases (35 yrs) [1] |
|---|
Local decisions & site
| Zoning | Use permitted by right under existing zoning [1]Source excerpt“The use is permitted by right. The property is zoned appropriately and is subject to meeting all zoning requirements.” |
|---|
Figures are as stated by the cited source. Where sources disagree, each figure is shown.
Timeline
El Paso City Council approves incentive agreements [1]
Meta announces El Paso data center, >$1.5B [2]
El Paso Electric proposes $473M McCloud gas plant to serve the data center [3]
Meta raises stated investment to more than $10B [5]
El Paso City Council votes 5-3 against beginning negotiations to end the Meta incentive agreement [8]
State Office of Administrative Hearings begins testimony on El Paso Electric's proposed McCloud Generation Facility [9]
Meta announces venture with BlackRock (80% BlackRock funds / 20% Meta), ~$14B total cost [6]
Issues raised
Sources
- Data CentersCity of El Paso · government
- Hello, El Paso!Meta Data Centers · Oct 15, 2025 · company
- El Paso Electric proposes $473 million gas plant to power Meta data center operationsKVIA (El Paso Matters) · Jan 18, 2026 · news
- El Paso's plan to build natural gas power plant for massive data center kicks up oppositionTexas Tribune (Inside Climate News) · Jan 26, 2026 · news
- Big things are happening, El Paso!Meta Data Centers · Mar 26, 2026 · company
- Meta Announces New Strategic Venture with BlackRock to Develop Data Center in El PasoMeta Investor Relations · Jul 28, 2026 · company
- DocketWatcher — PUCT Weekly BriefingDocketWatcher (Substack) · Jun 22, 2026 · other
- El Paso city council votes to keep Meta data center incentive agreementKFOX14 · Jun 9, 2026 · news
- Key hearing begins on El Paso Electric gas plant proposal for Meta data centerCBS4 / KFOX14 · Jul 8, 2026 · news