Company
Meta data centers: tracked projects and locations
Meta is linked to 8 tracked projects in Wisconsin, Wyoming, Texas, Louisiana, Indiana, Kentucky, Ohio, Minnesota, totaling 10.42 GW of planned capacity. Role: developer.
- Approved 1
- Under construction 6
- Operating 1
Ranked #4 of 59 developers by the published capacity of its tracked projects that are proposed, approved, under construction or operating, as developer or operator (10.42 GW). See the ranking →
| Project | Status | Capacity | Developer | Last update |
|---|---|---|---|---|
| Meta Beaver Dam Data Center Beaver Dam, Dodge County, WI |
Under construction | 220 MW | Meta | May 7, 2026 |
| Meta Cheyenne Data Center Cheyenne, Laramie County, WY |
Under construction | — | Meta | Jul 2, 2026 |
| Meta El Paso Data Center El Paso, El Paso County, TX |
Under construction | 1 GW | Meta | Jul 28, 2026 |
| Meta Hyperion Holly Ridge, Richland Parish, LA |
Under construction | 5 GW | Meta | Aug 12, 2026 |
| Meta Lebanon Data Center Lebanon, Boone County, IN |
Under construction | 1 GW | Meta | Feb 11, 2026 |
| Meta Maysville campus Maysville, Mason County, KY |
Approved | 2.2 GW | Meta | Oct 13, 2026 |
| Meta Prometheus New Albany, Franklin and Licking counties, OH |
1 GW | Meta | Aug 2026 | |
| Meta Rosemount Data Center Rosemount, Dakota County, MN |
Under construction | — | Meta | Apr 21, 2026 |
Latest Meta data center news
The newest dated changes at Meta’s tracked projects, each from the filing, notice or report linked beside it.
-
Meta Maysville campus KY
Mason County Fiscal Court unanimously approves an industrial revenue bond, a development agreement and road improvements, and the county judge-executive names Meta as the company behind the project WKYT -
Meta Hyperion LA
LPSC votes 3-1 to reject an administrative law judge's recommendation to make Meta job and power-demand information available through subpoenas WWNO -
Meta El Paso Data Center TX
Meta announces venture with BlackRock (80% BlackRock funds / 20% Meta), ~$14B total cost Meta Investor Relations -
Meta El Paso Data Center TX
State Office of Administrative Hearings begins testimony on El Paso Electric's proposed McCloud Generation Facility CBS4 / KFOX14 -
Meta Cheyenne Data Center WY
BOPU announces it will no longer accept industrial wastewater from data center fill-and-flush or closed-loop cooling operations Wyoming Tribune Eagle -
Meta Prometheus OH
OPSB authorizes the 250 MW Socrates the Younger plant (Case 26-0169-EL-BLN) to serve adjacent Meta data center Ohio Power Siting Board
This page lists projects in the Census where Meta is named as developer by a cited source. It is not a complete list of the company’s facilities, and this page is not affiliated with or endorsed by Meta.