Data Center Census Near me

Company

Meta data centers: tracked projects and locations

Meta is linked to 8 tracked projects in Wisconsin, Wyoming, Texas, Louisiana, Indiana, Kentucky, Ohio, Minnesota, totaling 10.42 GW of planned capacity. Role: developer.

Ranked #4 of 59 developers by the published capacity of its tracked projects that are proposed, approved, under construction or operating, as developer or operator (10.42 GW). See the ranking →

ProjectStatusCapacityDeveloperLast update
Meta Beaver Dam Data Center
Beaver Dam, Dodge County, WI
Under construction 220 MW Meta May 7, 2026
Meta Cheyenne Data Center
Cheyenne, Laramie County, WY
Under construction — Meta Jul 2, 2026
Meta El Paso Data Center
El Paso, El Paso County, TX
Under construction 1 GW Meta Jul 28, 2026
Meta Hyperion
Holly Ridge, Richland Parish, LA
Under construction 5 GW Meta Aug 12, 2026
Meta Lebanon Data Center
Lebanon, Boone County, IN
Under construction 1 GW Meta Feb 11, 2026
Meta Maysville campus
Maysville, Mason County, KY
Approved 2.2 GW Meta Oct 13, 2026
Meta Prometheus
New Albany, Franklin and Licking counties, OH
Operating 1 GW Meta Aug 2026
Meta Rosemount Data Center
Rosemount, Dakota County, MN
Under construction — Meta Apr 21, 2026

Latest Meta data center news

The newest dated changes at Meta’s tracked projects, each from the filing, notice or report linked beside it.

  1. Meta Maysville campus KY
    Mason County Fiscal Court unanimously approves an industrial revenue bond, a development agreement and road improvements, and the county judge-executive names Meta as the company behind the project WKYT
  2. Meta Hyperion LA
    LPSC votes 3-1 to reject an administrative law judge's recommendation to make Meta job and power-demand information available through subpoenas WWNO
  3. Meta Prometheus OH
    Building 12 operating, per Epoch AI Epoch AI
  4. Meta El Paso Data Center TX
    Meta announces venture with BlackRock (80% BlackRock funds / 20% Meta), ~$14B total cost Meta Investor Relations
  5. Meta Hyperion LA
    Meta announces expansion to 5 GW and more than $50 billion investment Meta
  6. Meta El Paso Data Center TX
    State Office of Administrative Hearings begins testimony on El Paso Electric's proposed McCloud Generation Facility CBS4 / KFOX14
  7. Meta Cheyenne Data Center WY
    BOPU announces it will no longer accept industrial wastewater from data center fill-and-flush or closed-loop cooling operations Wyoming Tribune Eagle
  8. Meta Prometheus OH
    OPSB authorizes the 250 MW Socrates the Younger plant (Case 26-0169-EL-BLN) to serve adjacent Meta data center Ohio Power Siting Board

This page lists projects in the Census where Meta is named as developer by a cited source. It is not a complete list of the company’s facilities, and this page is not affiliated with or endorsed by Meta.