SB Energy is linked to 2 tracked projects in Ohio, Texas, totaling 11.2 GW of planned capacity. Role: developer.

ProjectStatusCapacityDeveloperLast update
PORTS-Pike Technology Campus
Piketon, Pike County, OH
Under construction 10 GW SB Energy, SoftBank Aug 17, 2026
Stargate Milam County
Burlington, Milam County, TX
Under construction 1.2 GW SB Energy, SoftBank Apr 22, 2026

Recent changes

  1. PORTS-Pike Technology Campus OH
    OpenAI announces it has joined the project under a 20-year lease, with NVIDIA investing $1.5 billion OpenAI
  2. PORTS-Pike Technology Campus OH
    Permit filed with Ohio EPA covering wetlands and stream impacts on private land WOUB Public Media
  3. Stargate Milam County TX
    Filing for 548,950 sq ft Freebird Phase 1 reported DCD
  4. PORTS-Pike Technology Campus OH
    DOE, SoftBank and SB Energy announce 10 GW data center campus and 9.2 GW gas generation at the Portsmouth site U.S. Department of Energy
  5. PORTS-Pike Technology Campus OH
    Groundbreaking ceremony held WOUB Public Media
  6. Stargate Milam County TX
    Phase 1 reported topped out DCD
  7. Stargate Milam County TX
    OpenAI and SoftBank each invest $500M in SB Energy, which will build and operate the site DCD
  8. Stargate Milam County TX
    OpenAI and SoftBank announce Milam County as a Stargate site OpenAI

This page lists projects in the Census where SB Energy is named as developer by a cited source. It is not a complete list of the company’s facilities.