Data Center Census Near me

Stillwater Technology Park

Lovejoy, Clayton County, GA

Also known as Panhandle Road data center, Stillwater Lovejoy data center

CancelledDeveloper withdrew the proposal in August 2026; Lovejoy banned data centers in September 2026
  1. Rumored
  2. Proposed
  3. Approved
  4. Under construction
  5. Operating
Cancelled

Stillwater Technology Park was a proposed 15-building, 3.5 million square foot data center campus on about 400 acres at 11760 Panhandle Road in Lovejoy, with a planned capacity of 1.25 GW and a stated value of up to $13 billion. Residents opposed it, citing two nearby schools and traffic. The developer withdrew the application at an August 2026 city council session and now plans housing, and the council banned data centers citywide in late September.

Stated investment
$13 billion
up to; valuation at full build-out
Site size
400 acres
about

Key facts

Size & schedule

Planned capacity1.25 GW [1]
planned grid demand at full build-out per Atlanta News First and Hoodline; the AJC reports 1.2 GW
Site size400 acres [2]
about
Floor area3.5 million sq ft [1]
Central Georgia EMC was to supply power, per the AJC
Buildings15 [1]
Stated investment$13 billion [2]
up to; valuation at full build-out

How big is that? Data center sizes compared with football fields and Central Park.

Figures are as stated by the cited source. Where sources disagree, each figure is shown.

Water and power

Water

Not disclosed. No source reviewed gives a water figure for this site. The Census does not estimate one.

Power

Planned capacity1.25 GW [1]

Disclosed figures only, each as the cited source states it. Many are projections or permit limits, not metered use. How data center water and power use is measured, and every disclosed figure →

Timeline

  1. Lovejoy rezones the site to allow potential data center development; Stillwater first files plans [2]

  2. AJC reports the 1.2 GW Stillwater filing and the mayor's traffic concerns for nearby schools [4]

  3. Developer withdraws the proposal at a special city council session [1]

  4. Lovejoy council passes an ordinance banning data center construction in the city [3]

Issues raised

  • Residents and city leaders objected to the site's proximity to two schools and to traffic effects [3]

Issues are concerns and claims raised by the parties, officials or residents named in the cited sources. They are reported as attributed, not as findings by the Census.

Sources

  1. Proposal for Clayton County data center withdrawn
    Atlanta News First · Aug 6, 2026 · news
  2. Lovejoy kills 400-acre data center plan, vows to ban them for good
    Hoodline · Aug 9, 2026 · news
  3. City of Lovejoy passes ordinance banning data center construction
    Atlanta News First · Sep 29, 2026 · news
  4. OpenAI's $20B data center dominated Georgia headlines, but it wasn't alone
    Atlanta Journal-Constitution · Jul 28, 2026 · news

Cite this page

Last updated Oct 15, 2026. Figures may change as records are updated — include the date you retrieved them.

APAData Center Census. (2026). Stillwater Technology Park. Retrieved from https://datacentercensus.com/dc/stillwater-technology-park-lovejoy-ga
MLA“Stillwater Technology Park.” Data Center Census, Oct 15, 2026, https://datacentercensus.com/dc/stillwater-technology-park-lovejoy-ga.
Linkhttps://datacentercensus.com/dc/stillwater-technology-park-lovejoy-ga

Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.