Fayetteville, Fayette County, GA
QTS Fayetteville data center campus
Also known as Project Excalibur, Microsoft Fairwater Atlanta
- Rumored
- Proposed
- Approved
- Under construction
- Operating
QTS, a Blackstone subsidiary, is building a 615-acre data center campus on Highway 54 on the west side of Fayetteville, planned for up to about 7 million sq ft. Its first building, over 1 million sq ft, opened in October 2025 and is leased to Microsoft for its Fairwater AI 'superfactory'. QTS has also filed plans for a 2 million sq ft expansion on 313 acres west of Veterans Parkway.
Key facts
Size & schedule
| Planned capacity | 250 MW [2] approximate capacity as reported by DCD |
|---|---|
| Site size | 615 acres [3] land acquired in 2022 for about $154 million |
| Floor area | 7 million sq ft [3] up to about 7 million sq ft planned; DCD reports 6.6 million sq ft in 16 buildings |
| Buildings | 16 [2] planned |
| Target completion | Fully operational by 2030; ATL2 East expansion by 2029 [7] |
Power
| Utility | Georgia Power [4] |
|---|
Water
| Water use | 2,000 gal/day [8] per city officials; closed-loop system Source excerpt“According to officials, QTS uses 2,000 gallons of water a day compared to a 'typical data center' using more than one million gallons per day.” |
|---|---|
| Water source | Fayette County Water System (municipal) [5] construction use under 1% of county production; operational use described as about four households |
| Cooling | closed-loop [6] |
Local decisions & site
| Zoning | East campus expansion: two parcels fronting Veterans Parkway rezoned from planned community district to business park, with a future land use map update [8]Source excerpt“Rezoning changes the two parcels from planned community district to business park.” |
|---|
Figures are as stated by the cited source. Where sources disagree, each figure is shown.
Timeline
QTS confirmed as buyer of about 600 acres for $153.8 million for a 250 MW campus [1]
First building occupied [3]
Certificate of completion issued for first building [3]
Microsoft Fairwater AI facility opens in first building [3]
QTS files plans for 2 million sq ft ATL2 East expansion on 313 acres west of Veterans Parkway [2]
Fayette County issues statement on QTS construction water use [5]
Issues raised
- County records showed QTS used 109 million gallons across 13 water lines during construction, and two lines were installed without county inspection; QTS says it did not use water improperly, and the county later attributed billing problems to a smart meter transition [7]
- Residents along Georgia Power's Ashley Park-Wansley 500 kV transmission line face easement and eminent domain demands; Georgia Power says the line does not serve a single customer [4]
- Neighbors say the campus does not fit Fayette County's residential character [7]
Sources
- QTS confirmed as behind 250MW data center mega-project in Fayetteville, GeorgiaDatacenterDynamics · Aug 10, 2022 · news
- QTS files to expand Fayetteville data center campus in GeorgiaDatacenterDynamics · Jan 15, 2026 · news
- Microsoft's newest AI 'superfactory' opens at sprawling Fayetteville campusAtlanta Journal-Constitution · Nov 21, 2025 · news
- The data center boom is transforming Georgia. Some residents could lose their land.Atlanta Journal-Constitution · May 15, 2026 · news
- Facts about the QTS Fayetteville Data Center Campus ProjectFayette County · May 13, 2026 · government
- Fayetteville, GeorgiaQTS Data Centers · company
- Questions raise about massive data center in Georgia as QTS pursues plans to build campus in BessemerWBRC · Jul 16, 2026 · news
- Fayetteville Updates City's Future Land Use Map for QTS East CampusThe Fayette County News · news