Company
Microsoft data centers: tracked projects and locations
Microsoft is linked to 7 tracked projects in Georgia, Wisconsin, Michigan, North Carolina, New Jersey, Texas, totaling 3.22 GW of planned capacity. Role: developer and tenant.
- Proposed 3
- Under construction 1
- Operating 3
Ranked #13 of 59 developers by the published capacity of its tracked projects that are proposed, approved, under construction or operating, as developer or operator (2.67 GW). See the ranking →
| Project | Status | Capacity | Developer | Last update |
|---|---|---|---|---|
| Microsoft Fairwater Atlanta Fayetteville, Fayette County, GA |
— | Microsoft | May 13, 2026 | |
| Microsoft Fairwater Mount Pleasant, Racine County, WI |
— | Microsoft | Oct 14, 2026 | |
| Microsoft Gaines Township data center Caledonia, Kent County, MI |
Proposed | — | Microsoft | Apr 15, 2026 |
| Microsoft Mega Park Person County, NC |
Proposed | — | Microsoft | Jun 30, 2026 |
| Nebius Vineland Data Center Vineland, Cumberland County, NJ |
Under construction | 300 MW | Nebius, DataOne | Aug 12, 2026 |
| Project Kilby Pecos, Reeves County, TX |
Proposed | 2.67 GW | Microsoft, Chevron, Joulent LLC | Jul 31, 2026 |
| QTS Fayetteville data center campus Fayetteville, Fayette County, GA |
250 MW | QTS Data Centers | May 13, 2026 |
Latest Microsoft data center news
The newest dated changes at Microsoft’s tracked projects, each from the filing, notice or report linked beside it.
-
Microsoft Fairwater WI
Village Plan Commission unanimously backs Microsoft's amended site plan, which drops two of nine planned data center buildings while raising total floor area above 5.8 million sq ft; Village Board vote expected later in October Wisconsin Public Radio -
Nebius Vineland Data Center NJ
City issues two stop-construction orders over LNG tank and Bloom Energy fuel cell work done without permits WHYY -
Project Kilby TX
Chevron's second-quarter earnings release lists the signed agreement for about 2.67 GW of behind-the-meter power in West Texas Chevron / SEC -
Microsoft Fairwater WI
Microsoft signs 15-year electric service contract with We Energies Wisconsin Watch -
Project Kilby TX
Bloomberg reports that National Grid will invest $1.75 billion for a 35% stake in Joulent LLC, and that Joulent is developing a gas-fired power plant with Chevron for Microsoft in Texas. Morgan Lewis (National Grid's law firm) and w.media identify the plant as Project Kilby Bloomberg (Eamon Farhat and Naureen S. Malik) -
Microsoft Mega Park NC
Microsoft hosts a meeting with neighbors about the planned Microsoft Mega Park WRAL -
Microsoft Fairwater WI
Microsoft announces construction of first facility is complete Microsoft Source
This page lists projects in the Census where Microsoft is named as developer or a publicly reported tenant by a cited source. It is not a complete list of the company’s facilities, and this page is not affiliated with or endorsed by Microsoft.