Data Center Census Near me

QTS Augusta Data Center Campus

Augusta, Augusta-Richmond County, GADeveloper: QTS Data Centers

Also known as Project Eisenhower

Under constructionSite clearing began in 2026; QTS says site plans remain under city review and expects its first building in spring 2028
  1. Rumored
  2. Proposed
  3. Approved
  4. Under construction
  5. Operating

QTS Data Centers is developing a six-building data center campus, which it says is a $2 billion investment, at 2883 Gordon Highway in west Augusta, between the Haynes Station and Captain's Corner neighborhoods. The site was first rezoned in 2022 for a smaller T5 Data Centers project, and developer Eagle South LLC won approval for an expanded version in June 2024. Tree clearing began in 2026 and local news describes the campus as under construction, while QTS says detailed site plans are still under city review and expects its first building to be completed in spring 2028. Augusta's 2026 pause on new data centers does not apply to the project, and several neighbors say they did not know about it until local news reported on it.

Stated investment
$2 billion
QTS figure
Site size
165.21 acres
parcel rezoned in 2024

Key facts

Size & schedule

Site size165.21 acres [3]
parcel rezoned in 2024
Source excerpt
“Property owner Vitrified Brick & Clay Co. and developer Eagle South LLC petitioned to rezone 2883 Gordon Highway from Agricultural and General Business to only General Business, planning to build a data center on the 165.21-acre parcel.”
Floor areaalmost 2.2 million [7]
revised project in the state Development of Regional Impact filing; six two-story buildings
Source excerpt
“The DRI mentions a 'revised project' consisting of six two-story buildings and a total of almost 2.2 million square feet of warehouse and office space.”
Floor areamore than 1.4 million [3]
figure the applicants gave the planning commission in June 2024; differs from the DRI figure
Source excerpt
“The proposed facility would consist of six buildings, totaling more than 1.4 million square feet, and would employ between 160 and 220 people, according to the applicants.”
Buildings6 [16]
constructed over several phases
Source excerpt
“The project will include six buildings, constructed over several phases, with the first building expected to be completed in spring 2028.”
Stated investment$2 billion [16]
QTS figure
Source excerpt
“This project represents a $2 billion QTS investment that will have a transformative impact on Augusta, supporting its growth and development.”
Permanent jobs (promised)approximately 160 to 220 [16]
QTS figure, including jobs with tenants; the same QTS page also estimates around 45 permanent jobs
Source excerpt
“Once operational, we project approximately 160 to 220 permanent, on‑site jobs, including positions with QTS as well as jobs with the companies that lease space within the data center.”
Construction jobs1,000 [8]
roughly, over several years
Source excerpt
“The Augusta project would include six buildings going up over several years, bringing roughly 1,000 construction jobs over time and an estimated 160 to 220 permanent jobs once operational.”
Target completionFirst building expected to be completed in spring 2028 [16]
Source excerpt
“The project will include six buildings, constructed over several phases, with the first building expected to be completed in spring 2028.”

Water

Water use18,000 gal/day [4]
per the state application; a May 2026 report describes 18,000 gallons a day for each of six buildings [10]
Source excerpt
“The application states the facility is expected to consume 18,000 gallons of water per day.”
Water sourceAugusta Utilities [4]
per the state application as reported
Source excerpt
“The application says there's sufficient supply from Augusta Utilities.”
Coolingclosed-loop [16]
Source excerpt
“QTS data centers are built with a closed-loop cooling system that does not consume water for cooling, once operational.”

Local decisions & site

Deciding voteAugusta Planning Commission voted unanimously on June 3, 2024 to recommend rezoning for the expanded project [3]
Source excerpt
“The Augusta Planning Commission unanimously voted in favor of a prospective data center project on Gordon Highway during its meeting Monday afternoon, but not without deliberation and some contention.”
ZoningGeneral Business (B-2); rezoned from Agricultural (A) and Manufactured Home Residential (R-MH) in 2022 [5]
Source excerpt
“In 2022, T5 successfully petitioned to rezone the property from Agricultural (A) and Manufactured Home Residential (R-MH) to General Business (B-2) to make way for the facility.”

Figures are as stated by the cited source. Where sources disagree, each figure is shown.

Timeline

  1. T5 Data Centers wins rezoning of the property to General Business (B-2) for a smaller data center [5]

  2. Eagle South LLC files a state Development of Regional Impact application for an expanded campus called Project Eisenhower [1]

  3. Eagle South LLC and landowner Vitrified Brick & Clay Co. receive county approval for the expanded development [5]

  4. Augusta Planning Commission unanimously recommends rezoning the 165.21-acre parcel at 2883 Gordon Highway [3]

  5. QTS presents the project to the Augusta Commission, saying it plans to invest $2 billion [6]

  6. QTS and residents meet at a town hall at Belair Elementary [8]

  7. WGAC reports that crews have started clearing trees and brush at the site [11]

  8. Augusta Commission imposes a 49-day pause on new data centers that does not apply to the QTS project [12]

  9. Augusta releases a final draft data center ordinance that would not apply to the QTS campus [15]

Issues raised

  • Several neighbors say they did not know about the project until News 12 reported on it [8]
  • Residents want clarity on the data center's size and its impact on traffic, noise and wetlands [8]
  • The environmental section of the state application says the project is likely to affect the water supply watershed, wetlands and floodplains [6]
  • Neighbors cite a lack of transparency and communication from city leaders and the developer [13]
  • As of May 2026, grading permits were under review, building permits had not been issued, and Army Corps of Engineers approvals for wetland impacts were still required [9]

Sources

  1. Plans filed to expand former T5 campus site in Augusta, Georgia
    DatacenterDynamics · Mar 29, 2024 · news
  2. Rezoning request on Gordon Highway tract could bring back data center project
    The Augusta Press · May 30, 2024 · news
  3. Augusta Planning Commission votes to recommend rezoning for data center on Gordon Highway
    The Augusta Press · Jun 4, 2024 · news
  4. Flying under radar, new data center will be twice as big as Augusta Mall
    WRDW/WAGT News 12 · Dec 26, 2025 · news
  5. Augusta data center project still underway
    The Augusta Press · Dec 28, 2025 · news
  6. Augusta leaders hear about data center that came as a shock to neighbors
    WRDW/WAGT News 12 · Feb 3, 2026 · news
  7. QTS unveils more about Gordon Highway data project
    The Augusta Press · Feb 4, 2026 · news
  8. ‘It’s a lot of unknowns’: Augusta data center meeting draws concerned neighbors
    WRDW/WAGT News 12 · Feb 11, 2026 · news
  9. Data center developer responds to neighbors' concerns in Augusta
    WRDW/WAGT News 12 · May 5, 2026 · news
  10. Luncheon provides information on QTS data center project in Augusta
    WRDW/WAGT News 12 · May 28, 2026 · news
  11. QTS Facility in Augusta Draws Questions About Water Use and Local Impact
    WGAC · Jun 1, 2026 · news
  12. Augusta puts a hold on data centers — except the one that’s riled up neighbors
    WRDW/WAGT News 12 · Jun 2, 2026 · news
  13. WATCH LIVE: Community meeting on data center planned near Haynes Station
    WRDW/WAGT News 12 · Jun 22, 2026 · news
  14. Augusta Commission faces data center vote amid growing community pushback
    WRDW/WAGT News 12 · Jul 20, 2026 · news
  15. Here's what's in Augusta's final plan for data centers
    WRDW/WAGT News 12 · Sep 9, 2026 · news
  16. Augusta, Georgia Data Center Campus | QTS Data Centers
    QTS Data Centers · company

Cite this page

Last updated Sep 23, 2026. Figures may change as records are updated — include the date you retrieved them.

APAData Center Census. (2026). QTS Augusta Data Center Campus. Retrieved from https://datacentercensus.com/dc/qts-augusta-ga
MLA“QTS Augusta Data Center Campus.” Data Center Census, Sep 23, 2026, https://datacentercensus.com/dc/qts-augusta-ga.
Linkhttps://datacentercensus.com/dc/qts-augusta-ga

Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.