Data centers in Augusta-Richmond County, Georgia

The Census tracks 1 data center project in Augusta-Richmond County, Georgia: 1 under construction. 2 moratorium actions recorded.

How many data centers are in Augusta-Richmond County?

The Census tracks 1 major project here as of Sep 23, 2026: 1 under construction. They are in Augusta.

Projects

ProjectStatusCapacityDeveloper
QTS Augusta Data Center Campus
Augusta, Augusta-Richmond County, GA
Under constructionQTS Data Centers

Moratoriums

JurisdictionActionLengthWhat the source says
Augusta-Richmond County
Georgia · county
Adopted
Jun 2, 2026
49 days Pause on new data centers to allow public input; WRDW reported that it does not apply to the QTS campus on Gordon Highway. WRDW
Source excerpt
“The Augusta Commission on Tuesday imposed a 49-day pause on new data centers, but it doesn't apply to the one that's stirring up controversy.”
Augusta-Richmond County
Georgia · county
Extension recommended
reported Jul 20, 2026
The Augusta Planning Commission recommended extending the moratorium by 60 days; WRDW reported on July 20, 2026 that commissioners had been unable to reach agreement at their last meeting. WRDW
Source excerpt
“The Augusta Planning Commission recommended extending the moratorium by 60 more days.”

All Georgia moratoriums → · All tracked moratoriums →

Recent changes

DateWhat changedProject
Sep 9, 2026Augusta releases a final draft data center ordinance that would not apply to the QTS campus WRDW/WAGT News 12QTS Augusta Data Center Campus
Jun 2, 2026Augusta Commission imposes a 49-day pause on new data centers that does not apply to the QTS project WRDW/WAGT News 12QTS Augusta Data Center Campus
Jun 1, 2026WGAC reports that crews have started clearing trees and brush at the site WGACQTS Augusta Data Center Campus
Feb 11, 2026QTS and residents meet at a town hall at Belair Elementary WRDW/WAGT News 12QTS Augusta Data Center Campus
Feb 3, 2026QTS presents the project to the Augusta Commission, saying it plans to invest $2 billion WRDW/WAGT News 12QTS Augusta Data Center Campus
Jun 3, 2024Augusta Planning Commission unanimously recommends rezoning the 165.21-acre parcel at 2883 Gordon Highway The Augusta PressQTS Augusta Data Center Campus
Jun 2024Eagle South LLC and landowner Vitrified Brick & Clay Co. receive county approval for the expanded development The Augusta PressQTS Augusta Data Center Campus
Mar 2024Eagle South LLC files a state Development of Regional Impact application for an expanded campus called Project Eisenhower DatacenterDynamicsQTS Augusta Data Center Campus
2022T5 Data Centers wins rezoning of the property to General Business (B-2) for a smaller data center The Augusta PressQTS Augusta Data Center Campus

Augusta-Richmond County data centers: common questions

How many data centers are in Augusta-Richmond County, Georgia?

The Census tracks 1 major data center project in Augusta-Richmond County as of Sep 23, 2026: 1 under construction. That covers major sourced projects, not every smaller colocation or enterprise facility.

Is there a data center moratorium in Augusta-Richmond County?

Augusta-Richmond County adopted a data center moratorium (Jun 2, 2026), 49 days. Augusta-Richmond County had an extension of its data center moratorium recommended. Details and sources are in the moratorium tracker.

This page collects the county-level record: every tracked project, moratorium and local rule we can source for Augusta-Richmond County. See all Georgia projects or look up projects near your ZIP code.

Cite this page

Last updated Sep 23, 2026. Figures may change as records are updated — include the date you retrieved them.

APAData Center Census. (2026). Data centers in Augusta-Richmond County, Georgia. Retrieved from https://datacentercensus.com/us/georgia/augusta-richmond-county
MLA“Data centers in Augusta-Richmond County, Georgia.” Data Center Census, Sep 23, 2026, https://datacentercensus.com/us/georgia/augusta-richmond-county.
Linkhttps://datacentercensus.com/us/georgia/augusta-richmond-county

Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.