Data Center Census Near me

Natelli data center, U.S. 158

Vance County, NC

ProposedNatelli Holdings decided to file a development plan in September 2026, days before commissioners adopted a 60-day data center moratorium
  1. Rumored
  2. Proposed
  3. Approved
  4. Under construction
  5. Operating

Maryland-based Natelli Holdings is developing a 900-megawatt, four million square foot data center in Vance County, off US 158 and Poplar Creek Road, according to The Daily Dispatch. In a letter dated Sept. 9, 2026, the developer told county leaders it had decided to file a plan for development of the site, and on Sept. 14 commissioners voted 5-2 for a 60-day data center moratorium. Earlier, in April 2026, commissioners voted 6-1 to rezone a 40-acre Natelli Investments parcel on US-158 Business near Henderson to Light Industrial; the sources do not say whether that parcel is part of the 900 MW site.

Planned capacity
900 MW

Key facts

Size & schedule

Planned capacity900 MW [4]
Source excerpt
“Maryland-based company Natelli Holdings is developing a four million square foot, 900-megawatt data center off US 158 and Poplar Creek Road in what was once Triangle North Vance.”
Site size500 acres [3]
WIZS describes the tract of the opposed data center development as roughly 500 acres along U.S. Hwy. 158 but does not name the developer in that article; the April 2026 rezoning covered a 40-acre parcel (DatacenterDynamics)
Source excerpt
“During two public hearings – both involving data centers – commissioners on Monday heard from members of the public who oppose the data center development on a roughly 500-acre tract along U.S. Hwy. 158.”
Floor area4 million sq ft [4]
Source excerpt
“Maryland-based company Natelli Holdings is developing a four million square foot, 900-megawatt data center off US 158 and Poplar Creek Road in what was once Triangle North Vance.”

How big is that? Data center sizes compared with football fields and Central Park.

Power

UtilityDuke Energy [2]
the developer says it has held talks with Duke Energy on energy availability
Source excerpt
“along with environmental impact studies and talks with Duke Energy to make sure adequate energy is available”

Local decisions & site

Deciding voteVance County Board of Commissioners approved the rezoning 6-1 in April 2026 [1]
Source excerpt
“As reported by WRAL and the Henderson Dispatch, the Vance County board of commissioners voted 6-1 this week to approve the rezoning of land that could be used to develop a data center.”
Zoning40-acre parcel on US-158 Business near Henderson, between Horseshoe Bend Road and Pine Meadow Trail, rezoned from Employment and Institutional to Light Industrial [1]
Request by Natelli Investments; unclear whether this parcel is part of the 900 MW site off US 158 and Poplar Creek Road
Source excerpt
“Natelli Investments is looking to rezone a 40-acre parcel near Henderson on US-158 Business, between Pine Meadow Trail and Horseshoe Bend Road, from Employment and Institutional to Light Industrial.”

Figures are as stated by the cited source. Where sources disagree, each figure is shown.

Timeline

  1. Vance County Planning Board unanimously approves the Natelli rezoning request [1]

  2. Vance County Board of Commissioners votes 6-1 to rezone land that could be used for a data center [1]

  3. Vance County Board of Commissioners delays a decision on the rezoning [1]

  4. Tom Natelli of Natelli Holdings writes to county commissioners and the planning board that the company has decided to file a plan for development of its site along U.S. 158 [2]

  5. Vance County Board of Commissioners votes 5-2 to adopt a 60-day moratorium on data center development after two public hearings [3]

Issues raised

  • WIZS reports the moratorium ends Nov. 13 or when the county amends the data center requirements in its zoning ordinance [3]
  • The Daily Dispatch reports Natelli has secured 'permit choice', which lets developers who apply before new standards are adopted choose which rules to follow [4]
  • Natelli sent the county a red-lined copy of the draft Unified Development Ordinance with preferred edits on setbacks, buffers, cooling systems and decommissioning [2]
  • Residents at the September hearings opposed the project and many asked for a longer moratorium; some raised concerns about the Kerr Reservoir [3][4]
  • DatacenterDynamics names the April 2026 applicant as Natelli Investments; WIZS and The Daily Dispatch name Natelli Holdings [1][2][4]
  • DatacenterDynamics reports Natelli previously proposed a 250 MW campus in Apex, N.C., and withdrew that application [1]

Issues are concerns and claims raised by the parties, officials or residents named in the cited sources. They are reported as attributed, not as findings by the Census.

Sources

  1. Officials in North Carolina County give ok for rezoning, potential data center incoming
    DatacenterDynamics · Apr 21, 2026 · news
  2. Data Center Developer Files Plan With County Amid Talk Of Moratorium, UDO Revision
    WIZS · Sep 10, 2026 · news
  3. TownTalk: Vance County Commissioners Adopt 60-Day Data Center Moratorium
    WIZS · Sep 15, 2026 · news
  4. County adopts 60-day moratorium
    The Daily Dispatch (Henderson) · Sep 16, 2026 · news

Cite this page

Last updated Sep 24, 2026. Figures may change as records are updated — include the date you retrieved them.

APAData Center Census. (2026). Natelli data center, U.S. 158. Retrieved from https://datacentercensus.com/dc/natelli-vance-county-nc
MLA“Natelli data center, U.S. 158.” Data Center Census, Sep 24, 2026, https://datacentercensus.com/dc/natelli-vance-county-nc.