Logan Prairie Data Center

Latham, Logan County, ILDeveloper: Hut 8

ProposedApplications pending; Latham's Aug. 3 annexation vote was called off and county consideration could come in September at the earliest; no later outcome in sources
  1. Rumored
  2. Proposed
  3. Approved
  4. Under construction
  5. Operating

Hut 8 wants to build a 500-megawatt, $5 billion data center on about 200 acres of farm ground in rural Laenna Township near Latham, roughly 30 miles northeast of Springfield. Logan County's zoning officer deemed the land-use applications complete on June 29, 2026, after the state's attorney declared that a 12-month moratorium the County Board approved in May was invalid. In late July 2026 the Village of Latham called off an Aug. 3 vote on whether to annex and rezone the site, and county officials said technical mistakes in the applications meant they could be considered in September at the earliest.

Planned capacity
500 MW
Stated investment
$5 billion
Hut 8's project page lists "$5B+" (s6)

Key facts

Size & schedule

Planned capacity500 MW [2]
Source excerpt
“Hut 8, a publicly traded company based in Miami, wants to build a 500-megawatt data center in rural Laenna Township near Latham, about 30 miles northeast of Springfield.”
Site size200 acres [4]
Hut 8's project page lists a 50-acre site footprint [6]; Hut 8's initial rezoning request, withdrawn at county officials' request, covered about 250 acres [2]
Source excerpt
“Opponents of the proposed 500-megawatt Logan Prairie Data Center, on 200 acres of farm ground in unincorporated Logan County a mile west of Latham”
Stated investment$5 billion [2]
Hut 8's project page lists "$5B+" [6]
Source excerpt
“Logan County officials are on track to consider and potentially vote on land-use applications for a $5 billion data center near Latham as soon as August after the local state's attorney declared invalid a 12-month moratorium that the County Board approved in May.”
Permanent jobs (promised)200 [5]
Hut 8 estimate ("as many as 200"); Blockspace says the village application lists more than 100 permanent, full-time jobs
Source excerpt
“Hut 8's project materials estimate 1,500 construction jobs over an 18-month buildout and as many as 200 permanent positions. The village application puts the figure at over 100 permanent, full-time jobs.”
Construction jobs1,500 [5]
Hut 8 estimate, over an 18-month buildout
Source excerpt
“Hut 8's project materials estimate 1,500 construction jobs over an 18-month buildout and as many as 200 permanent positions.”

How big is that? Data center sizes compared with football fields and Central Park.

Power

UtilityAmeren [6]
Blockspace says Ameren and MISO have not publicly confirmed an approved interconnection [5]
Source excerpt
“We work with Ameren and MISO to confirm how the site can be served safely and reliably.”
Grid operatorMISO [5]
Source excerpt
“The proposed load would draw about 500 megawatts near an Ameren substation, although Ameren and regional grid operator MISO have not publicly confirmed an approved interconnection.”

Water

Water use9,000 gal/day [6]
company projection for domestic uses only (restrooms, sinks, limited landscaping); company says no local water will be used for cooling
Source excerpt
“is projected to be comparable to that of a standard office building, or up to approximately 9,000 gallons per day”
Water sourceCooling water hauled in from elsewhere, per Hut 8 officials [2]
CoolingClosed-loop cooling (company description) [6]
Source excerpt
“The facility is designed to use a closed-loop cooling system that recirculates water through sealed piping.”

Money & incentives

Payments / community benefitsProposed community-benefit agreement that would pay Latham $8 million to $11 million a year for 15 years once the facility operates, contingent on annexation [5]

Local decisions & site

ZoningCounty applications seeking either an agricultural-to-industrial rezoning or a conditional permitted use within an agricultural zone; separately, a request for annexation into the Village of Latham and business zoning [4]
Source excerpt
“Hut 8's applications – for either a zoning change to industrial or a conditional permitted use in an agricultural zone”

Figures are as stated by the cited source. Where sources disagree, each figure is shown.

Timeline

  1. Logan County Board approves a 60-day data center moratorium [2]

  2. County Board does not extend the moratorium and sends the issue back to the zoning board pending a data center ordinance [1]

  3. Logan County Board votes 6-4 for a 12-month data center moratorium [2]

  4. State's Attorney Bradley Hauge advises County Board members that proper procedures were not followed for the moratorium to be legally binding [2]

  5. County Board fails 5-6 to approve a zoning ordinance specifically for data centers [2]

  6. Logan County Zoning Officer Allan Green deems Hut 8's land-use applications complete [2]

  7. Village of Latham calls off a planned Aug. 3 public hearing and vote on annexing and rezoning the site; the village attorney says the meeting was postponed and the application has not been withdrawn [5]

  8. County zoning officer says the state's attorney determined technical mistakes disqualified Hut 8's applications from August county meetings; if fixed and resubmitted they could be considered in September at the earliest [4]

  9. Logan County officials cancel the Aug. 6 Zoning Board of Appeals meeting [4]

Issues raised

  • Residents have raised concerns about noise, light pollution, electricity rates and farmland conversion [5]
  • Some residents questioned Hut 8's claims of benefits for the county [1]
  • Hut 8 estimates up to $65 million in annual property tax revenue; this is a company estimate [2][6]
  • Sources differ on distance from Latham: about one mile west [4][5] or two miles west [3]
  • The eventual customer and use remain undetermined, per Blockspace; Hut 8 says the facility would support cloud or AI workloads, not cryptocurrency mining [5][6]

Issues are concerns and claims raised by the parties, officials or residents named in the cited sources. They are reported as attributed, not as findings by the Census.

Sources

  1. No new moratorium, but no data center either for Logan County
    FOX Illinois · Apr 29, 2026 · news
  2. Data center moratorium declared invalid
    Illinois Times · Jul 2, 2026 · news
  3. End run for data center developer
    Illinois Times · Jul 22, 2026 · news
  4. Future uncertain for Logan County data center
    Illinois Times · Jul 28, 2026 · news
  5. Hut 8's 500 MW Illinois data center stalls as Latham cancels zoning vote
    Blockspace · Jul 31, 2026 · news
  6. Logan Prairie Data Center | Hut 8
    Hut 8 Corp. · company

Cite this page

Last updated Sep 24, 2026. Figures may change as records are updated — include the date you retrieved them.

APAData Center Census. (2026). Logan Prairie Data Center. Retrieved from https://datacentercensus.com/dc/hut8-logan-prairie-logan-county-il
MLA“Logan Prairie Data Center.” Data Center Census, Sep 24, 2026, https://datacentercensus.com/dc/hut8-logan-prairie-logan-county-il.
Linkhttps://datacentercensus.com/dc/hut8-logan-prairie-logan-county-il

Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.