Logan Prairie Data Center
Latham, Logan County, ILDeveloper: Hut 8
- Rumored
- Proposed
- Approved
- Under construction
- Operating
Hut 8 wants to build a 500-megawatt, $5 billion data center on about 200 acres of farm ground in rural Laenna Township near Latham, roughly 30 miles northeast of Springfield. Logan County's zoning officer deemed the land-use applications complete on June 29, 2026, after the state's attorney declared that a 12-month moratorium the County Board approved in May was invalid. In late July 2026 the Village of Latham called off an Aug. 3 vote on whether to annex and rezone the site, and county officials said technical mistakes in the applications meant they could be considered in September at the earliest.
- Planned capacity
- 500 MW
- Stated investment
- $5 billion
- Hut 8's project page lists "$5B+" (s6)
Key facts
Size & schedule
| Planned capacity | 500 MW [2]Source excerpt“Hut 8, a publicly traded company based in Miami, wants to build a 500-megawatt data center in rural Laenna Township near Latham, about 30 miles northeast of Springfield.” |
|---|---|
| Site size | 200 acres [4] Hut 8's project page lists a 50-acre site footprint [6]; Hut 8's initial rezoning request, withdrawn at county officials' request, covered about 250 acres [2] Source excerpt“Opponents of the proposed 500-megawatt Logan Prairie Data Center, on 200 acres of farm ground in unincorporated Logan County a mile west of Latham” |
| Stated investment | $5 billion [2] Hut 8's project page lists "$5B+" [6] Source excerpt“Logan County officials are on track to consider and potentially vote on land-use applications for a $5 billion data center near Latham as soon as August after the local state's attorney declared invalid a 12-month moratorium that the County Board approved in May.” |
| Permanent jobs (promised) | 200 [5] Hut 8 estimate ("as many as 200"); Blockspace says the village application lists more than 100 permanent, full-time jobs Source excerpt“Hut 8's project materials estimate 1,500 construction jobs over an 18-month buildout and as many as 200 permanent positions. The village application puts the figure at over 100 permanent, full-time jobs.” |
| Construction jobs | 1,500 [5] Hut 8 estimate, over an 18-month buildout Source excerpt“Hut 8's project materials estimate 1,500 construction jobs over an 18-month buildout and as many as 200 permanent positions.” |
How big is that? Data center sizes compared with football fields and Central Park.
Power
| Utility | Ameren [6] Blockspace says Ameren and MISO have not publicly confirmed an approved interconnection [5] Source excerpt“We work with Ameren and MISO to confirm how the site can be served safely and reliably.” |
|---|---|
| Grid operator | MISO [5]Source excerpt“The proposed load would draw about 500 megawatts near an Ameren substation, although Ameren and regional grid operator MISO have not publicly confirmed an approved interconnection.” |
Water
| Water use | 9,000 gal/day [6] company projection for domestic uses only (restrooms, sinks, limited landscaping); company says no local water will be used for cooling Source excerpt“is projected to be comparable to that of a standard office building, or up to approximately 9,000 gallons per day” |
|---|---|
| Water source | Cooling water hauled in from elsewhere, per Hut 8 officials [2] |
| Cooling | Closed-loop cooling (company description) [6]Source excerpt“The facility is designed to use a closed-loop cooling system that recirculates water through sealed piping.” |
Money & incentives
| Payments / community benefits | Proposed community-benefit agreement that would pay Latham $8 million to $11 million a year for 15 years once the facility operates, contingent on annexation [5] |
|---|
Local decisions & site
| Zoning | County applications seeking either an agricultural-to-industrial rezoning or a conditional permitted use within an agricultural zone; separately, a request for annexation into the Village of Latham and business zoning [4]Source excerpt“Hut 8's applications – for either a zoning change to industrial or a conditional permitted use in an agricultural zone” |
|---|
Figures are as stated by the cited source. Where sources disagree, each figure is shown.
Timeline
Logan County Board approves a 60-day data center moratorium [2]
County Board does not extend the moratorium and sends the issue back to the zoning board pending a data center ordinance [1]
Logan County Board votes 6-4 for a 12-month data center moratorium [2]
State's Attorney Bradley Hauge advises County Board members that proper procedures were not followed for the moratorium to be legally binding [2]
County Board fails 5-6 to approve a zoning ordinance specifically for data centers [2]
Logan County Zoning Officer Allan Green deems Hut 8's land-use applications complete [2]
Village of Latham calls off a planned Aug. 3 public hearing and vote on annexing and rezoning the site; the village attorney says the meeting was postponed and the application has not been withdrawn [5]
County zoning officer says the state's attorney determined technical mistakes disqualified Hut 8's applications from August county meetings; if fixed and resubmitted they could be considered in September at the earliest [4]
Logan County officials cancel the Aug. 6 Zoning Board of Appeals meeting [4]
Issues raised
- Residents have raised concerns about noise, light pollution, electricity rates and farmland conversion [5]
- Some residents questioned Hut 8's claims of benefits for the county [1]
- Hut 8 estimates up to $65 million in annual property tax revenue; this is a company estimate [2][6]
- Sources differ on distance from Latham: about one mile west [4][5] or two miles west [3]
- The eventual customer and use remain undetermined, per Blockspace; Hut 8 says the facility would support cloud or AI workloads, not cryptocurrency mining [5][6]
Issues are concerns and claims raised by the parties, officials or residents named in the cited sources. They are reported as attributed, not as findings by the Census.
Sources
- No new moratorium, but no data center either for Logan CountyFOX Illinois · Apr 29, 2026 · news
- Data center moratorium declared invalidIllinois Times · Jul 2, 2026 · news
- End run for data center developerIllinois Times · Jul 22, 2026 · news
- Future uncertain for Logan County data centerIllinois Times · Jul 28, 2026 · news
- Hut 8's 500 MW Illinois data center stalls as Latham cancels zoning voteBlockspace · Jul 31, 2026 · news
- Logan Prairie Data Center | Hut 8Hut 8 Corp. · company
Cite this page
Last updated Sep 24, 2026. Figures may change as records are updated — include the date you retrieved them.
| APA | Data Center Census. (2026). Logan Prairie Data Center. Retrieved from https://datacentercensus.com/dc/hut8-logan-prairie-logan-county-il |
|---|---|
| MLA | “Logan Prairie Data Center.” Data Center Census, Sep 24, 2026, https://datacentercensus.com/dc/hut8-logan-prairie-logan-county-il. |
| Link | https://datacentercensus.com/dc/hut8-logan-prairie-logan-county-il |
Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.