Rowan Digital Infrastructure Temple Campus
Temple, Bell County, TX[1]
- Rumored
- Proposed
- Approved
- Under construction
- Operating
Follow this project
New dated changes arrive in your feed reader or calendar. No account, no email address, no tracking.
- RSS feed for any feed reader
- Atom feed
- Hearings calendar (.ics, subscribes in Apple, Google or Outlook Calendar)
Rowan Digital Infrastructure has a multi-building data center campus in Temple, Texas. Its Bob White Road project, about 700 acres and $700 million, won unanimous city council approval in September 2025. In August 2026 Rowan asked for approval of a sixth and final building, Lasso, as a relocated building; KWTX reports four of the six buildings are under construction. KWTX says residents have raised concerns about water, electricity, noise and infrastructure.
Key facts
Size & schedule
| Site size | 700 acres [1] Bob White Road project |
|---|---|
| Buildings | 6 [2] planned across the Temple campus, with Lasso as the sixth, per KWTX |
| Stated investment | $700 million [1] Bob White Road project, per KBTX |
How big is that? Data center sizes compared with football fields and Central Park.
Figures are as stated by the cited source. Where sources disagree, each figure is shown.
Water and power
Water
Not disclosed. No source reviewed gives a water figure for this site. The Census does not estimate one.
Power
Not disclosed. No capacity or power-supply figure is on the record.
Disclosed figures only, each as the cited source states it. Many are projections or permit limits, not metered use. How data center water and power use is measured, and every disclosed figure →
Timeline
Issues raised
- Residents have raised concerns about water, electricity, noise and infrastructure, per KWTX [2]
Issues are concerns and claims raised by the parties, officials or residents named in the cited sources. They are reported as attributed, not as findings by the Census.
Sources
- New $700 million data center in Temple will be near Robinson Family FarmKBTX · Oct 7, 2025 · news
- Rowan Digital Infrastructure seeks approval for 6th and final data center in TempleKWTX · Aug 12, 2026 · news
Cite this page
Last updated Nov 6, 2026. Figures may change as records are updated — include the date you retrieved them.
| APA | Data Center Census. (2026). Rowan Digital Infrastructure Temple Campus. Retrieved from https://datacentercensus.com/dc/rowan-project-temple-tx |
|---|---|
| MLA | “Rowan Digital Infrastructure Temple Campus.” Data Center Census, Nov 6, 2026, https://datacentercensus.com/dc/rowan-project-temple-tx. |
| Link | https://datacentercensus.com/dc/rowan-project-temple-tx |
Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.