Data Center Census Near me

Utility

Oncor and data centers

2 tracked data center projects in Texas, 360 MW of planned capacity.

Part of Sempra.

Tracked data center projects

ProjectStatusPlanned capacity
PowerCampus Dallas
Texas
Under construction300 MW
Blueprint Taylor Data Center
Texas
Approved60 MW

Capacity is the planned figure each project publishes (utility load or IT load as the record notes). Total for proposed, approved, under-construction and operating projects: 360 MW. A project served by two utilities counts in full for each.

Large-load tariff and rules

We have not yet reviewed this utility’s large-load rules.

Official forecasts of data center load

  • Oncor reported 737 large commercial and industrial transmission requests at the end of Q2 2026, including about 282 GW from data centers. (Oncor (PR Newswire via Finviz), 2026-08-06)
    Source excerpt
    “Those requests included approximately 282 gigawatts from data centers.”
  • ERCOT told its board it was assessing more than 233 GW of large-load interconnection requests, over 70% from data centers. (Utility Dive, 2026-01-06)
    Source excerpt
    “more than 233 GW of large load interconnection requests, with more than 70% coming from data centers”

What sources say about customer bills

Sources saying customers are protected, or bills are lower than they would be

  • Oncor: Oncor says it held customer collateral for large-load and generation interconnection requests as of August 2026. (Oncor (PR Newswire via Finviz), 2026-08-06)
    Source excerpt
    “Oncor held approximately $5.9 billion in customer collateral for active generation and Large Commercial and Industrial”

These are statements by regulators, utilities, advocates and researchers about this utility or its region. They are not a prediction of any customer’s bill, which depends on rates, usage and regulator decisions.

More

States: Texas. Look up another utility · All utilities · Power tracker · Energy news · Tax breaks tracker

Cite this page

Last updated Oct 13, 2026. Figures may change as records are updated — include the date you retrieved them.

APAData Center Census. (2026). Oncor and data centers. Retrieved from https://datacentercensus.com/utilities/oncor
MLA“Oncor and data centers.” Data Center Census, Oct 13, 2026, https://datacentercensus.com/utilities/oncor.
Linkhttps://datacentercensus.com/utilities/oncor

Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.