Data center power and grid news

Every dated change we record that involves electricity: utility supply deals, interconnection and transmission, substations, on-site gas or nuclear generation and backup engines. 110 dated changes at 56 tracked projects in 28 states, newest first, each with the source it came from.

RSS feed · AI buildout · Rules & votes · Courts · All changes

Latest

DateWhat changedProject
Sep 18, 2026Three Siemens gas turbines arrive on site ABC 7 AmarilloFermi America Project Matador
Amarillo, Carson County, TX · Under construction
Sep 18, 2026Public Utilities Commission of Nevada approves the two gas plants, subject to environmental permits and Storey County approvals Nevada CurrentFleet Data Centers TRIC campuses (South Valley and Peru Ridge)
Storey County, NV · Proposed
Sep 14, 2026ATC refiles its application for the grid upgrades serving the campus, dropping a Trenton-Saukville line segment and restarting the PSC's six-month review Wisconsin WatchPort Washington (Lighthouse) Data Center Campus
Port Washington, Ozaukee County, WI · Under construction
Sep 4, 2026Appalachian Power files application with the State Corporation Commission for grid upgrades to serve the campus Cardinal NewsGoogle Botetourt County Data Center Campus
Botetourt County, VA · Approved
Sep 2, 2026Chamber panel addresses resident concerns over housing, power, water and noise KACUStargate Abilene
Abilene, Taylor County, TX · Operating
Sep 2026Uinta County commissioners approve a conditional use permit for the project's independent power production facility Wyoming News (via NewsBreak)Prometheus Hyperscale Evanston Campus
Evanston, Uinta County, WY · Approved
Sep 2026State grants permission to add more natural gas turbines FOX CarolinaValara Holdings High Performance Compute Center
Spartanburg, Spartanburg County, SC · Under construction
Aug 28, 2026NC DEQ announces final air quality permits for Amazon's 588 emergency engines and Duke Energy's 57 bridge power engines NC Department of Environmental QualityAmazon Web Services Richmond County data center campus
Hamlet, Richmond County, NC · Under construction
Aug 27, 2026SC Public Service Commission rules the utility siting law does not apply to the facility SC Daily GazetteValara Holdings High Performance Compute Center
Spartanburg, Spartanburg County, SC · Under construction
Aug 12, 2026LPSC votes 3-1 to reject an administrative law judge's recommendation to make Meta job and power-demand information available through subpoenas WWNOMeta Hyperion
Holly Ridge, Richland Parish, LA · Under construction
Aug 12, 2026City issues two stop-construction orders over LNG tank and Bloom Energy fuel cell work done without permits WHYYNebius Vineland Data Center
Vineland, Cumberland County, NJ · Under construction
Aug 11, 2026Sailfish commits project to Governor Abbott's audit process and SB 6 interconnection requirements Sailfish Investors (via National Law Review)Comanche Circle
Tolar, Hood County, TX · Approved
Aug 10, 2026Linn County drops proposal to allow large data centers co-located with nuclear plants in the EU-2 zoning district KCRGGoogle Palo data center campus
Palo, Linn County, IA · Proposed
Aug 7, 2026Utility information form filed estimating 894 MW electric load Spotsylvania CountyCrossroads Technology Campus
Spotsylvania County, VA · Proposed
Aug 7, 2026PSC requires ATC to restart its application for the $1.3B+ transmission line and five substations serving the campus Wisconsin WatchPort Washington (Lighthouse) Data Center Campus
Port Washington, Ozaukee County, WI · Under construction
Aug 2026State regulators reviewing draft air permits for backup diesel generators after public hearings Inside Climate NewsAmazon Web Services Richmond County data center campus
Hamlet, Richmond County, NC · Under construction
Jul 30, 2026NC DEQ holds joint public hearing on the Amazon and Duke Energy air quality permits in Rockingham NC Department of Environmental QualityAmazon Web Services Richmond County data center campus
Hamlet, Richmond County, NC · Under construction
Jul 30, 2026Mississippi DEQ sets retirement schedule for 69 temporary turbines at the Southaven plant (Aug. 18, 2026 to July 14, 2027), allowing 13 to run past the original deadline Mississippi TodayxAI Colossus 2
Memphis, Shelby County, TN · Under construction
Jul 28, 2026Oracle says Bloom fuel cells will power campus; ~700 New Mexicans working onsite OracleProject Jupiter
Santa Teresa, Doña Ana County, NM · Under construction
Jul 24, 2026PUCT approves net metering application in Docket No. 59220 for the co-located Armstrong County data center load, with ERCOT curtailment obligations White & Case LLPGoodnight Campus
Claude, Armstrong County, TX · Under construction
Jul 16, 2026Microsoft signs 15-year electric service contract with We Energies Wisconsin WatchMicrosoft Fairwater
Mount Pleasant, Racine County, WI · Operating
Jul 8, 2026State Office of Administrative Hearings begins testimony on El Paso Electric's proposed McCloud Generation Facility CBS4 / KFOX14Meta El Paso Data Center
El Paso, El Paso County, TX · Under construction
Jul 2, 2026California Public Utilities Commission unanimously authorizes Liberty Utilities to seek bids for a new Lake Tahoe power supplier CapRadioFleet Data Centers TRIC campuses (South Valley and Peru Ridge)
Storey County, NV · Proposed
Jul 2026Palo passes a data center ordinance; Linn County, which recently began an 18-month data center moratorium, considers allowing data centers as accessories to nuclear plants Iowa Public RadioGoogle Palo data center campus
Palo, Linn County, IA · Proposed
Jul 2026CB-3 delivered, bringing AI capacity online to 102 MW TeraWulfLake Mariner
Somerset, Niagara County, NY · Operating
Jun 30, 2026CRG unveils refined design: four single-story buildings, ~600 MW, closed-loop cooling The Missouri Times (CRG release)CRG Festus Data Center
Festus, Jefferson County, MO · Approved
Jun 26, 2026OPSB authorizes the 250 MW Socrates the Younger plant (Case 26-0169-EL-BLN) to serve adjacent Meta data center Ohio Power Siting BoardMeta Prometheus
New Albany, Franklin and Licking counties, OH · Operating
Jun 18, 2026NRG requests withdrawal of its air permit application for the 2 GW Tolar Power Center planned to supply Comanche Circle KERA NewsComanche Circle
Tolar, Hood County, TX · Approved
Jun 12, 2026DNR issues air construction and operation permits for 45 diesel emergency generators Wisconsin Department of Natural ResourcesPort Washington (Lighthouse) Data Center Campus
Port Washington, Ozaukee County, WI · Under construction
Jun 10, 2026County adopts 180-day moratorium on new data centers and data center power plants; Stratos exempt because it falls under MIDA Utah Public RadioStratos Project
Box Elder County, UT · Proposed
Jun 9, 2026Permit documents show two buildings (10 MW and 40 MW) plus generator yards and substation WSMVDC BLOX Nashville Data Center
Nashville, Davidson County, TN · Proposed
Jun 9, 2026Southaven residents file a federal class action against xAI and MZX Tech over turbine noise. Mississippi TodayxAI Colossus 2
Memphis, Shelby County, TN · Under construction
Jun 2026Stream Data Centers says on its website that Project Liberty will not move forward, citing utility timing constraints WMBF NewsProject Liberty
Marion, Marion County, SC · Cancelled
May 23, 2026Buildings 3-4 become operational, bringing IT power to about 421 MW, per Epoch AI satellite analysis Epoch AIStargate Abilene
Abilene, Taylor County, TX · Operating
May 15, 2026NV Energy states data centers did not influence the Liberty decision and it will serve Liberty until Greenlink West is in place KTVN 2NewsFleet Data Centers TRIC campuses (South Valley and Peru Ridge)
Storey County, NV · Proposed
May 13, 2026Planning Commission approves site plan for substation/switching station Planet DetroitProject Cannoli
Van Buren Township, Wayne County, MI · Approved
May 12, 2026Fortune publishes report linking NV Energy's Tahoe supply exit to data center demand FortuneFleet Data Centers TRIC campuses (South Valley and Peru Ridge)
Storey County, NV · Proposed
May 7, 2026Wisconsin Public Service Commission approves a modified version of Alliant Energy's one-off power supply contract with the Meta subsidiary Wisconsin WatchMeta Beaver Dam Data Center
Beaver Dam, Dodge County, WI · Under construction
May 2026NV Energy enters large load electric service agreement with Fleet subsidiary SV RNO Property Owner 1, LLC This Is Reno / Nevada CurrentFleet Data Centers TRIC campuses (South Valley and Peru Ridge)
Storey County, NV · Proposed
Apr 24, 2026U.S. Energy Secretary Chris Wright tours campus The GazetteQTS Cedar Rapids Data Center Campus
Cedar Rapids, Linn County, IA · Under construction
Apr 20, 2026Fleet files PUCN applications for South Valley (Docket 26-04026) and Peru Ridge (Docket 26-04027) self-generation plants The Nevada IndependentFleet Data Centers TRIC campuses (South Valley and Peru Ridge)
Storey County, NV · Proposed
Apr 20, 2026Monarch Cloud Campus LLC submits air construction permit application to WVDEP for 2.16 GW on-site generation Charleston Gazette-MailMonarch Compute Campus
Point Pleasant, Mason County, WV · Under construction
Apr 16, 2026LPSC votes 4-1 to fast-track Entergy's plan for seven new gas plants for the campus Louisiana Radio NetworkMeta Hyperion
Holly Ridge, Richland Parish, LA · Under construction
Mar 23, 2026Environmental Hearing Board denies Homer City Generation's motion to consolidate the two permit appeals Lehigh DailyHomer City Energy Campus
Homer City, Indiana County, PA · Under construction
Mar 20, 2026CalMatters reports NV Energy will not renew power supply to Liberty Utilities' ~49,000 Lake Tahoe customers (contract ending May 2027), citing its own resource needs CalMattersFleet Data Centers TRIC campuses (South Valley and Peru Ridge)
Storey County, NV · Proposed
Mar 20, 2026DOE, SoftBank and SB Energy announce 10 GW data center campus and 9.2 GW gas generation at the Portsmouth site U.S. Department of EnergyPORTS-Pike Technology Campus
Piketon, Pike County, OH · Under construction
Mar 17, 2026Google and DTE Energy confirm Google as the company behind the project; Google commits to a contested case at the MPSC Michigan AdvanceProject Cannoli
Van Buren Township, Wayne County, MI · Approved
Mar 16, 2026KMUW reports Monarch Energy and NextEra Energy are pursuing 1,000+ acres in western Sedgwick County KMUWWest Sedgwick County data center land acquisitions
Sedgwick County, KS · Rumored
Mar 14, 2026Date of Amazon's air construction permit application cover letter; the application covers 483 generators Missouri Department of Natural Resources, Air Pollution Control ProgramAWS Project Green
New Florence, Montgomery County, MO · Approved
Mar 10, 2026Mississippi DEQ board approves 41 turbines (1.2 GW) to power Colossus 2 and planned Colossus 3 DatacenterDynamicsxAI Colossus 2
Memphis, Shelby County, TN · Under construction
Mar 2026Wind-powered portion of the campus sold to Ensign Infrastructure, which becomes the large load in the co-location application Latitude MediaGoodnight Campus
Claude, Armstrong County, TX · Under construction
Mar 2026Valara asks SCDES to add natural gas combustion turbines to its air permit SC Daily GazetteValara Holdings High Performance Compute Center
Spartanburg, Spartanburg County, SC · Under construction
Feb 12, 2026Google says it 'will cover the full energy costs associated with powering both of the Google data center campuses' KSHB 41Google Kansas City Data Center (Hunt Midwest Business Center)
Kansas City, Clay County, MO · Under construction
Feb 3, 2026DCD reports Aligned plans natural gas-powered data center buildings at the 660-acre Shippingport Industrial Park owned by Frontier Group of Companies DatacenterDynamicsProject Phoenix
Shippingport, Beaver County, PA · Under construction
Jan 27, 2026The Department of Energy ordered the data center to cut 50 MW from the grid; backup diesel generators ran and cold weather disrupted pollution controls on five of them InkFreeNews.com (Indianapolis Star / Notre Dame Gallivan Program)Project Rainier (AWS New Carlisle campus)
New Carlisle, St. Joseph County, IN · Operating
Jan 18, 2026El Paso Electric proposes $473M McCloud gas plant to serve the data center KVIA (El Paso Matters)Meta El Paso Data Center
El Paso, El Paso County, TX · Under construction
Jan 14, 2026Alliance for Affordable Energy and Union of Concerned Scientists ask the LPSC to investigate Meta's new financing arrangement for Hyperion and review Entergy's prudence Alliance for Affordable Energy and Union of Concerned Scientists (Earthjustice)Meta Hyperion
Holly Ridge, Richland Parish, LA · Under construction
Jan 14, 2026Application filed with Mississippi regulators for 41-turbine permit Southern Environmental Law CenterxAI Colossus 2
Memphis, Shelby County, TN · Under construction
Jan 13, 2026Commissioners conditionally approve concept plan 4-1, requiring more detail on drainage, wastewater, landscape and power generation KERA NewsComanche Circle
Tolar, Hood County, TX · Approved
Jan 13, 2026EGLE issues the air quality permit for 14 diesel backup generators and a diesel firewater pump. Planet DetroitSaline Township Stargate Data Center
Saline Township, Washtenaw County, MI · Under construction
Jan 12, 2026Pecos County Commissioners Court agenda includes a tax abatement agreement with CoreWeave, LLC within the Longfellow Renewable Energy Reinvestment Zone Pecos County, TexasProject Horizon
Fort Stockton, Pecos County, TX · Proposed
Jan 2026OpenAI and SoftBank each invest $500M in SB Energy, which will build and operate the site DCDStargate Milam County
Burlington, Milam County, TX · Under construction
Dec 17, 2025Hut 8 signs 15-year, 245 MW lease with Fluidstack; state and Entergy announce $10 billion project Louisiana Economic DevelopmentHut 8 River Bend Campus
St. Francisville, West Feliciana Parish, LA · Under construction
Dec 15, 2025Memphis and Shelby County Air Pollution Control Board dismisses appeals of the turbine permit as moot Action News 5xAI Colossus
Memphis, Shelby County, TN · Operating
Dec 5, 2025Fermi America announces electric service agreement with Southwestern Public Service Company for up to 200 MW Fermi America (PR Newswire)Fermi America Project Matador
Amarillo, Carson County, TX · Under construction
Dec 2025Google details plans for the 550-acre campus and says utilities and foundation work will begin in February WISH-TVGoogle Morgan County Data Center
Monrovia, Morgan County, IN · Under construction
Nov 26, 2025KOMU reports AWS plans a data center near New Florence, with power from Ameren Missouri KOMU 8AWS Project Green
New Florence, Montgomery County, MO · Approved
Nov 24, 2025Phase II ready for service; Building 1 fully energized at 100 MW Applied DigitalPolaris Forge 1
Ellendale, Dickey County, ND · Operating
Nov 2025Cloverleaf presents the proposal at a public meeting; residents raise water, power and noise concerns FOX 2 DetroitProject Cherry Blossom
Frenchtown Township, Monroe County, MI · Proposed
Oct 17, 2025EGLE issues a permit waiver allowing Related Digital to begin installing generators before the final air permit. Planet DetroitSaline Township Stargate Data Center
Saline Township, Washtenaw County, MI · Under construction
Oct 15, 2025Poolside announces Project Horizon with CoreWeave as anchor tenant under a 15-year, 250 MW lease PoolsideProject Horizon
Fort Stockton, Pecos County, TX · Proposed
Aug 29, 2025CoreWeave signs additional 150 MW lease, bringing Polaris Forge 1 to 400 MW Applied DigitalPolaris Forge 1
Ellendale, Dickey County, ND · Operating
Aug 25, 2025Beale and TEP file special power agreement with Arizona Corporation Commission AZ LuminariaProject Blue
Tucson, Pima County, AZ · Under construction
Aug 20, 2025LPSC approves Entergy Louisiana's three combined-cycle gas plants (~3,000 MW) and transmission for the data center EntergyMeta Hyperion
Holly Ridge, Richland Parish, LA · Under construction
Aug 18, 2025Fluidstack adds 160 MW CB-5 lease; Google backstop rises to about $3.2 billion TeraWulfLake Mariner
Somerset, Niagara County, NY · Operating
Aug 14, 2025TeraWulf signs 200+ MW, 10-year hosting agreements with Fluidstack; Google backstops $1.8 billion TeraWulfLake Mariner
Somerset, Niagara County, NY · Operating
Jul 16, 2025xAI affiliate MZX Tech buys former Duke power plant site in Southaven, MS Southern Environmental Law CenterxAI Colossus 2
Memphis, Shelby County, TN · Under construction
Jul 15, 2025Agreement in principle announced for EQT to supply up to 665,000 MMBtu/day of gas Homer City Redevelopment (via Seeking Alpha)Homer City Energy Campus
Homer City, Indiana County, PA · Under construction
Jul 2, 2025Shelby County Health Department approves permit for 15 gas turbines through Jan. 1, 2027 (DCD reports July 1 meeting) Tennessee LookoutxAI Colossus
Memphis, Shelby County, TN · Operating
Jun 11, 2025Talen and AWS sign a 1,920-MW PPA; the existing 300-MW co-location arrangement moves to a front-of-the-meter framework Utility DiveSalem Township Innovation Campus
Salem Township, Luzerne County, PA · Under construction

Showing the 80 most recent of 110 changes. Older entries stay on each project page.

Where it is happening

Read next

How this page is built

Entries come from the dated events in the Census. Each one was recorded from a published filing, notice or news report, which is linked beside it. Nothing here is written by an automated summarizer of the news.

Cite this page

Last updated Sep 22, 2026. Figures may change as records are updated — include the date you retrieved them.

APAData Center Census. (2026). Data center power and grid news. Retrieved from https://datacentercensus.com/news/power
MLA“Data center power and grid news.” Data Center Census, Sep 22, 2026, https://datacentercensus.com/news/power.