Prime Phoenix Campus

Also known as Prime Phoenix

Under constructionGround broken on first three buildings in May 2026
  1. Rumored
  2. Proposed
  3. Approved
  4. Under construction
  5. Operating

Prime Data Centers is building a five-building hyperscale data center campus in Avondale that will ultimately span 66.5 acres, 1.3 million square feet and 240MW of total critical power. In May 2026 Prime broke ground on the first three buildings, each a 267,000 square-foot facility delivering 48MW of critical IT load, and Buildings 1–3 have been secured by a leading hyperscaler. The campus is powered by a dedicated on-site substation and uses a closed-loop cooling system engineered for zero process water use during operations.

Key facts

Size & schedule

Planned capacity240 MW [2]
total critical power at full build-out
Source excerpt
“the campus, which will ultimately span 66.5 acres, 1.3 million square feet and 240MW of total critical power across five hyperscale data centers”
Planned capacity210 MW [1]
differing figure: critical power stated at the May 2023 announcement
Source excerpt
“Prime Phoenix will feature 210 megawatts of critical power and 1.3 million square feet of space.”
Phase 1 capacity144 MW [3]
critical IT load across first three buildings
Source excerpt
“48MW of critical IT load, for a combined 144MW in the opening phase”
Site size66.5 acres [2]
Source excerpt
“the campus, which will ultimately span 66.5 acres, 1.3 million square feet and 240MW of total critical power across five hyperscale data centers”
Floor area1.3 million sq ft [2]
Source excerpt
“the campus, which will ultimately span 66.5 acres, 1.3 million square feet and 240MW of total critical power across five hyperscale data centers”
Buildings5 [2]
Source excerpt
“the campus, which will ultimately span 66.5 acres, 1.3 million square feet and 240MW of total critical power across five hyperscale data centers”
Stated investment$3 billion [2]
more than $3 billion by Prime; release says customers invest an average 2x more
Source excerpt
“This more than $3 billion investment by Prime with its customers investing an average 2x more represents a major step forward for our local economy, bringing new jobs, long-term growth and world-class infrastructure to our community.”
Permanent jobs (promised)150 [4]
around
Source excerpt
“Around 150 high-tech, well-paid jobs will also be created.”

Power

Power supplyDedicated on-site substation [2]
Source excerpt
“Powering the campus is a dedicated on-site substation.”
Power supply250MW substation, Phase 1 commissioned [3]
Source excerpt
“Phase 1 of the campus's 250MW substation has already been commissioned.”

Water

Coolingclosed-loop cooling engineered for zero process water use during operations [2]
Source excerpt
“The facility will feature a closed-loop cooling system engineered for zero process water use during operations, eliminating the need for ongoing water consumption as part of the cooling process while enabling precise thermal management for high-density compute environments.”

Figures are as stated by the cited source. Where sources disagree, each figure is shown.

Timeline

  1. Prime announces a five-building, 66.5-acre campus in Avondale [1]

  2. Prime breaks ground on three buildings; Buildings 1–3 secured by a leading hyperscaler [2]

Sources

  1. Prime Announces First Phoenix Data Center Campus
    Prime Data Centers · May 4, 2023 · company
  2. Prime Data Centers Breaks Ground on Three Buildings at its 240MW Campus in Phoenix, Advancing $3B Investment in Avondale
    Prime Data Centers · May 21, 2026 · company
  3. Prime Data Centers Breaks Ground on Three Buildings in Phoenix
    ConstructConnect · May 26, 2026 · news
  4. Avondale is getting its first data center. Here's what you need to know
    12News · news