Bluffdale, Utah County, UT
Utah Data Center
Also known as NSA Utah Data Center, Community Comprehensive National Cybersecurity Initiative Data Center
- Rumored
- Proposed
- Approved
- Under construction
- Operating
The Utah Data Center is a National Security Agency facility at the Utah National Guard's Camp Williams near Bluffdale, built with the U.S. Army Corps of Engineers as construction agent; ground was broken on Jan. 6, 2011. Plans called for approximately 1 million sq ft of enclosed space, including 100,000 sq ft of computer space, on a 240-acre site, and the Army Corps estimated the facility would require 65 megawatts of electricity. Bluffdale built a $3 million water-delivery system for the center, and city records show more water went into the facility in 2014 than in previous years.
Key facts
Size & schedule
| Planned capacity | 65 MW [5] U.S. Army Corps of Engineers estimate of electricity required Source excerpt“The U.S. Army Corps of Engineers has estimated the NSA facility will require 65 megawatts of electricity to run its equipment around the clock, which would put its annual power bill at about $18 million.” |
|---|---|
| Site size | 240 acres [2] construction site at Camp Williams Source excerpt“Construction on the nation's first data security center for the National Security Agency officially launched with a groundbreaking Jan. 6 on a 240-acre site at the Utah National Guard's Camp Williams facility about 35 miles southwest of Salt Lake City.” |
| Site size | 235 acres [3] MIDA Utah Data Center Project Area Source excerpt“235 acres at Camp Williams” |
| Floor area | 1 million sq ft [2] approximately 1 million sq ft of enclosed space, including 100,000 sq ft of computer space Source excerpt“The center will consist of multiple buildings providing approximately 1 million sq ft of enclosed space, including 100,000 sq ft of computer space devoted to filtering and detecting threats to the nation's cyber security.” |
| Floor area | 1.5 million sq ft [7] differing figure reported by NPR in 2013 Source excerpt“The $1.2 billion complex covers 1.5 million square feet, and includes 100,000 square feet devoted solely to computers and servers.” |
| Stated investment | $1.2 billion [1] $1.2 billion as stated at the 2011 groundbreaking Source excerpt“Groundbreaking Ceremony Held for $1.2 Billion Utah Data Center” |
| Stated investment | $1.5 billion [5] differing figure: $1.5 billion construction, as stated by an official quoted in the Salt Lake Tribune in 2013 Source excerpt“Long-term stability in the utility rates was a major factor in Utah being selected as our site for our $1.5 billion construction at Camp Williams.” |
| Permanent jobs (promised) | 100 to 200 [1] range as stated Source excerpt“100 to 200 permanent, high-paid employees” |
| Construction jobs | 5,000 to 10,000 [1] range as stated Source excerpt“5,000 to 10,000 new jobs during the construction and development phase” |
| Target completion | October 2013 [2] original planned completion Source excerpt“Known officially as the Community Comprehensive National Cybersecurity Initiative Data Center or the Utah Data Center, the project is planned for completion in October 2013.” |
Power
| Power supply | Dedicated 65 MW power substation [2]Source excerpt“Kiewit Federal will remain at the site working on a $25-million contract to build the 65 MW power substation.” |
|---|
Water
| Water use | 1,700,000 gal/day [6] maximum projected requirement ('as many as') Source excerpt“The NSA data center in Bluffdale could require as many as 1.7 million gallons of water per day to operate and keep computers cool.” |
|---|---|
| Water use | 1,200,000 gal/day [9] planned figure later reduced from 1.7 million gallons a day, per Bluffdale City Council minutes Source excerpt“Bluffdale City Council minutes indicate that figure was later reduced to 1.2 million gallons a day.” |
| Water source | municipal (City of Bluffdale water-delivery system) [9]Source excerpt“Bluffdale built a $3 million water-delivery system for the center.” |
Figures are as stated by the cited source. Where sources disagree, each figure is shown.
Timeline
Utah Military Installation Development Authority (MIDA) creates the Utah Data Center Project Area [3]
Groundbreaking held at Camp Williams [2]
Bluffdale City Council unanimously adopts annexation plan encompassing the data center and Camp Williams [4]
NSA says failures that occurred during testing have been mitigated, after reports of electrical surges [7]
Bluffdale records show the facility's monthly water usage peaked at 6.6 million gallons [9]
Issues raised
- The Wall Street Journal reported 10 electrical 'meltdowns' and power surges over 13 months during testing, and that backup generators failed numerous tests [7]
- Water records showed the facility paying minimum 'take or pay' charges for water it was not using [8][9]
- State officials discussed exempting the facility from a MIDA tax on electricity use of up to 6 percent authorized by HB325 [5]
Sources
- Groundbreaking Ceremony Held for $1.2 Billion Utah Data CenterNational Security Agency/Central Security Service · Jan 6, 2011 · government
- Construction of National Cyber Security Center Gets Under Way in UtahEngineering News-Record · Jan 11, 2011 · news
- Utah Data Center Project AreaMilitary Installation Development Authority (MIDA) · government
- Bluffdale OKs plans to annex NSA data centerThe Salt Lake Tribune · Mar 10, 2011 · news
- Utah moving to exempt NSA Data Center from taxThe Salt Lake Tribune · Aug 2, 2013 · news
- New Utah NSA center requires 1.7M gallons of water daily to operateKSL.com · Jul 12, 2013 · news
- NSA Says It Has 'Mitigated' Meltdowns At Utah Data FarmNPR · Oct 8, 2013 · news
- NSA Data Center's Water Use Pattern Indicates EconomizationData Center Knowledge · May 2, 2014 · news
- NSA Utah Data Center using more waterThe Salt Lake Tribune · Feb 2, 2015 · news