Data Center Census Near me

Utility

AEP Ohio and data centers

1 tracked data center project in Ohio, 10 GW of planned capacity, large-load tariff approved.

Part of American Electric Power.

Tracked data center projects

ProjectStatusPlanned capacity
PORTS-Pike Technology Campus
Ohio
Under construction10 GW

Capacity is the planned figure each project publishes (utility load or IT load as the record notes). Total for proposed, approved, under-construction and operating projects: 10 GW. A project served by two utilities counts in full for each.

Large-load tariff and rules

Status
Large-load tariff or rules approved (2025-07-09)
Tariff
AEP Ohio data center tariff
Docket
Case No. 24-508-EL-ATA, Public Utilities Commission of Ohio
What it says
PUCO's July 9, 2025 order adopted a settlement; POWER Magazine reports large new data center customers (loads above 25 MW) must pay for at least 85% of subscribed usage for up to 12 years. (POWER Magazine)
Source excerpt
“requiring large new data center customers to pay for a minimum of 85% of their subscribed electricity usage—regardless of actual consumption—for up to 12 years.”

Official forecasts of data center load

  • AEP Ohio's testimony, as reported by POWER Magazine, projects data center load in Central Ohio reaching 5 GW by 2030, up from about 600 MW in 2024. (POWER Magazine, 2025-07-10)
    Source excerpt
    “the company projects data center loads will rapidly accelerate to reach 5 GW in Central Ohio by 2030.”
  • AEP Ohio reported service inquiries from over 50 customers at over 90 sites totaling more than 30,000 MW (requests, not a forecast). (POWER Magazine, 2025-07-10)
    Source excerpt
    “AEP Ohio has received inquiries and preliminary requests for service from over 50 customers at over 90 sites totaling more than 30,000 MW”

What sources say about customer bills

Sources warning that other customers’ costs could rise

  • PJM independent market monitor (Monitoring Analytics), PJM-wide finding: The PJM market monitor says data center load additions have raised costs that will be paid through May 2028 and may raise transmission, energy and capacity costs for other customers across the PJM region. (Utility Dive, 2026-03-12)
    Source excerpt
    “Large data center load additions have already had a significant and irreversible impact that will be paid through May of 2028 and will have additional significant impacts on other customers as a result of higher transmission costs, higher energy market prices and higher capacity market prices,”

Sources saying customers are protected, or bills are lower than they would be

  • Public Utilities Commission of Ohio: PUCO said the approved settlement safeguards non-data-center customers from cost-shifting risks of underused investments made to serve data centers. (Public Utilities Commission of Ohio, 2025-07-09)
    Source excerpt
    “In its order, the Commission noted the settlement safeguards other non-data center customers from cost-shifting risks of underused investments made to serve Ohio’s growing data center industry.”

These are statements by regulators, utilities, advocates and researchers about this utility or its region. They are not a prediction of any customer’s bill, which depends on rates, usage and regulator decisions.

More

States: Ohio. Look up another utility · All utilities · Power tracker · Energy news · Tax breaks tracker

Cite this page

Last updated Oct 13, 2026. Figures may change as records are updated — include the date you retrieved them.

APAData Center Census. (2026). AEP Ohio and data centers. Retrieved from https://datacentercensus.com/utilities/aep-ohio
MLA“AEP Ohio and data centers.” Data Center Census, Oct 13, 2026, https://datacentercensus.com/utilities/aep-ohio.
Linkhttps://datacentercensus.com/utilities/aep-ohio

Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.