How much does it cost to build a data center, and how long does it take?

Reviewed Sep 22, 2026 · 3 sections · every figure sourced

Short answer

Building a modern data center costs about $17.6 million per megawatt of capacity on average in the U.S. and Canada, not counting the chips and GPUs inside, according to Cushman & Wakefield’s 2026 cost guide, and costs per megawatt are up 21% since late 2024[1]. At that average, a 100-megawatt campus would cost about $1.76 billion before computing equipment. An individual data center building usually takes about 12 to 18 months to build, according to Virginia’s legislative auditors[2]; large campuses are built in phases over several years.

average all-in cost per MW, U.S. and Canada, excluding chips and GPUs[1]
$17.6M
rise in construction cost per MW since Q4 2024[1]
+21%
typical construction time for one data center building, per JLARC[2]
12–18 months

Cost per megawatt

Industry cost guides quote data center costs per megawatt (MW) of power capacity rather than per square foot, since power infrastructure is the biggest single cost[1]. Cushman & Wakefield’s 2026 Data Center Development Cost Guide puts all-in greenfield development costs in the U.S. and Canada at an average of $17.6 million per megawatt for the most modern facilities, excluding chips and GPUs[1]. The firm says construction costs per megawatt have risen an average of 21% since its previous guide in the fourth quarter of 2024[1].

Applied to that average, a 100 MW campus works out to about $1.76 billion and a 1 gigawatt campus to about $17.6 billion, before the servers and chips that fill the buildings. Real projects vary with the market, the design and how much power infrastructure the developer has to build. Globally, Cushman & Wakefield estimates the development pipeline at about $2.3 trillion, with $492 billion under construction[1].

For comparison, Georgia’s 2022 tax incentive evaluation modeled a hypothetical $800 million data center with a two-year construction phase[3].

What drives the cost

  • Power infrastructure. The largest single cost category, averaging 21% of total greenfield development costs; contingencies rank second because of long material lead times, labor shortages and regulatory uncertainty[1].
  • Land with power. Powered land in primary U.S. markets averaged $584,000 per megawatt in 2026 so far, 35% above its five-year average and 51% higher than a year earlier[1].
  • Skilled labor. Shortages of mechanical, electrical and plumbing workers drove a 5% average annual wage increase from 2021 to 2024, with steeper growth in secondary and tertiary markets[1].

Power plants and transmission lines built to serve a campus are sometimes announced separately from the data center itself. Project records in the Census note these where a source reports them; see the power and generation tracker.

How long does it take to build a data center?

Construction of an individual data center building usually takes about 12 to 18 months, according to Virginia’s Joint Legislative Audit and Review Commission, and data center representatives told JLARC that about 1,500 workers are on site at the peak[2]. Georgia’s evaluation assumed a construction phase of about two years for its modeled $800 million facility[3].

Large campuses take longer because they are built and switched on in phases, and because land use approvals, utility agreements and permits can come before any construction starts. The examples below, taken from dated timelines in the Census, show how widely schedules vary.

Build times from the Census record

ProjectFromToMonths
xAI Colossus
Reused an existing 785,000-sq-ft former factory building.
Announced
Jun 5, 2024
Began operations
Sep 2024
3
Project Rainier (AWS New Carlisle campus)
New campus; a county tax abatement was approved in between.
Announced by Indiana’s governor
Apr 25, 2024
AWS activated Project Rainier
Oct 29, 2025
18
Stargate Abilene
Eight buildings; construction expected to run into 2027.
Construction began
Jun 2024
First phase live
Sep 30, 2025
15
Polaris Forge 1
Second and third buildings slated for 2026 and 2027.
Construction began
Sep 2022
First building phase ready for service
Oct 2025
37

Months are counted between the dated timeline events shown; each project page lists the source for every date. Where only a month is published, the count uses that month.

What announced projects say they will spend

44 projects in the Census publish both a stated investment and a planned capacity. Dividing one by the other gives a median of $10M per megawatt, with the middle half of projects between $5.4M and $17M. Treat this as a rough comparison, not a construction cost: announced figures mix phases, land, power plants and sometimes regional totals, and capacity may be utility load rather than IT load. Open a project for the exact wording of each figure.

ProjectCapacityStated investmentPer MW
Project Jupiter
NM
2.46 GW$165 billion$67M
Meta Hyperion
LA
5 GW$50 billion$10M
Vantage Frontier Campus
TX
1.4 GW$25 billion$18M
Monarch Compute Campus
WV
8 GW$20 billion$2.5M
Project Camellia
GA
3.21 GW$20 billion$6.2M
Joliet Technology Center
IL
1.8 GW$20 billion$11M
Stream Data Centers STAMP Campus
NY
500 MW$19 billion$38M
T5 @ Chicago IV
IL
1.55 GW$18 billion$12M
Project Tembo
WY
2.7 GW$17 billion$6.3M
Project Sail
GA
900 MW$17 billion$19M
Saline Township Stargate Data Center
MI
1.38 GW$16 billion$12M
Port Washington (Lighthouse) Data Center Campus
WI
1.3 GW$15 billion$12M
Project Marvel
AL
1.2 GW$14.5 billion$12M
Meta El Paso Data Center
TX
1 GW$14 billion$14M
Sentinel Grove Technology Park
FL
1 GW$13.5 billion$14M
Project Tamarack
WV
2.16 GW$12 billion$5.6M
Amazon Web Services Louisa County campuses
VA
600 MW$11 billion$18M
PORTS-Pike Technology Campus
OH
10 GW$10 billion$1M
Homer City Energy Campus
PA
4.4 GW$10 billion$2.3M
Project Phoenix
PA
2 GW$10 billion$5M
QTS Cedar Rapids Data Center Campus
IA
1.05 GW$10 billion$9.5M
Meta Lebanon Data Center
IN
1 GW$10 billion$10M
Hut 8 River Bend Campus
LA
330 MW$10 billion$30M
Imperial Data Center
CA
330 MW$10 billion$30M
Viridian Data Center Campus (former GM/JATCO site)
WI
800 MW$8 billion$10M
Core Scientific Denton Data Center
TX
260 MW$6.1 billion$23M
Project Boulder
SC
1 GW$6 billion$6M
CRG Festus Data Center
MO
600 MW$6 billion$10M
Project Lincoln
KY
600 MW$6 billion$10M
CoreWeave Lancaster data center
PA
300 MW$6 billion$20M
Quantum Frederick
MD
2.4 GW$5 billion$2.1M
Brightseat Tech Park
MD
820 MW$5 billion$6.1M
Farmington Technology Park
MN
708 MW$5 billion$7.1M
Project Blue
AZ
286 MW$3.6 billion$13M
Prime Phoenix Campus
AZ
240 MW$3 billion$13M
Fort Meade Hyperscale Data Center
FL
1.2 GW$2.6 billion$2.2M
Utah Data Center
UT
65 MW$1.2 billion$18M
Meta Beaver Dam Data Center
WI
220 MW$1 billion$4.5M
Blueprint Taylor Data Center
TX
60 MW$1 billion$17M
CyrusOne Sangamon County Data Center
IL
634 MW$500 million$0.8M
Stargate Milam County
TX
1.2 GW$470 million$0.4M
DC BLOX Nashville Data Center
TN
10 MW$380 million$38M
Deep Green Lansing data center
MI
24 MW$120 million$5M
Project Aggie
TX
600 MW$30 million$0.1M

Common questions

How much does it cost to build a data center?

Cushman & Wakefield’s 2026 guide puts the average all-in cost of a modern greenfield data center in the U.S. and Canada at $17.6 million per megawatt, excluding chips and GPUs. Costs vary widely by market, design and how much power infrastructure has to be built.

How much does a 100 MW data center cost?

At Cushman & Wakefield’s 2026 average of $17.6 million per megawatt, a 100 MW data center would cost about $1.76 billion before servers, chips and GPUs.

How long does it take to build a data center?

Virginia’s JLARC says an individual data center building usually takes about 12 to 18 months to construct. Large campuses are built in phases over several years, and approvals and utility agreements can add time before construction starts.

What is the biggest cost in building a data center?

Power infrastructure, which averages 21% of total greenfield development costs according to Cushman & Wakefield, followed by contingencies.

Sources

  1. Cushman & Wakefield Releases 2026 Data Center Development Cost Guide, Citing 21% Rise in Per-MW Construction Costs
    Cushman & Wakefield (company press release) · 2026-09-03
    6 source excerpts
    “All-in greenfield development costs in the United States and Canada average $17.6M per megawatt for the most modern facilities, excluding chips and GPUs.”
    “Cushman & Wakefield (NYSE: CWK), a leading global commercial real estate services firm, has published its 2026 Data Center Development Cost Guide, revealing that data center construction costs have risen an average of 21% per megawatt (MW) since the previous edition was published in the fourth quarter of 2024.”
    “Power infrastructure remains the single largest cost category, representing an average of 21% of total greenfield development costs, while contingencies rank second, reflecting ongoing uncertainty driven by long material lead times, labor shortages, and a shifting regulatory environment.”
    “The global data center development pipeline now represents approximately $2.3 trillion in investment capital, of which $492 billion is currently under construction and the remaining $1.8 trillion is tied to planned and precommitted projects.”
    “markets achieving average values of $584,000 per MW in 2026 year-to-date—35% above its five-year average and 51% higher year-over-year.”
    “Skilled labor shortages in the mechanical, electrical, and plumbing trades continue to compound cost pressures, driving a 5% average annual wage increase from 2021 to 2024, with even steeper growth recorded in secondary and tertiary markets.”
  2. Data Centers in Virginia (Report Summary)
    Joint Legislative Audit and Review Commission (JLARC), Virginia General Assembly · 2024-12-09
    Source excerpt
    “Construction of an individual data center building usually takes about 12 to 18 months, and data center representatives indicated that, at the height of construction, approximately 1,500 workers are on site from various construction-related industries.”
  3. Tax Incentive Evaluation: High-Tech Data Center Sales Tax Exemption (Summary)
    Georgia Department of Audits and Accounts · 2022-12
    Source excerpt
    “50 HTDC employees and an additional 217 jobs would be supported by the center's existence each year. ... Approximately 4,200 construction jobs and 7,300 total jobs would be created during an approximate two-year construction phase.”

Each source was opened and checked against the excerpt shown. Company statements are identified as such. Figures are as published; where sources differ, each is shown.