How long does it take to build a data center?

Text updated Sep 23, 2026 · 4 cited sources, newest dated Jun 2026 · Census figures as of Sep 23, 2026

Short answer

An individual data center building usually takes about 12 to 18 months to construct, according to Virginia’s legislative auditors[1]. Whole campuses take longer because they are approved, powered and built in phases. In the Census record, 6 campuses have dated timelines from their first recorded step to the start of operations, and they took between 3 and 38 months; the fastest, xAI’s first Colossus supercomputer in Memphis, moved into an existing former factory building.

typical construction time for one data center building, per JLARC[1]
12–18 months
workers on site at the peak of construction, per data center representatives cited by JLARC[1]
~1,500
construction phase Georgia assumed for a modeled $800 million data center[2]
2 years

How long one building takes

Construction of an individual data center building usually takes about 12 to 18 months, according to Virginia’s Joint Legislative Audit and Review Commission (JLARC), and data center representatives told JLARC that about 1,500 workers are on site at the peak[1]. Georgia’s 2022 tax incentive evaluation assumed a construction phase of two years for the hypothetical $800 million data center it modeled[2].

Those figures cover putting up a building. They do not include the time it takes to buy land, win zoning and permits, and line up enough electricity.

What happens before construction starts

The project records in the Census show the steps that can come before anything is built: a land purchase or option, a rezoning or special use permit from the county or town, often a tax incentive agreement, and an agreement with the utility for power. Each step can involve public hearings, and some are challenged in court; the hearings calendar and lawsuits tracker list the ones in the record.

Power is a process of its own. Very large loads have to be connected to the transmission system, and federal regulators have opened a proceeding on how loads above 20 megawatts connect[3]. Assuming 50% average utilization, Lawrence Berkeley National Laboratory’s reference case translates to about 148 gigawatts of interconnection capacity needed to serve data centers in 2030[4].

Some counties and towns have also paused new applications while they write rules for data centers. The moratorium tracker lists each pause, with its length and source.

Why a whole campus takes years

Large campuses are rarely built at once. Developers often open a first building or data hall and keep building the rest, so a campus can be operating and under construction at the same time. The schedule targets that tracked projects have announced, listed below, often put the first building years ahead of full build-out.

The timelines in the table below run from the first dated event in each project’s record to the start of operations. That first event differs from project to project (an announcement, a land purchase, a local approval or the start of construction), so the range says more than any single number.

From first step to first operation

These are the campuses in the Census whose records date both their first step and the start of operations. Each span starts at the earliest dated event in the project’s record; every date comes from the project’s timeline, where its source is linked.

ProjectFromToMonths
xAI Colossus
TN · In an existing 785,000-sq-ft former factory building
xAI announces 'world's largest supercomputer' in Memphis and begins installing gas turbines
Jun 5, 2024
Began operations
Sep 2024
3
Stargate Abilene
TX · Eight buildings; later phases still under construction
Construction begins (Crusoe; DCD reports July 2024)
Jun 2024
Crusoe announced the first phase live
Sep 30, 2025
15
Project Rainier (AWS New Carlisle campus)
IN · WSBT reported on Oct. 31, 2025 that Project Rainier had started operations in New Carlisle
Indiana governor announces AWS $11 billion data center campus near New Carlisle
Apr 25, 2024
AWS activated Project Rainier, which runs partly on this campus
Oct 29, 2025
18
Google Fort Wayne data center
IN · State approvals for expansion phases followed in 2026
Allen County Commissioners vote 3-0 to approve annexation of 728 acres
Dec 2023
Began operations
Dec 2025
24
Microsoft Fairwater
WI · Microsoft announced the data center in May 2024
Village of Mount Pleasant approves purchase and sale, development and implementation agreements with Microsoft for about 315 acres in TID 5
Mar 30, 2023
Equipment brought online at the first facility
Apr 2026
37
Microsoft Fairwater Atlanta
GA · City development agreement adopted June 2023
QTS buys about 600 acres in Fayetteville for $153.8 million for a planned 250 MW campus
Aug 2022
Facility began operations
Oct 2025
38

Months are counted between the two dated timeline events; where a source gives only a month, the count uses that month. Expansions of campuses that were already operating are left out, and so is QTS’s Fayetteville campus, whose first building is Microsoft’s Fairwater Atlanta, listed above.

Announced schedule targets

51 tracked projects that are not yet operating have a published schedule target: a completion or first-operation date, a build-out period or, in a few cases, a planned construction start. Most are company or developer statements; the wording below is as each source gives it.

ProjectStatusStated target
Amazon Web Services Louisa County campuses
VA
Under constructionProjected 15-year build-out
Amazon Web Services Richmond County data center campus
NC
Under constructionFirst data center projected to open in 2027; more facilities through 2029
CoreWeave Lancaster data center
PA
Under constructionSummer 2027 for the first Greenfield Road building
CyrusOne CHI-11 Data Center Campus
IL
Under constructionFirst building expected to be running by end of Q1 2028
Fermi America Project Matador
TX
Under constructionTensorWave capacity delivered in phases starting 2H 2027
Goodnight Campus
TX
Under constructionLate 2028 or early 2029
Google Chesterfield County data center campuses
VA
Under constructionConstruction typically 18 to 24 months
Google West Memphis Data Center
AR
Under construction18 to 24 months from October 2025 construction start
Homer City Energy Campus
PA
Under constructionFirst power targeted for early 2028
Hut 8 River Bend Campus
LA
Under constructionQ2 2027 for first data hall, more halls through 2027
IREN Sweetwater data center campus
TX
Under constructionSweetwater 2 energization in late 2027 (IREN, 2025) or 2028 (DCD, 2026)
Meta Beaver Dam Data Center
WI
Under construction2027
Meta Cheyenne Data Center
WY
Under construction2027
Meta El Paso Data Center
TX
Under constructionCapacity starts coming online in 2028; McCloud plant expected in 2027
Meta Hyperion
LA
Under construction2030
Meta Lebanon Data Center
IN
Under constructionFirst phase late 2027 or early 2028
Meta Rosemount Data Center
MN
Under construction2026
Monarch Compute Campus
WV
Under constructionOperations start targeted for January 1, 2027 per air permit application
Nebius Vineland Data Center
NJ
Under constructionOperational by 2027, per Nebius
Port Washington (Lighthouse) Data Center Campus
WI
Under construction2028 (Vantage); We Energies CEO said launch on track for late 2027
PORTS-Pike Technology Campus
OH
Under constructionSix-year buildout through 2032
Project Blue
AZ
Under constructionFirst building operational as soon as 2027
Project Jupiter
NM
Under constructionInitial operations Q4 2026; Phase 1 complete Q3 2028 (county schedule)
QTS Augusta Data Center Campus
GA
Under constructionFirst building expected to be completed in spring 2028
QTS Cedar Rapids Data Center Campus
IA
Under constructionPhase 1 late 2026; Phase 2 late 2027
QTS York County Data Center Campus
SC
Under constructionFirst building operational by 2028
Stargate Lordstown
OH
Under constructionOperational in 2026 (company-stated in September 2025)
Stargate Milam County
TX
Under constructionInitial facilities in service starting 2026 (company); Phase 1 filing lists Oct 15 completion; Epoch AI projects full 1.2 GW by Q4 2028
Vantage Frontier Campus
TX
Under constructionVantage: first building 2H 2026; Epoch AI projects first building Aug 2027 and completion Nov 2028
Amazon Hobart data center
IN
Approved2028
Avemore Data Park
GA
ApprovedFirst phase set to launch in 2028
AWS Fayette County Data Center Campus
OH
ApprovedOperations could start in September 2026 (per OCC filing, 2024)
Blueprint Taylor Data Center
TX
ApprovedEnergized by 2027
Comanche Circle
TX
ApprovedExpected operational 2027 (per Jan 2026 report); 7-year buildout per Texas Tribune
Global AI Data Center
CO
ApprovedFirst data hall expected operational later in 2026
Google Botetourt County Data Center Campus
VA
Approvedcalendar year 2028 (first data center structure)
Joliet Technology Center
IL
ApprovedFirst sub-campus 2028; full build-out through 2032
Project Cannoli
MI
ApprovedLoad starting December 2027; maximum load December 2028
Project Cardinal Data Center Campus
IL
ApprovedFirst building slated for operation in 2029 (as reported in March 2025)
Project Galaxy (AWS Sidney data center)
OH
ApprovedOperations by Dec. 31, 2028; 75 jobs required by Dec. 31, 2030
Project Marvel
AL
ApprovedUp to 10 years to complete, per developers
Project Sail
GA
ApprovedOriginal 2025 filing projected completion by 2036-12-31
Project Steel Data Center Campus
IL
ApprovedDevelopers aiming to begin construction by summer 2027
Project Tembo
WY
Approved2031
Prometheus Hyperscale Evanston Campus
WY
ApprovedConstruction anticipated to begin within six months of final permitting; full 1.25 GW expected to be built in phases over 48 to 60 months (per company)
QTS Richmond campus expansion (RIC4 and RIC5)
VA
ApprovedConstruction start targeted by January 2028 (RIC5 DC4-6)
Ridgeline Facility
WV
ApprovedCommercial operations targeted for 2028 (per POWER Magazine)
Sabey Decatur Technology Park
IN
Approved2031
T5 @ Chicago IV
IL
ApprovedFirst 60MW in Q4 2027 (as announced May 2024)
Wallace Jackson Data Center Campus
GA
ApprovedFull build-out by 2035
Project Camellia
GA
ProposedPower delivered in phases 2028-2032

A target is a plan, not a record of what happened. Open a project for the source and date of each statement.

Where tracked projects stand

  • Proposed: 22
  • Approved: 40
  • Under construction: 43
  • Operating: 13

See every project and its current stage on the project list or the map.

Common questions

How long does it take to build a data center?

About 12 to 18 months for a single building, according to Virginia’s Joint Legislative Audit and Review Commission. Whole campuses take longer: 6 campuses in the Census went from their first recorded step to the start of operations in 3 to 38 months, and many announced targets put full build-out years after the first building.

How many workers does it take to build a data center?

Data center representatives told Virginia’s JLARC that about 1,500 workers are on site at the height of construction of a data center building.

What is the fastest a data center has been built?

Among the projects in the Census, xAI’s first Colossus supercomputer in Memphis began operating 3 months after it was announced, in an existing former factory building rather than a new one.

Why do data center campuses take so long?

Beyond construction, a campus needs land, zoning and permits, tax agreements and a power supply, and large loads have to be connected to the transmission system. Campuses are then built and switched on in phases, so the last building can open years after the first.

Sources

  1. Data Centers in Virginia (Report Summary)
    Joint Legislative Audit and Review Commission (JLARC), Virginia General Assembly · 2024-12-09
    Source excerpt
    “Construction of an individual data center building usually takes about 12 to 18 months, and data center representatives indicated that, at the height of construction, approximately 1,500 workers are on site from various construction-related industries.”
  2. Tax Incentive Evaluation: High-Tech Data Center Sales Tax Exemption (Summary)
    Georgia Department of Audits and Accounts · 2022-12
    Source excerpt
    “50 HTDC employees and an additional 217 jobs would be supported by the center's existence each year. ... Approximately 4,200 construction jobs and 7,300 total jobs would be created during an approximate two-year construction phase.”
  3. Interconnection of Large Loads to the Interstate Transmission System (Docket No. RM26-4-000)
    Federal Energy Regulatory Commission · 2026
    Source excerpt
    “The ANOPR seeks public input on potential reforms related to how large loads — generally defined as electricity demand greater than 20 megawatts (MW) – interconnect to the transmission system.”
  4. United States Data Center Energy Usage Report: 2025 Update
    Lawrence Berkeley National Laboratory · 2026-06
    Source excerpt
    “Assuming a 50% average utilization rate, the Reference Case electricity use projections translate to 148 gigawatts (GW) of interconnection capacity needed to serve data centers in 2030.”

Each source was opened and checked against the excerpt shown. Company statements are identified as such. Figures are as published; where sources differ, each is shown.

Cite this page

Last updated Sep 23, 2026. Figures may change as records are updated — include the date you retrieved them.

APAData Center Census. (2026). How long does it take to build a data center. Retrieved from https://datacentercensus.com/guides/how-long-does-it-take-to-build-a-data-center
MLA“How long does it take to build a data center.” Data Center Census, Sep 23, 2026, https://datacentercensus.com/guides/how-long-does-it-take-to-build-a-data-center.
Linkhttps://datacentercensus.com/guides/how-long-does-it-take-to-build-a-data-center

Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.