How long does it take to build a data center?
Text updated Sep 23, 2026 · 4 cited sources, newest dated Jun 2026 · Census figures as of Sep 23, 2026
Short answer
An individual data center building usually takes about 12 to 18 months to construct, according to Virginia’s legislative auditors[1]. Whole campuses take longer because they are approved, powered and built in phases. In the Census record, 6 campuses have dated timelines from their first recorded step to the start of operations, and they took between 3 and 38 months; the fastest, xAI’s first Colossus supercomputer in Memphis, moved into an existing former factory building.
- typical construction time for one data center building, per JLARC[1]
- 12–18 months
- workers on site at the peak of construction, per data center representatives cited by JLARC[1]
- ~1,500
- construction phase Georgia assumed for a modeled $800 million data center[2]
- 2 years
How long one building takes
Construction of an individual data center building usually takes about 12 to 18 months, according to Virginia’s Joint Legislative Audit and Review Commission (JLARC), and data center representatives told JLARC that about 1,500 workers are on site at the peak[1]. Georgia’s 2022 tax incentive evaluation assumed a construction phase of two years for the hypothetical $800 million data center it modeled[2].
Those figures cover putting up a building. They do not include the time it takes to buy land, win zoning and permits, and line up enough electricity.
What happens before construction starts
The project records in the Census show the steps that can come before anything is built: a land purchase or option, a rezoning or special use permit from the county or town, often a tax incentive agreement, and an agreement with the utility for power. Each step can involve public hearings, and some are challenged in court; the hearings calendar and lawsuits tracker list the ones in the record.
Power is a process of its own. Very large loads have to be connected to the transmission system, and federal regulators have opened a proceeding on how loads above 20 megawatts connect[3]. Assuming 50% average utilization, Lawrence Berkeley National Laboratory’s reference case translates to about 148 gigawatts of interconnection capacity needed to serve data centers in 2030[4].
Some counties and towns have also paused new applications while they write rules for data centers. The moratorium tracker lists each pause, with its length and source.
Why a whole campus takes years
Large campuses are rarely built at once. Developers often open a first building or data hall and keep building the rest, so a campus can be operating and under construction at the same time. The schedule targets that tracked projects have announced, listed below, often put the first building years ahead of full build-out.
The timelines in the table below run from the first dated event in each project’s record to the start of operations. That first event differs from project to project (an announcement, a land purchase, a local approval or the start of construction), so the range says more than any single number.
From first step to first operation
These are the campuses in the Census whose records date both their first step and the start of operations. Each span starts at the earliest dated event in the project’s record; every date comes from the project’s timeline, where its source is linked.
| Project | From | To | Months |
|---|---|---|---|
| xAI Colossus TN · In an existing 785,000-sq-ft former factory building | xAI announces 'world's largest supercomputer' in Memphis and begins installing gas turbines Jun 5, 2024 | Began operations Sep 2024 | 3 |
| Stargate Abilene TX · Eight buildings; later phases still under construction | Construction begins (Crusoe; DCD reports July 2024) Jun 2024 | Crusoe announced the first phase live Sep 30, 2025 | 15 |
| Project Rainier (AWS New Carlisle campus) IN · WSBT reported on Oct. 31, 2025 that Project Rainier had started operations in New Carlisle | Indiana governor announces AWS $11 billion data center campus near New Carlisle Apr 25, 2024 | AWS activated Project Rainier, which runs partly on this campus Oct 29, 2025 | 18 |
| Google Fort Wayne data center IN · State approvals for expansion phases followed in 2026 | Allen County Commissioners vote 3-0 to approve annexation of 728 acres Dec 2023 | Began operations Dec 2025 | 24 |
| Microsoft Fairwater WI · Microsoft announced the data center in May 2024 | Village of Mount Pleasant approves purchase and sale, development and implementation agreements with Microsoft for about 315 acres in TID 5 Mar 30, 2023 | Equipment brought online at the first facility Apr 2026 | 37 |
| Microsoft Fairwater Atlanta GA · City development agreement adopted June 2023 | QTS buys about 600 acres in Fayetteville for $153.8 million for a planned 250 MW campus Aug 2022 | Facility began operations Oct 2025 | 38 |
Months are counted between the two dated timeline events; where a source gives only a month, the count uses that month. Expansions of campuses that were already operating are left out, and so is QTS’s Fayetteville campus, whose first building is Microsoft’s Fairwater Atlanta, listed above.
Announced schedule targets
51 tracked projects that are not yet operating have a published schedule target: a completion or first-operation date, a build-out period or, in a few cases, a planned construction start. Most are company or developer statements; the wording below is as each source gives it.
| Project | Status | Stated target |
|---|---|---|
| Amazon Web Services Louisa County campuses VA | Under construction | Projected 15-year build-out |
| Amazon Web Services Richmond County data center campus NC | Under construction | First data center projected to open in 2027; more facilities through 2029 |
| CoreWeave Lancaster data center PA | Under construction | Summer 2027 for the first Greenfield Road building |
| CyrusOne CHI-11 Data Center Campus IL | Under construction | First building expected to be running by end of Q1 2028 |
| Fermi America Project Matador TX | Under construction | TensorWave capacity delivered in phases starting 2H 2027 |
| Goodnight Campus TX | Under construction | Late 2028 or early 2029 |
| Google Chesterfield County data center campuses VA | Under construction | Construction typically 18 to 24 months |
| Google West Memphis Data Center AR | Under construction | 18 to 24 months from October 2025 construction start |
| Homer City Energy Campus PA | Under construction | First power targeted for early 2028 |
| Hut 8 River Bend Campus LA | Under construction | Q2 2027 for first data hall, more halls through 2027 |
| IREN Sweetwater data center campus TX | Under construction | Sweetwater 2 energization in late 2027 (IREN, 2025) or 2028 (DCD, 2026) |
| Meta Beaver Dam Data Center WI | Under construction | 2027 |
| Meta Cheyenne Data Center WY | Under construction | 2027 |
| Meta El Paso Data Center TX | Under construction | Capacity starts coming online in 2028; McCloud plant expected in 2027 |
| Meta Hyperion LA | Under construction | 2030 |
| Meta Lebanon Data Center IN | Under construction | First phase late 2027 or early 2028 |
| Meta Rosemount Data Center MN | Under construction | 2026 |
| Monarch Compute Campus WV | Under construction | Operations start targeted for January 1, 2027 per air permit application |
| Nebius Vineland Data Center NJ | Under construction | Operational by 2027, per Nebius |
| Port Washington (Lighthouse) Data Center Campus WI | Under construction | 2028 (Vantage); We Energies CEO said launch on track for late 2027 |
| PORTS-Pike Technology Campus OH | Under construction | Six-year buildout through 2032 |
| Project Blue AZ | Under construction | First building operational as soon as 2027 |
| Project Jupiter NM | Under construction | Initial operations Q4 2026; Phase 1 complete Q3 2028 (county schedule) |
| QTS Augusta Data Center Campus GA | Under construction | First building expected to be completed in spring 2028 |
| QTS Cedar Rapids Data Center Campus IA | Under construction | Phase 1 late 2026; Phase 2 late 2027 |
| QTS York County Data Center Campus SC | Under construction | First building operational by 2028 |
| Stargate Lordstown OH | Under construction | Operational in 2026 (company-stated in September 2025) |
| Stargate Milam County TX | Under construction | Initial facilities in service starting 2026 (company); Phase 1 filing lists Oct 15 completion; Epoch AI projects full 1.2 GW by Q4 2028 |
| Vantage Frontier Campus TX | Under construction | Vantage: first building 2H 2026; Epoch AI projects first building Aug 2027 and completion Nov 2028 |
| Amazon Hobart data center IN | Approved | 2028 |
| Avemore Data Park GA | Approved | First phase set to launch in 2028 |
| AWS Fayette County Data Center Campus OH | Approved | Operations could start in September 2026 (per OCC filing, 2024) |
| Blueprint Taylor Data Center TX | Approved | Energized by 2027 |
| Comanche Circle TX | Approved | Expected operational 2027 (per Jan 2026 report); 7-year buildout per Texas Tribune |
| Global AI Data Center CO | Approved | First data hall expected operational later in 2026 |
| Google Botetourt County Data Center Campus VA | Approved | calendar year 2028 (first data center structure) |
| Joliet Technology Center IL | Approved | First sub-campus 2028; full build-out through 2032 |
| Project Cannoli MI | Approved | Load starting December 2027; maximum load December 2028 |
| Project Cardinal Data Center Campus IL | Approved | First building slated for operation in 2029 (as reported in March 2025) |
| Project Galaxy (AWS Sidney data center) OH | Approved | Operations by Dec. 31, 2028; 75 jobs required by Dec. 31, 2030 |
| Project Marvel AL | Approved | Up to 10 years to complete, per developers |
| Project Sail GA | Approved | Original 2025 filing projected completion by 2036-12-31 |
| Project Steel Data Center Campus IL | Approved | Developers aiming to begin construction by summer 2027 |
| Project Tembo WY | Approved | 2031 |
| Prometheus Hyperscale Evanston Campus WY | Approved | Construction anticipated to begin within six months of final permitting; full 1.25 GW expected to be built in phases over 48 to 60 months (per company) |
| QTS Richmond campus expansion (RIC4 and RIC5) VA | Approved | Construction start targeted by January 2028 (RIC5 DC4-6) |
| Ridgeline Facility WV | Approved | Commercial operations targeted for 2028 (per POWER Magazine) |
| Sabey Decatur Technology Park IN | Approved | 2031 |
| T5 @ Chicago IV IL | Approved | First 60MW in Q4 2027 (as announced May 2024) |
| Wallace Jackson Data Center Campus GA | Approved | Full build-out by 2035 |
| Project Camellia GA | Proposed | Power delivered in phases 2028-2032 |
A target is a plan, not a record of what happened. Open a project for the source and date of each statement.
Where tracked projects stand
- Proposed: 22
- Approved: 40
- Under construction: 43
- Operating: 13
See every project and its current stage on the project list or the map.
Common questions
How long does it take to build a data center?
About 12 to 18 months for a single building, according to Virginia’s Joint Legislative Audit and Review Commission. Whole campuses take longer: 6 campuses in the Census went from their first recorded step to the start of operations in 3 to 38 months, and many announced targets put full build-out years after the first building.
How many workers does it take to build a data center?
Data center representatives told Virginia’s JLARC that about 1,500 workers are on site at the height of construction of a data center building.
What is the fastest a data center has been built?
Among the projects in the Census, xAI’s first Colossus supercomputer in Memphis began operating 3 months after it was announced, in an existing former factory building rather than a new one.
Why do data center campuses take so long?
Beyond construction, a campus needs land, zoning and permits, tax agreements and a power supply, and large loads have to be connected to the transmission system. Campuses are then built and switched on in phases, so the last building can open years after the first.
Sources
- Data Centers in Virginia (Report Summary)Joint Legislative Audit and Review Commission (JLARC), Virginia General Assembly · 2024-12-09
Source excerpt
“Construction of an individual data center building usually takes about 12 to 18 months, and data center representatives indicated that, at the height of construction, approximately 1,500 workers are on site from various construction-related industries.”
- Tax Incentive Evaluation: High-Tech Data Center Sales Tax Exemption (Summary)Georgia Department of Audits and Accounts · 2022-12
Source excerpt
“50 HTDC employees and an additional 217 jobs would be supported by the center's existence each year. ... Approximately 4,200 construction jobs and 7,300 total jobs would be created during an approximate two-year construction phase.”
- Interconnection of Large Loads to the Interstate Transmission System (Docket No. RM26-4-000)Federal Energy Regulatory Commission · 2026
Source excerpt
“The ANOPR seeks public input on potential reforms related to how large loads — generally defined as electricity demand greater than 20 megawatts (MW) – interconnect to the transmission system.”
- United States Data Center Energy Usage Report: 2025 UpdateLawrence Berkeley National Laboratory · 2026-06
Source excerpt
“Assuming a 50% average utilization rate, the Reference Case electricity use projections translate to 148 gigawatts (GW) of interconnection capacity needed to serve data centers in 2030.”
Each source was opened and checked against the excerpt shown. Company statements are identified as such. Figures are as published; where sources differ, each is shown.
Cite this page
Last updated Sep 23, 2026. Figures may change as records are updated — include the date you retrieved them.
| APA | Data Center Census. (2026). How long does it take to build a data center. Retrieved from https://datacentercensus.com/guides/how-long-does-it-take-to-build-a-data-center |
|---|---|
| MLA | “How long does it take to build a data center.” Data Center Census, Sep 23, 2026, https://datacentercensus.com/guides/how-long-does-it-take-to-build-a-data-center. |
| Link | https://datacentercensus.com/guides/how-long-does-it-take-to-build-a-data-center |
Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.