Project Steel Data Center Campus

Yorkville, Kendall County, IL

ApprovedApproved by Yorkville City Council in March 2026; residents' lawsuit seeking to void the rezoning filed May 2026
  1. Rumored
  2. Proposed
  3. Approved
  4. Under construction
  5. Operating

Project Steel is a data center campus proposed by Prologis, L.P. on approximately 540 acres in Yorkville, Illinois, revised to 16 two-story buildings totaling about 6.8 million square feet. The Yorkville City Council approved the project in March 2026 with one dissenting vote, and a residents' group filed a lawsuit in Kendall County Court asking that the rezoning be declared void.

Key facts

Size & schedule

Site size540 acres [1]
approximately 540 acres across sixteen parcels
Source excerpt
“preliminary PUD Plan approval for approximately 540 acres across sixteen (16) parcels”
Floor area6.8 million sq ft [2]
about 6.8 million square feet
Source excerpt
“The remaining warehouses will be slightly larger than the original plan, meaning the total square footage remains about 6.8 million square feet.”
Buildings16 [2]
reduced from 18 in the original application
Source excerpt
“To make room, the original number of 18 warehouses is being reduced to 16, two-story warehouses.”
Target completionDevelopers aiming to begin construction by summer 2027 [2]
Source excerpt
“The developers are aiming to begin construction by the summer of 2027.”

Water

Water use25,000–42,400 [3]
range stated by city official Olson
Source excerpt
“Addressing residents concerns about water consumption, Olson said Project Steel is an air-cooled system that will only use about 25,000 – 42,400 gallons per day.”
Coolingair-cooled [3]
Source excerpt
“Addressing residents concerns about water consumption, Olson said Project Steel is an air-cooled system that will only use about 25,000 – 42,400 gallons per day.”

Money & incentives

Payments / community benefits$30 million of the payment pledged to Yorkville School District 115 [3]
Source excerpt
“Within the check, $30 million is being pledged straight to Yorkville School District 115.”

Local decisions & site

Deciding voteYorkville City Council approved Project Steel; only Alderman Rusty Corneils voted no [3]
Source excerpt
“The Project Steel project received approval votes from every council member except Alderman Rusty Corneils.”
ZoningRezone from R-1 Single-Family Suburban Residence District to M-2 General Manufacturing District [1]
Source excerpt
“The proposal aims to rezone the parcels from R-1 Single-Family Suburban Residence District to M-2 General Manufacturing District to facilitate the development of a high-tech data center campus”
Nearest homes or schools1,670 feet from houses on Corneils Road [3]
Source excerpt
“Project Steel is 1,670 feet from houses on Corneils Road.”

Figures are as stated by the cited source. Where sources disagree, each figure is shown.

Lawsuits

Preserve Our Yorkville and Community lawsuit over Project Steel rezoningpending [4]
The lawsuit argues the city failed to properly notify residents by mail and that the rezoning is inconsistent with the city's comprehensive plan, and asks the court to declare the rezoning void.
· filed May 2026
Source excerpt
“The lawsuit argues that Yorkville City Hall failed to properly notify residents by mail and that the rezoning is inconsistent with the city's comprehensive plan. The suit asks the court to declare the rezoning void.”

Timeline

  1. Plans for a 540-acre campus with 24 two-story data center buildings totaling more than 9 million square feet are reported [5]

  2. Yorkville City Council approves Project Steel, with only Alderman Rusty Corneils voting no [3]

  3. The group suing over Project Cardinal files another lawsuit targeting the Project Steel campus [4]

Issues raised

  • Residents asked the council for a moratorium on data center approvals, citing cumulative sound, light and environmental impacts [3]
  • After feedback from ComEd, the developer increased the number of new electrical substations from three to four [2]
  • Construction is planned in three phases over 20 years [2]
  • Plaintiffs in the lawsuit include the Teska Family Farm and Yorkville residents [6]

Sources

  1. Project Steel Data Center Campus (Annex Agreement, Rezone, Preliminary PUD & PUD)
    United City of Yorkville · 2026 · government
  2. Yorkville could approve 2 more data center projects, including 540-acre Project Steel
    Shaw Local · Mar 23, 2026 · news
  3. 'Nobody wants to live in data center row' - Residents speak out after Yorkville approves 540-acre data center
    Shaw Local · Mar 26, 2026 · news
  4. Group files second lawsuit over Yorkville data centers
    WSPY News · May 27, 2026 · news
  5. Two data center campuses totaling 38 buildings proposed in Yorkville, Illinois
    DatacenterDynamics · Mar 24, 2025 · news
  6. Yorkville farm, residents sue to stop second massive data center project
    CBS News Chicago · May 29, 2026 · news

Cite this page

Last updated Sep 22, 2026. Figures may change as records are updated — include the date you retrieved them.

APAData Center Census. (2026). Project Steel Data Center Campus. Retrieved from https://datacentercensus.com/dc/project-steel-yorkville-il
MLA“Project Steel Data Center Campus.” Data Center Census, Sep 22, 2026, https://datacentercensus.com/dc/project-steel-yorkville-il.
Linkhttps://datacentercensus.com/dc/project-steel-yorkville-il