Data Center Census Near me

Monthly report

U.S. data centers in September 2026

In September 2026, the Data Center Census recorded 91 dated changes at 61 tracked projects across 30 states.

Final report for September 2026, published October 1, 2026. Last data change: . Page rebuilt .

← August 2026 October 2026 → All reports · Monthly RSS

Dated changes
91
Projects with a first milestone
2
Moratorium actions
24
Court cases filed
3

The month in one paragraph

In September 2026, the Data Center Census recorded 91 dated changes at 61 tracked projects across 30 states. 2 projects have their earliest dated milestone in the month. Events recorded include 22 approvals, 4 denials, 4 cancellations, 1 construction or operations start. 24 moratorium actions were recorded, 22 of them adopted, extended or announced. 3 court cases were filed. 6 hearings or votes on the record were held. That is 25 more than the 66 changes recorded in August 2026.

Counts describe what was recorded in this tracker, from published filings, notices and reports. They are not a measure of everything that happened in the industry, and a month’s counts can rise later if sources dated in it are added.

Compared with August 2026

MeasureSeptember 2026August 2026Change
Dated changes recorded9166+25
Projects with a change6154+7
States30300
Projects with first milestone20+2
Approval events225+17
Denial events41+3
Cancellation events45−1
Construction or operations starts10+1
Moratorium actions2414+10
Court cases filed31+2
Hearings and votes held60+6
Hearings and votes upcoming000

Projects with their first milestone in September 2026

ProjectFirst milestoneStatus now
Project Tamarack
West Columbia, Mason County, WV
Sep 3, 2026Approved
Project Thunderbird
Enid, Garfield County, OK
Sep 8, 2026Proposed

A project appears here when its earliest dated timeline entry is in this month. It does not mean it was announced publicly that month.

Every dated change

DateWhat changedProject
Sep 25, 2026A city spokeswoman said the proposal had not yet been scheduled before the Planning Commission or City Council. 102.7 Coyote Country (Beasley Media)Switch Core 2.0 Phase 1 Campus
North Las Vegas, Clark County, NV · Proposed
Sep 24, 2026Oracle sends developer Blue Owl Capital a force-majeure notice after a natural-gas pipeline meant to supply the project's power is delayed to February 2027 following New Mexico State Land Office permit denials; both companies say it does not change their commitment to the project SiliconANGLEProject Jupiter
Santa Teresa, Doña Ana County, NM · Under construction
Sep 23, 2026KTNV reported Switch's letter of intent for a 175.8-acre campus, based on documents filed with the city in August. KTNV Channel 13 Las VegasSwitch Core 2.0 Phase 1 Campus
North Las Vegas, Clark County, NV · Proposed
Sep 22, 2026Fermi and TensorWave amend their 222 MW lease to move the closing date from Sept. 30 to Oct. 31, 2026, while a lease guaranty is negotiated Fermi America (ACCESS Newswire)Fermi America Project Matador
Amarillo, Carson County, TX · Under construction
Sep 22, 2026Mayor Kenneth Gulley, who backed Project Marvel, loses the mayoral runoff to former council member Louise Alexander, 54.53% to 45.47%, after an election season the Birmingham Free Press describes as dominated by the project Birmingham Free PressProject Marvel
Bessemer, Jefferson County, AL · Approved
Sep 22, 2026St. Joseph County Council advances, on a 6-3 vote, a resolution that would bar new hyperscale data centers from the county ABC57Project Rainier (AWS New Carlisle campus)
New Carlisle, St. Joseph County, IN · Operating
Sep 21, 2026Judge grants the developers' emergency motion to stay the zoning hearing on the residents' group appeal of the second Greenfield Road building LancasterOnlineCoreWeave Lancaster data center
Lancaster, Lancaster County, PA · Under construction
Sep 21, 2026At a Hermantown City Council meeting, Google says its changes include monitoring wells and a 37 percent reduction in wetland impacts, and that it is creating a decommissioning agreement in case the site becomes obsolete Northern News NowGoogle Hermantown Data Center
Hermantown, St. Louis County, MN · Proposed
Sep 21, 2026Google tells the City Council that a labor memorandum of understanding for the project has been reached between Mortenson, its developer, and the Duluth Building Trades FOX 21 (KQDS)Google Hermantown Data Center
Hermantown, St. Louis County, MN · Proposed
Sep 21, 2026Salem City Council adopts a 120-day moratorium on new data center projects, with the option to extend it by six months Salem ReporterOakline at Mill Creek
Salem, OR · Proposed
Sep 21, 2026One Hundred Miles and five residents sue the Effingham IDA and Octans GA alleging open-government law violations WTOCProject Camellia
Rincon, Effingham County, GA · Proposed
Sep 21, 2026O’Leary and Fox News ask the U.S. District Court in Utah to dismiss the defamation suit Utah News DispatchStratos Project
Box Elder County, UT · Proposed
Sep 18, 2026Cole County Circuit Judge Cotton Walker denies most of the motion to dismiss and finds the group has standing KBIA / Columbia Missourian
Denial
AWS Project Green
New Florence, Montgomery County, MO · Approved
Sep 18, 2026Supreme Court of Ohio rules the initiative cannot appear on the Nov. 3 ballot Court News OhioAWS Wilmington data center
Wilmington, Clinton County, OH · Approved
Sep 18, 2026Three Siemens gas turbines arrive on site ABC 7 AmarilloFermi America Project Matador
Amarillo, Carson County, TX · Under construction
Sep 18, 2026Public Utilities Commission of Nevada approves the two gas plants, subject to environmental permits and Storey County approvals Nevada Current
Approval
Fleet Data Centers TRIC campuses (South Valley and Peru Ridge)
Storey County, NV · Proposed
Sep 17, 2026Texas Attorney General Ken Paxton launches an investigation into the land deal Office of the Attorney General of TexasBlueprint Taylor Data Center
Taylor, Williamson County, TX · Approved
Sep 17, 2026Legislators on the joint energy committee question Entergy Arkansas about the data center's effect on ratepayers and table remaining questions to next month's meeting Action News 5Google West Memphis Data Center
West Memphis, Crittenden County, AR · Under construction
Sep 17, 2026NM Supreme Court denies petitions and lifts stay KVIA
Denial
Project Jupiter
Santa Teresa, Doña Ana County, NM · Under construction
Sep 16, 2026Planning Commission votes 4-2 to recommend approval of the special use permit Fredericksburg Free Press
Approval
Crossroads Technology Campus
Spotsylvania County, VA · Proposed
Sep 16, 2026City reports plaintiffs in both lawsuits involving the city have filed dismissals, pending final court direction City of FarmingtonFarmington Technology Park
Farmington, Dakota County, MN · Approved
Sep 16, 2026Entergy Arkansas files a notice of dismissal of its lawsuit against the two newspapers and a central Arkansas resident Arkansas AdvocateGoogle West Memphis Data Center
West Memphis, Crittenden County, AR · Under construction
Sep 16, 2026Massena Town Board votes 3-2 against a proposed six-month moratorium on data center development WWNY 7 NewsNorth Country Colocation Services Massena Expansion
Massena, St. Lawrence County, NY · Proposed
Sep 16, 2026Coastal Regional Commission's full DRI report released; county site plan consideration postponed at developer request WTOCProject Camellia
Rincon, Effingham County, GA · Proposed
Sep 16, 2026Metropolitan Development Commission approves more than $240 million in tax breaks WFYI
Approval
Sabey Decatur Technology Park
Indianapolis, Marion County, IN · Approved
Sep 15, 2026The Franklin County Commission votes to approve the Diamond 66 and Diamond Farms rezoning requests (Commission Orders 2026-255 and 2026-256), rezoning the site from its prior districts to industrial (A district) use, and separately adopts new countywide data-center regulations First Alert 4 (KMOV)
Approval
Gateway Digital Campus
Villa Ridge, Franklin County, MO · Approved
Sep 15, 2026The Imperial Irrigation District board approves a Large Load Tariff, new pricing rules making data centers the first to have their power cut during surges in demand KPBS
Approval
Imperial Data Center
Imperial, Imperial County, CA · Paused
Sep 15, 2026The Franklin County Commission votes to approve BLE Landholdings' rezoning request (Commission Order 2026-257), reversing the Planning and Zoning Commission's April recommendation against it, and separately adopts new countywide data-center regulations First Alert 4 (KMOV)
Approval
Meramec Valley Technology Park
Pacific, Franklin County, MO · Approved
Sep 15, 2026A large crowd, most of it opposed to Project Thunderbird, fills the Enid City Commission meeting Enid News & EagleProject Thunderbird
Enid, Garfield County, OK · Proposed
Sep 15, 2026The Augusta Commission approves rules governing new data centers, 6-5, ending the city’s almost three-month moratorium The Augusta Press
Approval
QTS Augusta Data Center Campus
Augusta, Augusta-Richmond County, GA · Under construction
Sep 15, 2026Board of Supervisors votes 7-1-1 to have staff draft a resolution pausing new data center applications for 12 months; final vote expected in October WJLASpring Valley Technology Park
Loudoun County, VA · Proposed
Sep 14, 2026Statesville City Council unanimously approves a 180-day moratorium on new data centers in the city; WBTV reports it will not affect previously approved data centers WBTV
Approval
Compass Statesville
Statesville, Iredell County, NC · Approved
Sep 14, 2026Vance County Board of Commissioners votes 5-2 to adopt a 60-day moratorium on data center development after two public hearings WIZSNatelli data center, U.S. 158
Vance County, NC · Proposed
Sep 14, 2026ATC refiles its application for the grid upgrades serving the campus, dropping a Trenton-Saukville line segment and restarting the PSC's six-month review Wisconsin WatchPort Washington (Lighthouse) Data Center Campus
Port Washington, Ozaukee County, WI · Under construction
Sep 14, 2026County Council unanimously adopts Digital Infrastructure Overlay District, partially repealing the moratorium Live 5 News (WCSC)Project Boulder
Walterboro, Colleton County, SC · Proposed
Sep 14, 2026Commissioners approve rezoning again 3-2 under restarted process WFAE
Approval
Project Delta
Walnut Cove, Stokes County, NC · Approved
Sep 14, 2026County Executive rejects the Frederick Digital Campus DRRA and extends the data center pause through July 1, 2027 Frederick County GovernmentQuantum Frederick
Adamstown, Frederick County, MD · Under construction
Sep 14, 2026County records showed Switch had bought about 176 more acres at Apex for roughly $196 million, with no announced plans for that land. FOX5 Las Vegas (KVVU)Switch Core 2.0 Phase 1 Campus
North Las Vegas, Clark County, NV · Proposed
Sep 11, 2026County defends its approval in circuit court; Judge Adam Giganti sets an Oct. 9 hearing on the county's motion to dismiss the residents' suit Illinois Times
Approval
CyrusOne Sangamon County Data Center
Waverly, Sangamon County, IL · Approved
Sep 11, 2026The borough received preliminary design plans and posted a link to them. Big Beaver BoroughSwitch Big Beaver data center campus
Big Beaver, Beaver County, PA · Proposed
Sep 10, 2026IDEM approves a permit to fill 2.13 acres of forested, isolated wetlands for three new buildings in the third expansion phase 21Alive (WPTA)
Approval
Google Fort Wayne data center
Fort Wayne, Allen County, IN · Operating
Sep 10, 2026Aligned announces groundbreaking of the 2 GW Project Phoenix campus GlobeNewswire (Aligned Data Centers)
Construction or operations start
Project Phoenix
Shippingport, Beaver County, PA · Under construction
Sep 9, 2026Coalition announces it is withdrawing its lawsuit, citing litigation costs Blandin on Broadband (citing Sun This Week)
Cancellation
Farmington Technology Park
Farmington, Dakota County, MN · Approved
Sep 9, 2026Board of County Commissioners votes 5-0 to approve Use by Special Review permit after eight-hour hearing Colorado Public Radio
Approval
Global AI Data Center
Windsor, Weld County, CO · Approved
Sep 9, 2026Superior Court sets aside lot merger approval and orders CEQA environmental review KPBS
Approval
Imperial Data Center
Imperial, Imperial County, CA · Paused
Sep 9, 2026Tom Natelli of Natelli Holdings writes to county commissioners and the planning board that the company has decided to file a plan for development of its site along U.S. 158 WIZSNatelli data center, U.S. 158
Vance County, NC · Proposed
Sep 9, 2026Google holds a community open house in Cheyenne Gillette News RecordProject Tembo
Cheyenne, Laramie County, WY · Approved
Sep 9, 2026Augusta releases a final draft data center ordinance that would not apply to the QTS campus WRDW/WAGT News 12QTS Augusta Data Center Campus
Augusta, Augusta-Richmond County, GA · Under construction
Sep 8, 2026Hood County Commissioners Court postpones its discussion of the proposed data center projects, including Comanche Circle, to October 13 so a public hearing can be properly advertised NBC DFWComanche Circle
Tolar, Hood County, TX · Approved
Sep 8, 2026City Council unanimously approves up to $20,000 for a consultant to guide discussions with tribal governments on the proposal Northern News Now
Approval
Google Hermantown Data Center
Hermantown, St. Louis County, MN · Proposed
Sep 8, 2026IREN says the 2 GW Sweetwater Hub was conditionally included in ERCOT's Batch Zero process as base load, with 300 MW under construction at Sweetwater 1 for Q4 2027 delivery IREN (GlobeNewswire)IREN Sweetwater data center campus
Sweetwater, Fisher County, TX · Under construction
Sep 8, 2026Will County Judge Victoria Breslan hears arguments on the city's and developer's motions to dismiss the residents' lawsuit and says she will rule in October Shaw Local (The Herald-News)Joliet Technology Center
Joliet, Will County, IL · Approved
Sep 8, 2026On the mayor's tie-breaking vote, Burgin City Council approves on first reading an ordinance for the city to rejoin the joint Mercer County, Harrodsburg and Burgin Planning and Zoning Commission WKYT
Approval
Project Bluegrass
Burgin, Mercer County, KY · Proposed
Sep 8, 2026A planned council vote on directing the city attorney to draft an ordinance annexing the data center site does not happen after council member Melinda Wofford walks out and the council loses its quorum Kentucky LanternProject Bluegrass
Burgin, Mercer County, KY · Proposed
Sep 8, 2026Mercer County Fiscal Court gives a first reading of the commission's data center regulations Kentucky LanternProject Bluegrass
Burgin, Mercer County, KY · Proposed
Sep 8, 2026Plainsmen Holdings announces Project Thunderbird Freedom 96.9Project Thunderbird
Enid, Garfield County, OK · Proposed
Sep 8, 2026Commissioners split 3-3 on a resolution approving an amended economic development agreement, so the amendments are not adopted The Daily Herald (Roanoke Rapids)
Approval
Quiet Data Centers, Trestle Road
Enfield, Halifax County, NC · Proposed
Sep 4, 2026Appalachian Power files application with the State Corporation Commission for grid upgrades to serve the campus Cardinal NewsGoogle Botetourt County Data Center Campus
Botetourt County, VA · Approved
Sep 4, 2026Developer reports more than 1,800 tradespeople on site Lehigh DailyHomer City Energy Campus
Homer City, Indiana County, PA · Under construction
Sep 4, 2026Revised land development plans, stormwater calculations and an acoustics study were submitted to the borough. Big Beaver BoroughSwitch Big Beaver data center campus
Big Beaver, Beaver County, PA · Proposed
Sep 3, 2026Gov. Morrisey announces state 'high-impact' certification for the project Charleston Gazette-MailMonarch Compute Campus
Point Pleasant, Mason County, WV · Under construction
Sep 3, 2026Attorney General Raúl Torrez files responses backing emergency petitions New Mexico Department of JusticeProject Jupiter
Santa Teresa, Doña Ana County, NM · Under construction
Sep 3, 2026Gov. Morrisey announces at the West Virginia Chamber of Commerce business summit that Starwood Digital Ventures received high-impact data center certification for Project Tamarack West Virginia Public BroadcastingProject Tamarack
West Columbia, Mason County, WV · Approved
Sep 3, 2026Project Tamarack says it is forming a Community Advisory Group of Mason County residents and leaders WDTVProject Tamarack
West Columbia, Mason County, WV · Approved
Sep 3, 2026Utah News Dispatch reports plans paused while county drafts ordinance Utah News DispatchTooele Valley data center (Burmester Road / I-80)
Tooele County, UT · Paused
Sep 3, 2026Satellite imagery shows Buildings 1-5 shells complete and roofed Epoch AIVantage Frontier Campus
Albany, Shackelford County, TX · Under construction
Sep 3, 2026Plaintiffs' attorney says the parties are awaiting a ruling from the judge on a joint motion the county and developer filed The Griffin Daily NewsWallace Jackson Data Center Campus
Griffin, Spalding County, GA · Approved
Sep 3, 2026County community development director says the county has received no applications, plans or other submittals for a land disturbance permit at its approved data center sites The Griffin Daily News
Approval
Wallace Jackson Data Center Campus
Griffin, Spalding County, GA · Approved
Sep 2, 2026Three Effingham County residents sue in Effingham County Superior Court to throw out Ordinance 2026-352, the zoning change that paved the way for the project; the Effingham Herald reports the suit does not ask the court to stop Project Camellia Effingham HeraldProject Camellia
Rincon, Effingham County, GA · Proposed
Sep 2, 2026Chamber panel addresses resident concerns over housing, power, water and noise KACUStargate Abilene
Abilene, Taylor County, TX · Operating
Sep 2, 2026Commission extends interim control through 2026-12-24 to finalize zoning rules KWCHWest Sedgwick County data center land acquisitions
Sedgwick County, KS · Rumored
Sep 1, 2026Weld County Planning Commission votes 7-0 to recommend approval Weld County
Approval
Global AI Data Center
Windsor, Weld County, CO · Approved
Sep 1, 2026Residents sue the Perry Township trustees, Panattoni and other local bodies over the noise ordinance and tax-exemption resolution; the suit does not seek to halt development Ideastream Public MediaPerry Township Data Center
Canton, Stark County, OH · Under construction
Sep 1, 2026County receives first draft of the community benefits agreement / DRRA Frederick County GovernmentQuantum Frederick
Adamstown, Frederick County, MD · Under construction
Sep 1, 2026Village issues first building permit, for an 800,000-square-foot facility Lake and McHenry County ScannerT5 @ Chicago IV
Grayslake, Lake County, IL · Approved
Sep 2026Trenton's city attorney notifies Butler County that the city is withdrawing the annexation petition, effective immediately WVXU
Cancellation
Amazon Web Services data center campus, Madison and St. Clair townships
Butler County, OH · Proposed
Sep 2026The withdrawal comes one day before a scheduled Butler County Board of Commissioners public hearing on the annexation WCPO
Cancellation
Amazon Web Services data center campus, Madison and St. Clair townships
Butler County, OH · Proposed
Sep 2026Butler County commissioners accept the withdrawal WCPO
Cancellation
Amazon Web Services data center campus, Madison and St. Clair townships
Butler County, OH · Proposed
Sep 2026Council committee unanimously recommends legislation to reinstate detailed site plan review for data centers The DiamondbackBrightseat Tech Park
Landover, Prince George's County, MD · Approved
Sep 2026At a Google and Crusoe community open house in Claude, Crusoe says the campus will include six buildings; KFDA reports Google is expected to receive the first buildings in early 2027, with construction wrapping up by the end of 2027 KFDA NewsChannel 10Goodnight Campus
Claude, Armstrong County, TX · Under construction
Sep 2026Google seeks a third air permit modification, for 228 more emergency diesel generators on top of 174 existing WBOIGoogle Fort Wayne data center
Fort Wayne, Allen County, IN · Operating
Sep 2026Released documents show Entergy Arkansas and Google plan to cover two-thirds of the project's cost through a monthly ratepayer increase of nearly $6 over 20 years Action News 5Google West Memphis Data Center
West Memphis, Crittenden County, AR · Under construction
Sep 2026A federal judge denies Entergy Arkansas a temporary restraining order that would have barred the Arkansas Times and the Arkansas Democrat-Gazette from revealing details of its agreements with Altitude Capital LLC, the Google subsidiary setting up the data center Arkansas Advocate
Denial
Google West Memphis Data Center
West Memphis, Crittenden County, AR · Under construction
Sep 2026Planning commissioner confirms DB STU LLC purchased the mega site properties with the intent of developing a data center WCPOMt. Orab Mega Site data center
Mount Orab, Brown County, OH · Rumored
Sep 2026Planning Commission hears resident opposition to a High Tech Overlay district; no vote taken FOX19Mt. Orab Mega Site data center
Mount Orab, Brown County, OH · Rumored
Sep 2026Two neighboring residents file a land use appeal in Lycoming County Court of Common Pleas against the deemed approval of the conditional use application Williamsport Sun-Gazette
Approval
Muncy Data Center
Muncy Township, Lycoming County, PA · Proposed
Sep 2026Township supervisors approve Phase 1-B final land development, allowing the first six buildings WITF
Approval
Pennsylvania Digital 1 (PAX-1)
Middlesex Township, Cumberland County, PA · Approved
Sep 2026Cumberland County Judge Matthew P. Smith denies residents' request to halt work on PAX-1 while their appeal is considered CBS 21 News (WHP)
Denial
Pennsylvania Digital 1 (PAX-1)
Middlesex Township, Cumberland County, PA · Approved
Sep 2026Uinta County commissioners approve a conditional use permit for the project's independent power production facility Wyoming News (via NewsBreak)
Approval
Prometheus Hyperscale Evanston Campus
Evanston, Uinta County, WY · Approved
Sep 2026Halifax County commissioners approve the amended economic development agreement 5-1, the Daily Herald reports The Daily Herald (Roanoke Rapids)
Approval
Quiet Data Centers, Trestle Road
Enfield, Halifax County, NC · Proposed
Sep 2026State grants permission to add more natural gas turbines FOX CarolinaValara Holdings High Performance Compute Center
Spartanburg, Spartanburg County, SC · Under construction

Moratorium actions

JurisdictionActionDateSource
Mesa County
Colorado · 12 months
AdoptedSep 30, 2026 KJCT 8
City of Woodbury
Minnesota · up to one year
AdoptedSep 23, 2026 Woodbury News Net
Marshall County
Iowa · six months
AdoptedSep 23, 2026 Times Republican
Pima County
Arizona · 120 days
AdoptedSep 23, 2026 AZ Luminaria
Baltimore County
Maryland · about one additional year
ExtendedSep 22, 2026 WYPR
City of North Port
Florida · 18 months
AdoptedSep 22, 2026 WWSB ABC7 / MySuncoast
Kershaw County
South Carolina · one year
AdoptedSep 22, 2026 South Carolina Public Radio
Tulare County
California · 10 months and 15 days
ExtendedSep 22, 2026 Porterville Recorder
City of North Mankato
Minnesota · 12 months
AdoptedSep 21, 2026 Mankato Free Press
City of Salem
Oregon · 120 days
AdoptedSep 21, 2026 KATU
Texas
Texas
AdoptedSep 21, 2026 The Texas Tribune
Town of Massena
New York
RejectedSep 16, 2026 WWNY 7 News
City of Woodburn
Oregon · 120 days
AdoptedSep 14, 2026 Woodburn Independent
Vance County
North Carolina · 60 days
AdoptedSep 14, 2026 WIZS
Lake County
Illinois · eight months
AdoptedSep 8, 2026 Lake County, Illinois
Woodford County
Kentucky · permanent
AdoptedSep 8, 2026 WUKY / Kentucky Lantern
McDowell County
North Carolina · six months
Adoptedreported Sep 3, 2026 WCAB News
City of Miamisburg
Ohio · nine months
AdoptedSep 1, 2026 City of Miamisburg, OH
Mendocino County
California · 45 days
AdoptedSep 1, 2026 The Mendocino Voice
Lawrence County
Illinois · two years
AdoptedSep 2026 WZDM Wisdom 92.1
Loudoun County
Virginia
Vote to draft a pauseSep 2026 DatacenterDynamics
Pierce Township
Ohio
ExtendedSep 2026 FOX19 (WXIX)
Spartanburg County
South Carolina · one year
AdoptedSep 2026 FOX Carolina
Village of Pioneer
Ohio · six months
AdoptedSep 2026 The Bryan Times

Full moratorium tracker →

Court cases filed

CaseProjectStatus
One Hundred Miles, Inc. et al. v. Effingham County Industrial Development Authority and Octans GA
Effingham County Superior Court · filed Sep 21, 2026 WTOC
Project Camelliapending
Residents’ challenge to Effingham County Ordinance 2026-352
Effingham County Superior Court · filed Sep 2, 2026 Effingham Herald
Project Camelliapending
Perry Township residents v. Perry Township Board of Trustees et al.
· filed Sep 1, 2026 Ideastream Public Media
Perry Township Data Centerpending

Hearings and votes: held and upcoming

DateBody and subjectProjectOutcome on record
Sep 23, 2026
held
City of Festus (Festus Forward): Public webinar for questions about the proposed data center City of FestusCRG Festus Data Centernot yet on record
Sep 24, 2026
held
Palm Beach County Board of County Commissioners: Adoption hearing and final vote on a proposed one-year moratorium on large-scale data centers, proposed after the Project Tango denial CBS12Project Tangonot yet on record
Sep 24, 2026
held
East Whiteland Township Board of Supervisors: Hearing to consider adoption of data center zoning ordinance amendment (municipal curative amendment) East Whiteland TownshipSentinel / Green Fig Data Centernot yet on record
Sep 28, 2026
held
King George County Circuit Court: Trial dates of September 28 and 29 set in Amazon Data Services v. King George County Board of Supervisors Fredericksburg AdvanceAmazon Data Services King George campus (former Birchwood power plant site)not yet on record
Sep 28, 2026
held
Pike County Commissioners: Community open house on the PORTS Project, 5–7 p.m., Pike County Fairgrounds Multipurpose Building; AEP and SoftBank expected to attend Scioto Valley GuardianPORTS-Pike Technology Campusnot yet on record
Sep 28, 2026
held
Enid Metropolitan Area Planning Commission: Meeting and public hearing on the Project Thunderbird rezoning request; city staff present the request and any formal citizen protests received City of EnidProject Thunderbirdnot yet on record

Hearings still on a project’s record. Upcoming hearings calendar →

How this report is made

Generated from the Census records at build time. It lists dated timeline events, hearings, lawsuit filing dates and moratorium actions that fall in the month; each links to its project record and source. A month-only date belongs to its month. Entries dated only to a year are not placed in a month. Approval, denial, cancellation and construction counts are made by reading the wording of each dated event, so one event can count in more than one group, and a vote on a related item can be miscounted; open the linked record to read the source. Nothing is estimated.

The same data is behind the statistics page, the charts and the downloads.

Cite this page

Last updated Oct 14, 2026. Figures may change as records are updated — include the date you retrieved them.

APAData Center Census. (2026). U.S. data centers in September 2026. Retrieved from https://datacentercensus.com/reports/2026-09
MLA“U.S. data centers in September 2026.” Data Center Census, Oct 14, 2026, https://datacentercensus.com/reports/2026-09.
Linkhttps://datacentercensus.com/reports/2026-09

Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.