Quarterly report

U.S. data centers in Q3 2026

What changed in the U.S. data center record in Q3 2026: 258 dated changes at 117 tracked projects across 35 states, plus 51 moratorium actions and 8 court cases filed. Every figure below is computed from the Census record and links to its source.

Changes recorded
258
Projects affected
117
States
35
Moratorium actions
51

The quarter in one paragraph

The Census tracked 186 major U.S. data center projects in 36 states as of Nov 6, 2026, with 143.98 GW of published capacity across the projects that publish one. In Q3 2026 we recorded 258 dated changes at 117 projects: 157 rules and votes, 55 court, 49 power and grid, 28 AI buildout. 51 moratorium actions were recorded in 23 states. 1 project recorded construction starting. 11 projects with activity this quarter now sits cancelled, denied or paused.

Counts describe what was recorded in this tracker during the quarter, from published filings, notices and reports. They are not a measure of everything that happened in the industry.

Where the activity was

What the changes were about

Topics overlap: one vote on a power agreement counts in both categories.

Largest projects with activity in Q3 2026

ProjectStatusCapacityLatest change
Fermi America Project Matador
Amarillo, Carson County, TX
Under construction17 GWSep 22, 2026 — Fermi and TensorWave amend their 222 MW lease to move the closing date from Sept. 30 to Oct. 31, 2026, while a lease guaranty is negotiated
PORTS-Pike Technology Campus
Piketon, Pike County, OH
Under construction10 GWAug 17, 2026 — OpenAI announces it has joined the project under a 20-year lease, with NVIDIA investing $1.5 billion
Stratos Project
Box Elder County, UT
Proposed9 GWSep 21, 2026 — O’Leary and Fox News ask the U.S. District Court in Utah to dismiss the defamation suit
Monarch Compute Campus
Point Pleasant, Mason County, WV
Under construction8 GWSep 3, 2026 — Gov. Morrisey announces state 'high-impact' certification for the project
Comanche Circle
Tolar, Hood County, TX
Approved5 GWSep 8, 2026 — Hood County Commissioners Court postpones its discussion of the proposed data center projects, including Comanche Circle, to October 13 so a public hearing can be properly advertised
Meta Hyperion
Holly Ridge, Richland Parish, LA
Under construction5 GWAug 12, 2026 — LPSC votes 3-1 to reject an administrative law judge's recommendation to make Meta job and power-demand information available through subpoenas
Homer City Energy Campus
Homer City, Indiana County, PA
Under construction4.4 GWSep 4, 2026 — Developer reports more than 1,800 tradespeople on site
Project Camellia
Rincon, Effingham County, GA
Proposed3.21 GWSep 21, 2026 — One Hundred Miles and five residents sue the Effingham IDA and Octans GA alleging open-government law violations
Project Thunderbird
Enid, Garfield County, OK
Proposed2.75 GWSep 15, 2026 — A large crowd, most of it opposed to Project Thunderbird, fills the Enid City Commission meeting
Project Tembo
Cheyenne, Laramie County, WY
Approved2.7 GWSep 9, 2026 — Google holds a community open house in Cheyenne

Moratorium actions in Q3 2026

JurisdictionActionLengthWhat the source says
Prince George's County
Maryland · county
Adopted
Jul 2026
two years Hyperscale data center development. WTOP
Source excerpt
“The Prince George's County Council passed a two-year moratorium on hyperscale data center development to give members more time to consider how the county will go about it in the future.”
Metropolitan Government of Nashville and Davidson County
Tennessee · city
Adopted
reported Aug 11, 2026
—
until Dec 1, 2026
Moratorium until Dec. 1, created alongside new regulations for data centers. Axios Nashville
DC BLOX Grassmere Park
Source excerpt
“council imposed a moratorium until Dec. 1 and created new regulations for data centers.”
Imperial County
California · county
Extended
reported Aug 28, 2026
ten months and fifteen days Temporary moratorium extended for an additional ten months and fifteen days. County of Imperial
Source excerpt
“the Board extended the temporary moratorium for an additional ten months and fifteen days”
Imperial County
California · county
Set aside by court
reported Aug 28, 2026
— The Imperial County Superior Court ruled that the moratorium's supporting findings did not adequately cover every applicable state-law requirement and ordered that the moratorium be set aside. County of Imperial
Source excerpt
“The Imperial County Superior Court recently ruled that the findings supporting the moratorium did not sufficiently address all applicable requirements under state law and directed that the moratorium be set aside.”
Montgomery County
Maryland · county
Extended
Aug 2026
18 months Extension of the county's pause on data centers from six months to 18 months. Maryland Matters
Source excerpt
“The Montgomery County Council voted recently to extend its current six-month pause on data centers to 18 months.”
Frederick County
Maryland · county
Adopted
Jul 1, 2026
—
until Dec 31, 2026
Order signed July 1 by County Executive Jessica Fitzwater halting new data center permitting or approvals for the rest of the year. Maryland Matters
Source excerpt
“County Executive Jessica Fitzwater signed an order July 1, pausing new data center permitting or approvals until the end of the year.”
New York
New York · state
Adopted
Jul 14, 2026
until the state completes a Generic Environmental Impact Statement Executive Order No. 62 directs the Department of Environmental Conservation to hold in abeyance discretionary permits, approvals and licenses for construction or expansion of data centers that consume or can consume 50 MW or more, where the application was not complete before the order took effect. It reaches state DEC approvals, not local permits, and exempts facilities primarily used for manufacturing, research (including quantum and biomedical), education (including the Empire AI consortium) or medical care. Office of the Governor of New York
Source excerpt
“is not covered by this definition and thus not subject to this Executive Order”
Paulding County
Georgia · county
Adopted
Jul 2026
—
until Jan 1, 2027
Moratorium in effect until January 1, 2027. FOX 5 Atlanta
Source excerpt
“During Tuesday's board of commissioners meeting, commissioners unanimously approved the moratorium, which will be in effect until January 1, 2027.”
City of Indianapolis
Indiana · city
Adopted
Aug 19, 2026
—
until 2027
Pause on data center projects through 2027 (commission vote 6-0 on language drafted by the City-County Council). Axios Indianapolis
Source excerpt
“The commission voted 6-0 in favor of language drafted earlier this month by the City-County Council to pause data projects through 2027.”
City of Elkhart
Indiana · city
Adopted
Aug 27, 2026
— Moratorium on data centers and battery storage facilities. WNDU
Source excerpt
“The Elkhart City Council passed a moratorium on data centers and battery storage facilities at a special hearing on Thursday, August 27.”
Gregg Township
Pennsylvania · township
Adopted
Aug 2026
— Temporary moratorium on applications for data centers; per the headline, PNK's pending project is still on the table. NorthcentralPA.com
PNK Group data center
Source excerpt
“Supervisors approved a temporary moratorium on applications for data centers at their meeting Thursday”
Village of Wrightstown
Wisconsin · village
Adopted
Jul 2026
one year Moratorium on data center projects in the village. NBC 26
Source excerpt
“The Village of Wrightstown passed a one-year moratorium on data center projects Tuesday night”
Loudoun County
Virginia · county
Vote to draft a pause
Sep 2026
— Supervisors voted 7-1-1 to have staff prepare a resolution pausing data center applications for 12 months. DatacenterDynamics
Source excerpt
“The county board of supervisors this week voted 7-1 on a motion to pause data center applications for 12 months.”
Anderson County
South Carolina · county
Adopted
Aug 2026
six months Six-month moratorium on data centers (final reading, per the headline). FOX Carolina
Source excerpt
“Anderson County Council passed a six-month moratorium on data centers Tuesday night.”
Spartanburg County
South Carolina · county
Adopted
Sep 2026
one year One-year freeze on new data centers, plus strict conditions on any facility that tries to build in the county. FOX Carolina
Source excerpt
“Spartanburg County Council voted 5-1 Monday night to approve a one-year freeze on new data centers, adding strict conditions for any facilities attempting to build in the county.”
Greenwood County
South Carolina · county
Adopted
Jul 2026
one year One-year moratorium on data centers; 4-3 vote on third and final reading. FOX Carolina
Source excerpt
“Councilmembers voted 4-3 on Tuesday on the third and final reading of the ordinance.”
Durham County
North Carolina · county
Adopted
Aug 2026
nine months Nine-month moratorium on new large-scale data centers. WUNC
Source excerpt
“Durham County commissioners voted 4-1 Monday night to adopt a nine-month moratorium on new large-scale data centers.”
Town of Cary
North Carolina · town
Adopted
Aug 27, 2026
18 months Data center development in the town. WRAL
Source excerpt
“Town council on Aug. 27 unanimously approved an 18-month pause on data center development.”
Edgecombe County
North Carolina · county
Adopted
Aug 3, 2026
two years Data centers in the county. WRAL
Source excerpt
“On Aug. 3, the Board of Commissioners reversed course, approving a two-year moratorium on data centers.”
McDowell County
North Carolina · county
Adopted
reported Sep 3, 2026
six months Six-month moratorium on data centers, approved unanimously after a public hearing. WCAB News
Source excerpt
“After the public hearing closed, commissioners voted unanimously for the six-month moratorium.”
Lake County
Illinois · county
Adopted
Sep 8, 2026
eight months Data centers in unincorporated Lake County. Lake County, Illinois
Source excerpt
“The Lake County Board today approved an eight-month moratorium on data centers in unincorporated Lake County”
Lawrence County
Illinois · county
Adopted
Sep 2026
two years Two-year moratorium on data centers. WZDM Wisdom 92.1
Source excerpt
“The Lawrence County, Illinois Board voted Thursday to approve an ordinance for a two-year moratorium on data centers.”
Mercer County
Kentucky · county
Adopted
Aug 2026
one year One-year moratorium on all applications to build new data centers in the county's unincorporated areas. Louisville Public Media
Source excerpt
“The Mercer County Fiscal Court passed an ordinance by a unanimous vote that morning for a one-year moratorium on any application to construct a new data center in unincorporated areas of the county.”
Texas
Texas · state
Announced
Aug 2026
— Gov. Greg Abbott announced a moratorium on data center approvals until regulatory agencies can audit data center proposals that seek to connect to the state's electric grid. The Texas Tribune
Source excerpt
“Amid growing public backlash to the rapid buildout of data centers across Texas, Gov. Greg Abbott on Monday announced a moratorium on the approval of data centers until regulatory agencies can audit proposed data centers seeking connection to the state's electric grid.”
Town of Brookhaven
New York · town
Adopted
Jul 17, 2026
18 months
until Jan 2028
Halts approval of new data centers town-wide while the Department of Planning, Environment and Land Management drafts zoning rules defining data center use, which is currently undefined in the town code. Adopted unanimously after a public hearing that ran nearly six hours. Fire Island News
Source excerpt
“ran nearly six hours”
Town of Massena
New York · town
Rejected
Sep 16, 2026
— Town board voted 3-2 against a proposed six-month moratorium on data center development. WWNY 7 News
Source excerpt
“The Massena town board voted against a six-month moratorium on data center development, moving the town closer to construction of a data center. The town board rejected the moratorium in a 3-2 vote.”
Village of Pioneer
Ohio · village
Adopted
Sep 2026
six months Six-month moratorium on all data centers, adopted 6-0 after a developer proposed a 20-megawatt data center at the AquaBounty property; council can end it early. The Bryan Times
Source excerpt
“Less than a week after a developer spoke to the village planning commission about putting in a data center, village council put a moratorium on all data centers for six months.”
Pierce Township
Ohio · township
Extended
Sep 2026
—
until May 31, 2027
Trustees extended the township's zoning moratorium for data center uses to May 31, 2027 while the zoning commission reviews the zoning code; they also said they are not considering a data center at any site in the township. FOX19 (WXIX)
Source excerpt
“Pierce Township trustees rule out data center, extend zoning moratorium”
Augusta-Richmond County
Georgia · county
Extension recommended
reported Jul 20, 2026
— The Augusta Planning Commission recommended a 60-day extension of the moratorium; WRDW reported on July 20, 2026 that commissioners had been unable to reach agreement at their last meeting. WRDW
Source excerpt
“The Augusta Planning Commission recommended extending the moratorium by 60 more days.”
City of North Mankato
Minnesota · city
Adopted
Sep 21, 2026
12 months Moratorium on new data centers in the city; none may be built while it is in effect. Mankato Free Press
Source excerpt
“The ordinance will last for 12 months, during which no new data centers will be allowed to be constructed in the city.”
City of Salem
Oregon · city
Adopted
Sep 21, 2026
120 days
until Jan 19, 2027
Moratorium on new data center development while a city task force studies how to regulate data centers. KATU
verrus-oakline-mill-creek-salem-or
Source excerpt
“Salem councilors gave final approval to a 120-day moratorium on data center development Monday night”
Kershaw County
South Carolina · county
Adopted
Sep 22, 2026
one year Temporary moratorium on data centers, cryptocurrency mining operations and data processing facilities. South Carolina Public Radio
Source excerpt
“Council voted unanimously to pass the final reading of the ordinance Tuesday night, thus enacting the one-year pause.”
Vance County
North Carolina · county
Adopted
Sep 14, 2026
60 days
until Nov 13, 2026
Moratorium on data center development, ending Nov. 13 or when the county amends the data center requirements in its zoning ordinance. WIZS
natelli-vance-county-nc
Source excerpt
“The Vance County Board of Commissioners voted 5-2 to put a 60-day moratorium in place for data center development.”
City of Miamisburg
Ohio · city
Adopted
Sep 1, 2026
nine months Moratorium halting data center development within the city. City of Miamisburg, OH
Source excerpt
“Miamisburg City Council members voted unanimously, 6-0, to impose a nine-month moratorium on the development of data centers in the city.”
Mendocino County
California · county
Adopted
Sep 1, 2026
45 days
until Oct 16, 2026
Urgency ordinance that prohibits new data centers anywhere in the county's unincorporated area. The Mendocino Voice
Source excerpt
“Mendocino County supervisors voted 5-0 Tuesday to adopt an urgency ordinance barring any new data center in the unincorporated county”
Baltimore County
Maryland · county
Extended
Sep 22, 2026
about one additional year
until Dec 31, 2027
Extends the county's data center permit moratorium, originally due to expire January 2027, through the end of 2027. WYPR
Source excerpt
“There are lawyers and developers that think it's the right way to go, but in terms of residents that we represent, I haven't spoken to one.”
Pima County
Arizona · county
Adopted
Sep 23, 2026
120 days Bars new data center development in unincorporated Pima County for developers who have not yet submitted permit applications; the county says the existing Project Blue campus is exempt because it already holds county land and permits. AZ Luminaria
Source excerpt
“In a desert community already confronting drought and rising temperatures, we as a county have a public health responsibility to understand those impacts before we approve any projects that could place significant new demands on our resources and our infrastructure”
Texas
Texas · state
Adopted
Sep 21, 2026
— Gov. Greg Abbott ordered the Texas Commission on Environmental Quality to stop approving environmental permits for data centers until ERCOT and the Texas Water Development Board complete their audits, broadening his August 2026 moratorium on grid-connection approvals to cover environmental permitting. The Texas Tribune
Source excerpt
“Data centers must pay their own way, protect our grid and water and complete the ERCOT and TWDB audits.”
Marshall County
Iowa · county
Adopted
Sep 23, 2026
six months
until Mar 23, 2027
Moratorium on applications for data centers, AI computing facilities, data mining facilities and cryptocurrency mining operations in unincorporated Marshall County. Times Republican
Source excerpt
“The change gives the county more flexibility to work through the process of drafting regulations through the Zoning Commission.”
Tulare County
California · county
Extended
Sep 22, 2026
10 months and 15 days Extends the county's moratorium on new data center development in unincorporated Tulare County, first adopted for 45 days on August 18, 2026, while the county drafts a permanent zoning ordinance; the board also separately adopted a letter opposing data center construction in the county, 3-2. Porterville Recorder
Source excerpt
“The Tulare County Board of Supervisors extended its moratorium on new data center development Tuesday, giving county officials an additional 10 months and 15 days to consider potential regulations as residents continue to push for a permanent ban.”
City of Woodbury
Minnesota · city
Adopted
Sep 23, 2026
up to one year Blocks permits for new data centers and for expansion of existing high-volume infrastructure beyond what is already approved, while the city spends up to a year reviewing effects on the water supply, power demand, noise and its zoning code. The city planner said Woodbury has no active applications or conversations with data center developers. Woodbury News Net
Source excerpt
“giving the city up to a year to study water use, electricity demand, noise and possible zoning changes”
City of North Port
Florida · city
Adopted
Sep 22, 2026
18 months Retroactive moratorium on accepting and approving new data center applications, passed 3-2 after a pending roughly 900,000-square-foot data center application was excluded from the halt on staff review (though not final approval) after the city attorney warned excluding it entirely could expose the city to a lawsuit. WWSB ABC7 / MySuncoast
Source excerpt
“Including the project in the moratorium could expose North Port to a lawsuit. The company could argue it was denied legal rights granted under the application process.”
Woodford County
Kentucky · county
Adopted
Sep 8, 2026
permanent Fiscal Court unanimously banned the construction of data centers, landfills and large battery storage systems in the county, becoming the first Kentucky county to permanently ban data centers; no specific developer proposal was pending at the time. The county seat, Versailles, had separately adopted a temporary moratorium in July 2026. WUKY / Kentucky Lantern
Source excerpt
“Our rolling pastures, our historic farms, our agriculture, are not just scenic views. They are the backbone of our economy.”
City of Woodburn
Oregon · city
Adopted
Sep 14, 2026
120 days Pauses new data center development while the city weighs strain on the power grid, drinking water and sewer capacity, road traffic, first responders, backup generators, noise, jobs and the supply of industrial land. Woodburn Independent
Source excerpt
“The impact of a data center may extend beyond the building itself, increasing demand on electric service, water and wastewater, roads, emergency response resources, generators, noise, employment, and industrial land supply.”
Spokane County
Washington · county
Adopted
Aug 18, 2026
4 months
until Dec 15, 2026
Pauses the county's intake and review of building permit applications for data centers in unincorporated Spokane County while the Planning Commission works through a zoning text amendment on data center rules. Spokane County Board of County Commissioners
Source excerpt
“Today, the Board of County Commissioners unanimously approved a fourmonth pause on the acceptance and processing of County building permits for data centers.”
Mesa County
Colorado · county
Adopted
Sep 30, 2026
12 months Pauses acceptance, processing and approval of land-use applications for data centers in unincorporated Mesa County while the county rewrites its land development code. KJCT 8
Source excerpt
“The moratorium temporarily halts the acceptance, processing and approval of land-use applications for any data centers in unincorporated Mesa County.”
Madison County
Florida · county
Adopted
Jul 22, 2026
— Pauses the county's acceptance, review, processing and approval of applications tied to data center construction, expansion or operation in the unincorporated county. One local news report describes the pause as one year; the ordinance text was not reviewed. WWALS Watershed Coalition
Source excerpt
“Madison County BOCC passed the datacenter moratorium 4:0.”
City of Cleveland
Ohio · city
Adopted
Jul 15, 2026
3 months Pause on data centers in Cleveland while a working group develops recommendations. City Council vote was 14-1. Cleveland 19 News
Source excerpt
“Cleveland City Council approved a moratorium on data centers by a 14-to-1 vote Wednesday night.”
City of Mattoon
Illinois · city
Adopted
Sep 2026
renewed each year New data center developments larger than 21,780 square feet in the city and the area up to 1.5 miles outside it where the city has zoning authority. Existing businesses can keep operating. Stays in place until the council changes or ends it. The article is dated September 3, 2026 and says the vote was Tuesday night. City of Mattoon
Source excerpt
“The moratorium applies to any new data center developments larger than 21,780 square feet”
Nodaway County
Missouri · county
Adopted
Jul 21, 2026
6 months Unincorporated areas of the county; bars building or operating data centers and supporting facilities such as substations, backup generators and water systems. KXCV
Source excerpt
“unanimously approve a six-month moratorium on building data centers”
Town of Beloit
Wisconsin · town
Vote to draft a pause
Aug 17, 2026
12 months Supervisors voted 4-0 on a resolution starting the process for a 12-month moratorium; a public hearing and an ordinance were still to come. Beloit Daily News
Source excerpt
“calling for a 12-month moratorium on data center projects”

Court cases filed in Q3 2026

CaseProjectStatus
One Hundred Miles, Inc. et al. v. Effingham County Industrial Development Authority and Octans GA
Effingham County Superior Court · filed Sep 21, 2026
Project Camelliapending
Residents’ challenge to Effingham County Ordinance 2026-352
Effingham County Superior Court · filed Sep 2, 2026
Project Camelliapending
Waverly residents v. Sangamon County and Sangamon County Board
Illinois circuit court (Circuit Judge Adam Giganti) · filed Jul 6, 2026
CyrusOne Sangamon County Data Centerpending
Tonawanda Seneca Nation et al. v. Genesee County IDA and Town of Alabama officials
New York State Supreme Court, Genesee County · filed Jul 2026
Stream Data Centers STAMP Campuspending
NV Energy v. Tract
Second Judicial District Court, Washoe County, Nevada · filed Jul 2026
Fleet Data Centers TRIC campuses (South Valley and Peru Ridge)pending
Perry Township residents v. Perry Township Board of Trustees et al.
· filed Sep 1, 2026
Perry Township Data Centerpending
DCB Nashville, LLC v. The Metropolitan Government of Nashville and Davidson County, No. 3:26-cv-01143
U.S. District Court for the Middle District of Tennessee · filed Aug 11, 2026
DC BLOX Nashville Data Centerpending
Sturtevant residents v. Microsoft (noise class action)
U.S. District Court for the Eastern District of Wisconsin · filed Jul 1, 2026
Microsoft Fairwaterpending

How this report is made

Everything above is generated from the Census dataset at build time: the dated events, project records, moratorium entries and court cases, each of which was recorded from a published source that is linked on the project or tracker page. Nothing is estimated or modeled. Because the record grows as projects are researched, a quarter’s counts can rise after the fact; the report is regenerated on every publish, and the date below is the current one.

Reporters and researchers are welcome to use these figures. The underlying data is downloadable as JSON, CSV and GeoJSON, and the press kit has the standing numbers, wording and contact details.

Which other quarters have a report?

Q4 2026 · Q2 2026 · Q1 2026 · All reports · Statistics

Cite this page

Last updated Nov 6, 2026. Figures may change as records are updated — include the date you retrieved them.

APAData Center Census. (2026). U.S. data centers in Q3 2026: quarterly data report. Retrieved from https://datacentercensus.com/reports/2026-q3
MLA“U.S. data centers in Q3 2026: quarterly data report.” Data Center Census, Nov 6, 2026, https://datacentercensus.com/reports/2026-q3.
Linkhttps://datacentercensus.com/reports/2026-q3

Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.