Quarterly report
U.S. data centers in Q2 2026
What changed in the U.S. data center record in Q2 2026: 135 dated changes at 76 tracked projects across 31 states, plus 22 moratorium actions and 10 court cases filed. Every figure below is computed from the Census record and links to its source.
- Changes recorded
- 135
- Projects affected
- 76
- States
- 31
- Moratorium actions
- 22
The quarter in one paragraph
The Census tracked 138 major U.S. data center projects in 35 states as of Sep 22, 2026, with 122.02 GW of published capacity across the projects that publish one. In Q2 2026 we recorded 135 dated changes at 76 projects: 73 rules and votes, 27 court, 20 AI buildout, 18 power and grid. 22 moratorium actions were recorded in 12 states. 3 projects recorded construction starting. 13 projects with activity this quarter now sits cancelled, denied or paused.
Counts describe what was recorded in this tracker during the quarter, from published filings, notices and reports. They are not a measure of everything that happened in the industry.
Where the activity was
What the changes were about
| Topic | Changes |
|---|---|
| Rules & votes | 73 |
| Courts | 27 |
| AI buildout | 20 |
| Power & grid | 18 |
Topics overlap: one vote on a power agreement counts in both categories.
Largest projects with activity in Q2 2026
| Project | Status | Capacity | Latest change |
|---|---|---|---|
| Fermi America Project Matador Amarillo, Carson County, TX | Under construction | 17 GW | Apr 2026 — CEO Toby Neugebauer removed; CFO resigns |
| PORTS-Pike Technology Campus Piketon, Pike County, OH | Under construction | 10 GW | May 28, 2026 — Permit filed with Ohio EPA covering wetlands and stream impacts on private land |
| Stratos Project Box Elder County, UT | Proposed | 9 GW | Jun 10, 2026 — County adopts 180-day moratorium on new data centers and data center power plants; Stratos exempt because it falls under MIDA |
| Monarch Compute Campus Point Pleasant, Mason County, WV | Under construction | 8 GW | Jun 15, 2026 — WVDEP public hearing on air permit at Mason County Courthouse |
| Comanche Circle Tolar, Hood County, TX | Approved | 5 GW | Jun 18, 2026 — NRG requests withdrawal of its air permit application for the 2 GW Tolar Power Center planned to supply Comanche Circle |
| Meta Hyperion Holly Ridge, Richland Parish, LA | Under construction | 5 GW | Apr 16, 2026 — LPSC votes 4-1 to fast-track Entergy's plan for seven new gas plants for the campus |
| Project Tembo Cheyenne, Laramie County, WY | Approved | 2.7 GW | Jun 30, 2026 — Site-plan amendment filing with the county identifies Google as the owner |
| Project Jupiter Santa Teresa, Doña Ana County, NM | Under construction | 2.46 GW | Apr 14, 2026 — County Commission orders review of developer statements, including on closed-loop cooling and water |
| Quantum Frederick Adamstown, Frederick County, MD | Under construction | 2.4 GW | Jun 30, 2026 — Maryland Supreme Court rules that a citizen referendum on the county's expanded data center zoning must stay off the ballot |
| IREN Sweetwater data center campus Sweetwater, Fisher County, TX | Under construction | 2 GW | May 28, 2026 — IREN announces NVIDIA partnership on AI-ready design; about 300 construction workers on site |
Moratorium actions in Q2 2026
| Jurisdiction | Action | Length | What the source says |
|---|---|---|---|
| Carroll County Georgia · county |
Extended Jun 2026 |
100 days | Data center moratorium for unincorporated areas of the county, extended another 100 days. Times-GeorgianSource excerpt“The Carroll County Board of Commissioners on Tuesday voted to extend for another 100 days a data center moratorium for unincorporated areas of the county.” |
| Citrus County Florida · county |
Adopted May 1, 2026 |
one year | New data centers. Spectrum NewsSource excerpt“Despite the county enacting a one-year moratorium on new data centers on May 1, discussions are continuing on a data center proposal in Lecanto, which was initiated before the pause was instituted.” |
| Imperial County California · county |
Adopted Jun 2026 |
45 days | Temporary moratorium on data centers in the county. County of ImperialSource excerpt“In June 2026, the Imperial County Board of Supervisors adopted a 45-day temporary moratorium” |
| Town of Apex North Carolina · town |
Adopted Apr 2026 |
one year until Apr 27, 2027 |
Review or approval of applications for data centers (and associated uses like cryptocurrency mining) until April 27, 2027. INDY WeekSource excerpt“The moratorium prevents Apex from reviewing or approving applications for the development of data centers (along with associated uses like cryptocurrency mining) until April 27, 2027.” |
| Box Elder County Utah · county |
Adopted Jun 2026 |
180 days | New data centers and data center power plants on unincorporated land in the county. Utah Public RadioSource excerpt“The commissioners unanimously passed an ordinance Wednesday that imposes a 180-day moratorium on new data centers and data center power plants on unincorporated land in Box Elder County.” |
| Augusta-Richmond County Georgia · county |
Adopted Jun 2026 |
49 days | Pause on new data centers to allow public input. WRDWSource excerpt“commissioners approved a 49-day pause on new data centers to allow public input” |
| Elmwood Township Michigan · township |
Adopted Jun 17, 2026 |
12 months | Data centers and cryptocurrency mining facilities (Resolution No. 2026.06.17.A). Tuscola TodaySource excerpt“Resolution No. 2026.06.17.A, imposing a 12-month temporary moratorium on data centers and cryptocurrency mining facilities.” |
| Butler County Ohio · county |
Adopted Jun 2026 |
six months | Six-month moratorium on data centers. WVXUSource excerpt“voted unanimously Tuesday to approve a six-month moratorium on data centers.” |
| City of Minneapolis Minnesota · city |
Adopted Jun 2026 |
five months | Pause on new data center development. CBS MinnesotaSource excerpt“Minneapolis City Council members approved a five-month pause on new data center development Thursday.” |
| City of Inver Grove Heights Minnesota · city |
Adopted Jun 2026 |
one year | New data center development within the city (interim ordinance). Limitless NewsSource excerpt“The Inver Grove Heights City Council voted 3-2 Friday to approve the third and final reading of a one-year interim ordinance establishing a moratorium on new data center development within the city.” |
| Manitowoc County Wisconsin · county |
Adopted Apr 2026 |
18 months | Moratorium on data center permitting. WPRSource excerpt“the Manitowoc County Board unanimously approved an 18-month moratorium on data center permitting Tuesday night.” |
| Dane County Wisconsin · county |
Adopted Jun 2026 |
— until Dec 2027 |
Pause on zoning permit applications for hyperscale data centers until December 2027. IsthmusSource excerpt“The Dane County Board unanimously approved a data center moratorium Thursday, pausing zoning permit applications for hyperscale data centers until December 2027.” |
| City of Durham North Carolina · city |
Adopted May 4, 2026 |
60 days | Data center planning and development. WRALSource excerpt“On May 4, city council members passed a 60-day moratorium on data center planning and development.” |
| Orange County North Carolina · county |
Adopted Apr 21, 2026 |
one year | Data center construction across the county. WRALSource excerpt“Commissioners voted unanimously on April 21 to establish a one-year pause on data center construction across the county.” |
| Harnett County North Carolina · county |
Adopted May 4, 2026 |
12 months | Data centers in the county. WRALSource excerpt“The Board of Commissioners voted on May 4 to adopt a 12-month data center moratorium.” |
| Cumberland County North Carolina · county |
Adopted Jun 15, 2026 |
six months until Dec 2026 |
Data centers in the county. WRALSource excerpt“Commissioners adopted a six-month data center moratorium on June 15, which will expire in December.” |
| City of Charlotte North Carolina · city |
Adopted Jun 2026 |
150 days | Moratorium on data center construction (150 days, per the headline). Axios CharlotteSource excerpt“Charlotte City Council unanimously voted to enact the moratorium Monday night.” |
| Oklahoma City Oklahoma · city |
Adopted Apr 2026 |
— until Dec 31, 2026 |
Takes effect immediately and remains until Dec. 31, 2026, or earlier if zoning code amendments on data centers are approved. City of Oklahoma CitySource excerpt“The moratorium takes effect immediately and will remain in place until either December 31, 2026, or earlier if amendments to the City's Zoning Code regarding data centers are approved by City Council.” |
| Logan County Illinois · county |
Adopted May 19, 2026 |
— | Moratorium approved 6-4 on May 19; per the headline, it was later declared invalid. Illinois TimesSource excerpt“Logan County Board members on May 19 voted 6-4 in favor of the moratorium” |
| Montgomery Township Ohio · township |
Adopted Jun 2026 |
two years | Two-year moratorium on the construction of data centers within the township (per Ashland Source). Ashland SourceSource excerpt“The three-member board unanimously approved a two-year moratorium on the construction of data centers within Montgomery Township.” |
| DeKalb County Georgia · county |
Extended Jun 2026 |
100 days | New data center applications; extension keeps the pause in place through the end of September. CBS News AtlantaSource excerpt“DeKalb County commissioners have approved a 100-day extension of a moratorium on new data center applications, keeping the pause in place through the end of September.” |
| Jackson County Missouri · county |
Adopted Jun 2026 |
180 days | Six-month moratorium on data center applications (per the headline); passed with eight votes in favor and one excused. KCTV5Source excerpt“The legislature passed it on Monday with eight votes in favor and one excused.” |
Court cases filed in Q2 2026
| Case | Project | Status |
|---|---|---|
| Box Elder Accountability Referendum (BEAR) v. Box Elder County Utah First District Court · filed Jun 3, 2026 | Stratos Project | pending |
| Nearby residents' lawsuit against the City of Yorkville and Pioneer Development LLC · filed Apr 2026 | Project Cardinal Data Center Campus | pending |
| NAACP v. X.AI Corp. and MZX Tech LLC, No. 3:26-cv-00074-MPM-JMV U.S. District Court for the Northern District of Mississippi · filed Apr 14, 2026 | xAI Colossus 2 | pending |
| Oracle America Cloud Services LLC v. Public Service Commission of Wisconsin Ozaukee County Circuit Court (Case No. 2026CV000256) · filed Jun 19, 2026 | Port Washington (Lighthouse) Data Center Campus | pending |
| Bockrath et al. v. Coweta County and Atlas Development LLC Coweta County Superior Court · filed May 5, 2026 | Project Sail | pending |
| Wake Up Jeffco LLC et al. v. City of Festus, Missouri and CRG Acquisition LLC St. Louis County Circuit Court · filed Apr 8, 2026 | CRG Festus Data Center | pending |
| Imperial Valley Computer Manufacturing v. Imperial Irrigation District Imperial County Superior Court · filed Jun 5, 2026 | Imperial Data Center | pending |
| Brown, Montgomery and Gentile v. DataOne New Jersey Superior Court, Cumberland County · filed Jun 2026 | Nebius Vineland Data Center | pending |
| Stop the Hermantown Data Center lawsuit over comprehensive plan and rezoning St. Louis County District Court · filed Apr 29, 2026 | Google Hermantown Data Center | pending |
| Preserve Our Yorkville and Community lawsuit over Project Steel rezoning · filed May 2026 | Project Steel Data Center Campus | pending |
How this report is made
Everything above is generated from the Census dataset at build time: the dated events, project records, moratorium entries and court cases, each of which was recorded from a published source that is linked on the project or tracker page. Nothing is estimated or modeled. Because the record grows as projects are researched, a quarter’s counts can rise after the fact; the report is regenerated on every publish, and the date below is the current one.
Reporters and researchers are welcome to use these figures. The underlying data is downloadable as JSON, CSV and GeoJSON, and the press kit has the standing numbers, wording and contact details.
Cite this page
Last updated Sep 22, 2026. Figures may change as records are updated — include the date you retrieved them.
| APA | Data Center Census. (2026). U.S. data centers in Q2 2026: quarterly data report. Retrieved from https://datacentercensus.com/reports/2026-q2 |
|---|---|
| MLA | “U.S. data centers in Q2 2026: quarterly data report.” Data Center Census, Sep 22, 2026, https://datacentercensus.com/reports/2026-q2. |
| Link | https://datacentercensus.com/reports/2026-q2 |
Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.