Data Center Census Near me

Monthly report

U.S. data centers in April 2026

In April 2026, the Data Center Census recorded 70 dated changes at 54 tracked projects across 31 states.

Final report for April 2026, published May 1, 2026. Last data change: . Page rebuilt .

← March 2026 May 2026 → All reports · Monthly RSS

Dated changes
70
Projects with a first milestone
6
Moratorium actions
7
Court cases filed
4

The month in one paragraph

In April 2026, the Data Center Census recorded 70 dated changes at 54 tracked projects across 31 states. 6 projects have their earliest dated milestone in the month. Events recorded include 15 approvals, 1 cancellation, 1 construction or operations start. 7 moratorium actions were recorded, 5 of them adopted, extended or announced. 4 court cases were filed. 2 hearings or votes on the record were held. That is 19 more than the 51 changes recorded in March 2026.

Counts describe what was recorded in this tracker, from published filings, notices and reports. They are not a measure of everything that happened in the industry, and a month’s counts can rise later if sources dated in it are added.

Compared with March 2026

MeasureApril 2026March 2026Change
Dated changes recorded7051+19
Projects with a change5447+7
States3120+11
Projects with first milestone65+1
Approval events1511+4
Denial events02−2
Cancellation events110
Construction or operations starts110
Moratorium actions79−2
Court cases filed40+4
Hearings and votes held20+2
Hearings and votes upcoming000

Projects with their first milestone in April 2026

ProjectFirst milestoneStatus now
Fort Meade Hyperscale Data Center
Fort Meade, Polk County, FL
Apr 14, 2026Approved
Muncy Data Center
Muncy Township, Lycoming County, PA
Apr 15, 2026Proposed
Ranalli Lysander Data Center
Lysander, Onondaga County, NY
Apr 18, 2026Rumored
Stratos Project
Box Elder County, UT
Apr 24, 2026Proposed
Compass Datacenters Red Oak second campus
Red Oak, Ellis County, TX
Apr 27, 2026Approved
Switch Big Beaver data center campus
Big Beaver, Beaver County, PA
Apr 30, 2026Proposed

A project appears here when its earliest dated timeline entry is in this month. It does not mean it was announced publicly that month.

Every dated change

DateWhat changedProject
Apr 30, 2026Five buildings reported operating at the Mega Site; Veolia wastewater partnership for cooling described WLBTAmazon Web Services Madison County Mega Site campus
Canton, Madison County, MS · Operating
Apr 30, 2026QTS files appeal petitions with the Supreme Court of Virginia Virginia BusinessPrince William Digital Gateway
Gainesville, Prince William County, VA · Cancelled
Apr 30, 2026Switch announced a 382-acre campus in Big Beaver Borough, to join its existing campuses in Atlanta, Austin, Grand Rapids, Las Vegas and Tahoe Reno. SwitchSwitch Big Beaver data center campus
Big Beaver, Beaver County, PA · Proposed
Apr 29, 2026Stop the Hermantown Data Center files a lawsuit in St. Louis County District Court MPR NewsGoogle Hermantown Data Center
Hermantown, St. Louis County, MN · Proposed
Apr 28, 2026Muncy Township acknowledges receipt of a conditional use plan for the Muncy Data Center NorthcentralPA.comMuncy Data Center
Muncy Township, Lycoming County, PA · Proposed
Apr 28, 2026Financing secured (Related Digital, Blackstone-affiliated funds, PIMCO-managed accounts) CBS DetroitSaline Township Stargate Data Center
Saline Township, Washtenaw County, MI · Under construction
Apr 28, 2026Application filed with the Utah Division of Water Rights to transfer an 11 acre-foot Hansel Valley water right for the project KSL.comStratos Project
Box Elder County, UT · Proposed
Apr 27, 2026Planning and zoning board votes 3-2 not to recommend the rezoning Ellis County PressCompass Datacenters Red Oak second campus
Red Oak, Ellis County, TX · Approved
Apr 27, 2026Oakland County Election Commission approves recall petition language against township trustees WDIV ClickOnDetroit
Approval
Project Flex
New Hudson, Oakland County, MI · Approved
Apr 24, 2026Earthjustice, for the Environmental Confederation of Southwest Florida, asks the city to reconsider and revoke its approval The Ledger (via AOL)
Approval
Fort Meade Hyperscale Data Center
Fort Meade, Polk County, FL · Approved
Apr 24, 2026Construction underway as dozens protest at the site AZ Luminaria
Construction or operations start
Project Blue
Tucson, Pima County, AZ · Under construction
Apr 24, 2026U.S. Energy Secretary Chris Wright tours campus The GazetteQTS Cedar Rapids Data Center Campus
Cedar Rapids, Linn County, IA · Under construction
Apr 24, 2026MIDA announces plans for the Stratos Project KPCWStratos Project
Box Elder County, UT · Proposed
Apr 23, 2026The Missouri Times reports on the Planning and Zoning Commission's recommendation, citing projections of more than 3,000 jobs and tens of millions of dollars a year in tax revenue The Missouri TimesGateway Digital Campus
Villa Ridge, Franklin County, MO · Approved
Apr 22, 2026Filing for 548,950 sq ft Freebird Phase 1 reported DCDStargate Milam County
Burlington, Milam County, TX · Under construction
Apr 21, 2026Franklin County's Planning and Zoning Commission votes 8-1 to recommend approval of the Diamond 66/Diamond Farms (Gateway Digital Campus) rezoning Franklin County, Missouri (franklinmo.gov)
Approval
Gateway Digital Campus
Villa Ridge, Franklin County, MO · Approved
Apr 21, 2026Motion to prohibit data centers citywide fails 3-4; data centers restricted to high industrial zones Community ImpactHighlander SM One data center
San Marcos, Hays County, TX · Denied
Apr 21, 2026Franklin County's Planning and Zoning Commission votes against recommending approval of BLE Landholdings' rezoning request, four in favor to five opposed Franklin County, Missouri (franklinmo.gov)
Approval
Meramec Valley Technology Park
Pacific, Franklin County, MO · Approved
Apr 21, 2026Rosemount City Council unanimously adopts a one-year moratorium covering new data center developments Sun ThisWeek (hometownsource.com)Meta Rosemount Data Center
Rosemount, Dakota County, MN · Under construction
Apr 21, 2026Dickey County closes several roads damaged by construction traffic KFGOPolaris Forge 1
Ellendale, Dickey County, ND · Operating
Apr 21, 2026Township board unanimously approves first reading of a six-month moratorium on data center uses Frenchtown Charter Township
Approval
Project Cherry Blossom
Frenchtown Township, Monroe County, MI · Proposed
Apr 21, 2026Council approves rezoning of 914 acres, allowing 18 data center structures across an expanded footprint ABC 33/40
Approval
Project Marvel
Bessemer, Jefferson County, AL · Approved
Apr 20, 2026City approves updated development agreements for two additions City of Farmington
Approval
Farmington Technology Park
Farmington, Dakota County, MN · Approved
Apr 20, 2026Fleet files PUCN applications for South Valley (Docket 26-04026) and Peru Ridge (Docket 26-04027) self-generation plants The Nevada IndependentFleet Data Centers TRIC campuses (South Valley and Peru Ridge)
Storey County, NV · Proposed
Apr 20, 2026Monarch Cloud Campus LLC submits air construction permit application to WVDEP for 2.16 GW on-site generation Charleston Gazette-MailMonarch Compute Campus
Point Pleasant, Mason County, WV · Under construction
Apr 20, 2026Reporting describes plans for two 250,000 sq ft data centers totaling 200 MW on the former plant site, with an online petition against the proposal gathering more than 150 signatures DatacenterDynamicsRemington Site Data Center
Ilion, Herkimer County, NY · Proposed
Apr 18, 2026Lysander Town Board work session and regular meeting; the board votes 5-0 to authorize the town attorney to begin drafting a data center moratorium after a petition gathers more than 1,500 signatures Baldwinsville Messenger / Eagle News OnlineRanalli Lysander Data Center
Lysander, Onondaga County, NY · Rumored
Apr 17, 2026Seven Decatur Township residents file petition for judicial review of the commission's decision Mirror IndySabey Decatur Technology Park
Indianapolis, Marion County, IN · Approved
Apr 17, 2026AG Dana Nessel appeals MPSC approval to Michigan Court of Appeals Michigan Department of Attorney General
Approval
Saline Township Stargate Data Center
Saline Township, Washtenaw County, MI · Under construction
Apr 17, 2026Epoch AI review reports land cleared but no large-scale data center construction visible Epoch AIStargate Lordstown
Lordstown, Trumbull County, OH · Under construction
Apr 16, 2026LPSC votes 4-1 to fast-track Entergy's plan for seven new gas plants for the campus Louisiana Radio NetworkMeta Hyperion
Holly Ridge, Richland Parish, LA · Under construction
Apr 15, 2026Third public hearing on rezoning of about 104 acres; Planning Commission tables decision WWMTMicrosoft Gaines Township data center
Caledonia, Kent County, MI · Proposed
Apr 15, 2026Zoning permit application for the data center is dated April 15 Williamsport Sun-GazetteMuncy Data Center
Muncy Township, Lycoming County, PA · Proposed
Apr 14, 2026City Commission votes 5-0 to approve the 20-year developer agreement, revised to be contingent on a water district permit The Ledger (via AOL)
Approval
Fort Meade Hyperscale Data Center
Fort Meade, Polk County, FL · Approved
Apr 14, 2026DNR public hearing on air permit (comment period Mar. 3-Apr. 14) Wisconsin Department of Natural ResourcesPort Washington (Lighthouse) Data Center Campus
Port Washington, Ozaukee County, WI · Under construction
Apr 14, 2026Board of County Supervisors unanimously votes not to appeal Virginia BusinessPrince William Digital Gateway
Gainesville, Prince William County, VA · Cancelled
Apr 14, 2026County Commission orders review of developer statements, including on closed-loop cooling and water Doña Ana CountyProject Jupiter
Santa Teresa, Doña Ana County, NM · Under construction
Apr 14, 2026NAACP files Clean Air Act lawsuit against xAI and MZX Tech; DOJ moved in June 2026 to intervene on the company’s side Scientific AmericanxAI Colossus 2
Memphis, Shelby County, TN · Under construction
Apr 13, 2026Superior Court Judge Brenden Griffin dismisses No Desert Data Center Coalition's open-meeting lawsuit; plaintiffs planned appeal AZPMProject Blue
Tucson, Pima County, AZ · Under construction
Apr 13, 2026Guido files notices of appeal of the dismissals WRDWPumpkin Technology Campus
Harlem, Columbia County, GA · Approved
Apr 13, 2026Guido files notices of appeal to Georgia Court of Appeals WRDWWhite Oak Technology Park
Appling, Columbia County, GA · Approved
Apr 9, 2026Gov. Tate Reeves announces $11 billion AWS expansion in Madison County, part of $25 billion statewide Office of Governor Tate ReevesAmazon Web Services Madison County Mega Site campus
Canton, Madison County, MS · Operating
Apr 8, 2026Residents and Wake Up Jeffco LLC sue City of Festus and CRG Acquisition LLC in St. Louis County Circuit Court Jefferson County LeaderCRG Festus Data Center
Festus, Jefferson County, MO · Approved
Apr 8, 2026Public hearing on the moratorium; residents voice support for it WBNGEco-Yotta Oneonta Data Center
Oneonta, Otsego County, NY · Proposed
Apr 7, 2026Four pro-project incumbent council members lose reelection Jefferson County LeaderCRG Festus Data Center
Festus, Jefferson County, MO · Approved
Apr 7, 2026County Board approves zoning 17-10 NPR Illinois
Approval
CyrusOne Sangamon County Data Center
Waverly, Sangamon County, IL · Approved
Apr 7, 2026Board of Supervisors approves lot merger 4-1 KPBS
Approval
Imperial Data Center
Imperial, Imperial County, CA · Paused
Apr 7, 2026Port Washington voters approve a referendum requiring voter approval of future large TIDs; it does not affect the TID already approved for the data center WUWM
Approval
Port Washington (Lighthouse) Data Center Campus
Port Washington, Ozaukee County, WI · Under construction
Apr 7, 2026Board of Commissioners approves rezoning 3-2 (McKenzie and Blackburn opposed) Atlanta Journal-Constitution
Approval
Project Sail
Newnan, Coweta County, GA · Approved
Apr 6, 2026Deep Green withdraws its conditional rezoning request Lansing State Journal (via AOL)
Cancellation
Deep Green Lansing data center
Lansing, Ingham County, MI · Cancelled
Apr 6, 2026Vance County Board of Commissioners delays a decision on the rezoning DatacenterDynamicsNatelli data center, U.S. 158
Vance County, NC · Proposed
Apr 2, 2026DCD reports, citing the Financial Times, that the CoreWeave deal collapsed and Poolside is seeking new partners DatacenterDynamicsProject Horizon
Fort Stockton, Pecos County, TX · Proposed
Apr 1, 2026Planning Commission holds public hearing on the proposed moratorium Frenchtown Charter TownshipProject Cherry Blossom
Frenchtown Township, Monroe County, MI · Proposed
Apr 2026Amazon reveals it may develop a data center close to the Calvert Cliffs Nuclear Power Plant, according to DatacenterDynamics DatacenterDynamicsCalvert Technology Center
Lusby, Calvert County, MD · Cancelled
Apr 2026CEO Toby Neugebauer removed; CFO resigns ABC 7 AmarilloFermi America Project Matador
Amarillo, Carson County, TX · Under construction
Apr 2026Fort Meade Planning and Zoning Commission approves the project and sends it to the City Commission Spectrum News 13
Approval
Fort Meade Hyperscale Data Center
Fort Meade, Polk County, FL · Approved
Apr 2026Florida Commerce Secretary Alex Kelly issues a letter opposing the project WUSFFort Meade Hyperscale Data Center
Fort Meade, Polk County, FL · Approved
Apr 2026IDEM approves plans for more than 140 additional emergency diesel generators at the campus 21Alive (WPTA)
Approval
Google Fort Wayne data center
Fort Wayne, Allen County, IN · Operating
Apr 2026County Board does not extend the moratorium and sends the issue back to the zoning board pending a data center ordinance FOX IllinoisLogan Prairie Data Center
Latham, Logan County, IL · Proposed
Apr 2026Equipment brought online at first facility Microsoft SourceMicrosoft Fairwater
Mount Pleasant, Racine County, WI · Operating
Apr 2026Microsoft says the project is in the planning phase with early site preparation underway, including road work tied to permanently closing Country Club Road, expected to last until late summer 2026 MicrosoftMicrosoft Mega Park
Person County, NC · Proposed
Apr 2026Vance County Board of Commissioners votes 6-1 to rezone land that could be used for a data center DatacenterDynamicsNatelli data center, U.S. 158
Vance County, NC · Proposed
Apr 2026More than 100 residents rally against the project at Giampietro Memorial Park SNJ TodayNebius Vineland Data Center
Vineland, Cumberland County, NJ · Under construction
Apr 2026Apex Town Council unanimously passes a 12-month moratorium on data centers INDY WeekNew Hill Digital Campus
Apex, Wake County, NC · Cancelled
Apr 2026Panattoni hosts an open house at Perry High School on the project Ideastream Public MediaPerry Township Data Center
Canton, Stark County, OH · Under construction
Apr 2026Compass Datacenters drops its appeal WTOP NewsPrince William Digital Gateway
Gainesville, Prince William County, VA · Cancelled
Apr 2026A lawsuit names the City of Yorkville and Pioneer Development LLC as defendants Shaw LocalProject Cardinal Data Center Campus
Yorkville, Kendall County, IL · Approved
Apr 2026Crusoe pauses development 'at the request of our customer' and leaves the project Wyoming Tribune EagleProject Tembo
Cheyenne, Laramie County, WY · Approved
Apr 2026An environmental assessment of the Remington Arms site finds contamination New York AlmanackRemington Site Data Center
Ilion, Herkimer County, NY · Proposed
Apr 2026Plans for a 300MW, 500,000 sq ft data center on the site are before the Town of Tonawanda planning board DatacenterDynamicsRiverview Innovation & Technology Campus
Tonawanda, Erie County, NY · Proposed

Moratorium actions

JurisdictionActionDateSource
Maine
Maine
RejectedApr 29, 2026 Maine Morning Star
Maine
Maine
RejectedApr 24, 2026 Office of Governor Janet T. Mills
Orange County
North Carolina · one year
AdoptedApr 21, 2026 WRAL
Providence Township
Ohio · 12 months
AdoptedApr 15, 2026 Toledo Free Press
Manitowoc County
Wisconsin · 18 months
AdoptedApr 2026 WPR
Oklahoma City
Oklahoma
AdoptedApr 2026 City of Oklahoma City
Town of Apex
North Carolina · one year
AdoptedApr 2026 INDY Week

Full moratorium tracker →

Court cases filed

CaseProjectStatus
Stop the Hermantown Data Center lawsuit over comprehensive plan and rezoning
St. Louis County District Court · filed Apr 29, 2026 MPR News
Google Hermantown Data Centerpending
NAACP v. X.AI Corp. and MZX Tech LLC, No. 3:26-cv-00074-MPM-JMV
U.S. District Court for the Northern District of Mississippi · filed Apr 14, 2026 U.S. District Court for the Northern District of Mississippi (via NAACP)
xAI Colossus 2pending
Wake Up Jeffco LLC et al. v. City of Festus, Missouri and CRG Acquisition LLC
St. Louis County Circuit Court · filed Apr 8, 2026 Leader (Jefferson County, MO)
CRG Festus Data Centerpending
Nearby residents' lawsuit against the City of Yorkville and Pioneer Development LLC
· filed Apr 2026 Shaw Local
Project Cardinal Data Center Campuspending

Hearings and votes: held and upcoming

DateBody and subjectProjectOutcome on record
Apr 8, 2026
held
Town of Oneonta Town Board: WBNGEco-Yotta Oneonta Data Centernot yet on record
Apr 18, 2026
held
Lysander Town Board: Baldwinsville Messenger / Eagle News OnlineRanalli Lysander Data Centernot yet on record

Hearings still on a project’s record. Upcoming hearings calendar →

How this report is made

Generated from the Census records at build time. It lists dated timeline events, hearings, lawsuit filing dates and moratorium actions that fall in the month; each links to its project record and source. A month-only date belongs to its month. Entries dated only to a year are not placed in a month. Approval, denial, cancellation and construction counts are made by reading the wording of each dated event, so one event can count in more than one group, and a vote on a related item can be miscounted; open the linked record to read the source. Nothing is estimated.

The same data is behind the statistics page, the charts and the downloads.

Cite this page

Last updated Oct 14, 2026. Figures may change as records are updated — include the date you retrieved them.

APAData Center Census. (2026). U.S. data centers in April 2026. Retrieved from https://datacentercensus.com/reports/2026-04
MLA“U.S. data centers in April 2026.” Data Center Census, Oct 14, 2026, https://datacentercensus.com/reports/2026-04.
Linkhttps://datacentercensus.com/reports/2026-04

Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.