Monthly report

U.S. data centers in October 2025

In October 2025, the Data Center Census recorded 35 dated changes at 29 tracked projects across 15 states.

Final report for October 2025, published November 1, 2025. Last data change: . Page rebuilt .

← September 2025 November 2025 → All reports · Monthly RSS

Dated changes
35
Projects with a first milestone
5
Moratorium actions
0
Court cases filed
0

The month in one paragraph

In October 2025, the Data Center Census recorded 35 dated changes at 29 tracked projects across 15 states. 5 projects have their earliest dated milestone in the month. Events recorded include 2 approvals, 1 denial, 2 construction or operations starts. That is 6 more than the 29 changes recorded in September 2025.

Counts describe what was recorded in this tracker, from published filings, notices and reports. They are not a measure of everything that happened in the industry, and a month’s counts can rise later if sources dated in it are added.

Compared with September 2025

MeasureOctober 2025September 2025Change
Dated changes recorded3529+6
Projects with a change2925+4
States1514+1
Projects with first milestone58−3
Approval events25−3
Denial events110
Cancellation events01−1
Construction or operations starts20+2
Moratorium actions01−1
Court cases filed000
Hearings and votes held000
Hearings and votes upcoming000

Projects with their first milestone in October 2025

ProjectFirst milestoneStatus now
Google Hermantown Data Center
Hermantown, St. Louis County, MN
Oct 17, 2025Proposed
Project Galaxy (AWS Sidney data center)
Sidney, Shelby County, OH
Oct 27, 2025Approved
QTS DeForest Data Center Campus
DeForest, Dane County, WI
Oct 30, 2025Cancelled
CyrusOne Sangamon County Data Center
Waverly, Sangamon County, IL
Oct 31, 2025Approved
Google Palo data center campus
Palo, Linn County, IA
Oct 31, 2025Proposed

A project appears here when its earliest dated timeline entry is in this month. It does not mean it was announced publicly that month.

Every dated change

DateWhat changedProject
Oct 30, 2025Vantage and Wisconsin Building Trades Council announce labor partnership for $15B+ campus Business WirePort Washington (Lighthouse) Data Center Campus
Port Washington, Ozaukee County, WI · Under construction
Oct 30, 2025QTS announces plans for a data center campus in Dane County and a $50 million community commitment Spectrum News 1QTS DeForest Data Center Campus
DeForest, Dane County, WI · Cancelled
Oct 30, 2025OpenAI, Oracle and Related Digital announce Stargate site CBS DetroitSaline Township Stargate Data Center
Saline Township, Washtenaw County, MI · Under construction
Oct 29, 2025AWS activates Project Rainier; cluster fully operational with ~500,000 Trainium2 chips Data Center KnowledgeProject Rainier (AWS New Carlisle campus)
New Carlisle, St. Joseph County, IN · Operating
Oct 28, 2025Village Board takes up an ordinance amending the PUD conditional use and final plat for the Mount Prospect Technology Campus Village of Mount Prospect, ILCloudHQ ORD Campus
Mount Prospect, Cook County, IL · Under construction
Oct 27, 2025Sidney City Council passes resolution supporting the 30-year tax abatement Dayton Daily NewsProject Galaxy (AWS Sidney data center)
Sidney, Shelby County, OH · Approved
Oct 25, 2025Somerset Planning Board and Town Board unanimously approve expansion on 61 acres Niagara Gazette (via Yahoo Finance)
Approval
Lake Mariner
Somerset, Niagara County, NY · Operating
Oct 21, 2025Commissioner Melissa Link calls for a data center moratorium after the denial WUGAOld Elberton Road data center proposal
Athens, Athens-Clarke County, GA · Denied
Oct 21, 2025First three buildings topped out Corridor Business JournalQTS Cedar Rapids Data Center Campus
Cedar Rapids, Linn County, IA · Under construction
Oct 17, 2025Environmental Quality Board receives a petition requesting an Environmental Assessment Worksheet for the project City of HermantownGoogle Hermantown Data Center
Hermantown, St. Louis County, MN · Proposed
Oct 17, 2025EGLE issues a permit waiver allowing Related Digital to begin installing generators before the final air permit. Planet DetroitSaline Township Stargate Data Center
Saline Township, Washtenaw County, MI · Under construction
Oct 15, 2025Meta announces El Paso data center, >$1.5B Meta Data CentersMeta El Paso Data Center
El Paso, El Paso County, TX · Under construction
Oct 15, 2025Poolside announces Project Horizon with CoreWeave as anchor tenant under a 15-year, 250 MW lease PoolsideProject Horizon
Fort Stockton, Pecos County, TX · Proposed
Oct 15, 2025Consent judgment filed in Washtenaw County Circuit Court allowing project to proceed DatacenterDynamicsSaline Township Stargate Data Center
Saline Township, Washtenaw County, MI · Under construction
Oct 8, 2025Judge Ryan Larson of the 395th District Court dismisses neighbors' lawsuit over the parkland deed KUT RadioBlueprint Taylor Data Center
Taylor, Williamson County, TX · Approved
Oct 7, 2025Athens-Clarke Mayor and Commission unanimously deny the rezoning DatacenterDynamics
Denial
Old Elberton Road data center proposal
Athens, Athens-Clarke County, GA · Denied
Oct 2, 2025Google announces its $4 billion Arkansas investment and first data center in the state GoogleGoogle West Memphis Data Center
West Memphis, Crittenden County, AR · Under construction
Oct 2025Amazon breaks ground on the campus DatacenterDynamicsAmazon Web Services Richmond County data center campus
Hamlet, Richmond County, NC · Under construction
Oct 2025CyrusOne proposal for 280-acre Talkington Township campus becomes public Illinois TimesCyrusOne Sangamon County Data Center
Waverly, Sangamon County, IL · Approved
Oct 2025Fermi raises $746M in IPO; land clearing begins CleanviewFermi America Project Matador
Amarillo, Carson County, TX · Under construction
Oct 2025Amarillo City Council votes 4-1 to sell up to 2.5M gallons/day of water ABC 7 AmarilloFermi America Project Matador
Amarillo, Carson County, TX · Under construction
Oct 2025Commissioners unanimously approve amended abatement as project is scaled back to 3–4 buildings KFDA NewsChannel 10
Approval
Goodnight Campus
Claude, Armstrong County, TX · Under construction
Oct 2025Google confirms it is exploring a development in Morgan County DatacenterDynamicsGoogle Morgan County Data Center
Monrovia, Morgan County, IN · Under construction
Oct 2025Google informs the Linn County Board of Supervisors of plans for a six-building campus on 545 acres Inside Climate NewsGoogle Palo data center campus
Palo, Linn County, IA · Proposed
Oct 2025Construction begins Action News 5
Construction or operations start
Google West Memphis Data Center
West Memphis, Crittenden County, AR · Under construction
Oct 2025Second land use amendment application submitted Community ImpactHighlander SM One data center
San Marcos, Hays County, TX · Denied
Oct 2025Building 1 operating, per Epoch AI Epoch AIMeta Prometheus
New Albany, Franklin and Licking counties, OH · Operating
Oct 2025Facility begins operations MicrosoftMicrosoft Fairwater Atlanta
Fayetteville, Fayette County, GA · Operating
Oct 2025Phase I of Building 1 reaches ready for service Applied DigitalPolaris Forge 1
Ellendale, Dickey County, ND · Operating
Oct 2025Prologis's purchase of the city-owned industrial park land closes WCPO (Journal-News story by Bryn Dippold)Project Mila
Trenton, Butler County, OH · Under construction
Oct 2025Microsoft Fairwater AI facility opens in first building Atlanta Journal-ConstitutionQTS Fayetteville data center campus
Fayetteville, Fayette County, GA · Operating
Oct 2025Construction starts Amazon
Construction or operations start
Salem Township Innovation Campus
Salem Township, Luzerne County, PA · Under construction
Oct 2025Planning and Zoning Commission votes 4-2 to recommend against the proposal WPTVSentinel Grove Technology Park
Fort Pierce, St. Lucie County, FL · Paused
Oct 2025Timberline announces it will temporarily pause the project TCPalm (via AOL)Sentinel Grove Technology Park
Fort Pierce, St. Lucie County, FL · Paused
Oct 2025Crews begin site preparation along Hallock Young Road The Business Journal (Youngstown)Stargate Lordstown
Lordstown, Trumbull County, OH · Under construction

How this report is made

Generated from the Census records at build time. It lists dated timeline events, hearings, lawsuit filing dates and moratorium actions that fall in the month; each links to its project record and source. A month-only date belongs to its month. Entries dated only to a year are not placed in a month. Approval, denial, cancellation and construction counts are made by reading the wording of each dated event, so one event can count in more than one group, and a vote on a related item can be miscounted; open the linked record to read the source. Nothing is estimated.

The same data is behind the statistics page, the charts and the downloads.

Cite this page

Last updated Oct 14, 2026. Figures may change as records are updated — include the date you retrieved them.

APAData Center Census. (2026). U.S. data centers in October 2025. Retrieved from https://datacentercensus.com/reports/2025-10
MLA“U.S. data centers in October 2025.” Data Center Census, Oct 14, 2026, https://datacentercensus.com/reports/2025-10.
Linkhttps://datacentercensus.com/reports/2025-10

Republishing a figure or table? Attribute it to Data Center Census with a link to this page. The underlying data is downloadable as JSON and CSV; the press kit has standing figures and contact details.