Monthly report
U.S. data centers in November 2025
In November 2025, the Data Center Census recorded 29 dated changes at 27 tracked projects across 15 states.
Final report for November 2025, published December 1, 2025. Last data change: . Page rebuilt .
← October 2025 December 2025 → All reports · Monthly RSS
- Dated changes
- 29
- Projects with a first milestone
- 6
- Moratorium actions
- 1
- Court cases filed
- 0
The month in one paragraph
In November 2025, the Data Center Census recorded 29 dated changes at 27 tracked projects across 15 states. 6 projects have their earliest dated milestone in the month. Events recorded include 10 approvals, 1 denial, 1 construction or operations start. 1 moratorium action was recorded, 1 of them adopted, extended or announced. That is 6 fewer than the 35 changes recorded in October 2025.
Counts describe what was recorded in this tracker, from published filings, notices and reports. They are not a measure of everything that happened in the industry, and a month’s counts can rise later if sources dated in it are added.
Compared with October 2025
| Measure | November 2025 | October 2025 | Change |
|---|---|---|---|
| Dated changes recorded | 29 | 35 | −6 |
| Projects with a change | 27 | 29 | −2 |
| States | 15 | 15 | 0 |
| Projects with first milestone | 6 | 5 | +1 |
| Approval events | 10 | 2 | +8 |
| Denial events | 1 | 1 | 0 |
| Cancellation events | 0 | 0 | 0 |
| Construction or operations starts | 1 | 2 | −1 |
| Moratorium actions | 1 | 0 | +1 |
| Court cases filed | 0 | 0 | 0 |
| Hearings and votes held | 0 | 0 | 0 |
| Hearings and votes upcoming | 0 | 0 | 0 |
Projects with their first milestone in November 2025
| Project | First milestone | Status now |
|---|---|---|
| Quiet Data Centers, Trestle Road Enfield, Halifax County, NC | Nov 3, 2025 | Proposed |
| Meta Beaver Dam Data Center Beaver Dam, Dodge County, WI | Nov 12, 2025 | Under construction |
| Wallace Jackson Data Center Campus Griffin, Spalding County, GA | Nov 25, 2025 | Approved |
| AWS Project Green New Florence, Montgomery County, MO | Nov 26, 2025 | Approved |
| CRG Festus Data Center Festus, Jefferson County, MO | Nov 30, 2025 | Approved |
| Project Cherry Blossom Frenchtown Township, Monroe County, MI | Nov 30, 2025 | Proposed |
A project appears here when its earliest dated timeline entry is in this month. It does not mean it was announced publicly that month.
Every dated change
| Date | What changed | Project |
|---|---|---|
| Nov 26, 2025 | KOMU reports AWS plans a data center near New Florence, with power from Ameren Missouri KOMU 8 | AWS Project Green New Florence, Montgomery County, MO · Approved |
| Nov 25, 2025 | Spalding County Planning Commission hearing on the data center rezoning is tabled over what the county zoning attorney called a legal issue The Griffin Daily News | Wallace Jackson Data Center Campus Griffin, Spalding County, GA · Approved |
| Nov 24, 2025 | Phase II ready for service; Building 1 fully energized at 100 MW Applied Digital | Polaris Forge 1 Ellendale, Dickey County, ND · Operating |
| Nov 21, 2025 | Trustee Bob Wilson says Meta is behind the project Michigan Advance | Howell Township Data Center Howell, Livingston County, MI · Paused |
| Nov 20, 2025 | Lancaster City Council approves $20 million community benefits agreement, 6-1 LancasterOnline Approval | CoreWeave Lancaster data center Lancaster, Lancaster County, PA · Under construction |
| Nov 20, 2025 | Howell Township Board unanimously adopts a six-month data center moratorium; it does not cover the pending rezoning request Michigan Advance | Howell Township Data Center Howell, Livingston County, MI · Paused |
| Nov 19, 2025 | Wilmington City Schools Board of Education approves the School Compensation Agreement Clinton County Port Authority (Choose Clinton County) Approval | AWS Wilmington data center Wilmington, Clinton County, OH · Approved |
| Nov 19, 2025 | Livingston County Planning Commission recommends against the rezoning Planet Detroit | Howell Township Data Center Howell, Livingston County, MI · Paused |
| Nov 18, 2025 | DEP issues final air quality plan approval 32-00457A Pennsylvania Department of Environmental Protection Approval | Homer City Energy Campus Homer City, Indiana County, PA · Under construction |
| Nov 18, 2025 | Fiscal Court approves new moratorium lasting until regulations are approved The Oldham Era Approval | Project Lincoln Oldham County, KY · Cancelled |
| Nov 18, 2025 | Bessemer City Council gives final approval to the Project Marvel rezoning DatacenterDynamics Approval | Project Marvel Bessemer, Jefferson County, AL · Approved |
| Nov 14, 2025 | Google announces $40 billion Texas plan including a data center in Armstrong County Texas Tribune | Goodnight Campus Claude, Armstrong County, TX · Under construction |
| Nov 13, 2025 | Dakota County judge denies the city's motion to dismiss City of Farmington Denial | Farmington Technology Park Farmington, Dakota County, MN · Approved |
| Nov 12, 2025 | Intergovernmental PILOT agreement amended after approval by county commission, school board and development authority; water/sewer funding moved to a separate agreement with the Butts County Water and Sewer Authority Jackson Progress-Argus Approval | Amazon Web Services Butts County data center campus Jackson, Butts County, GA · Approved |
| Nov 12, 2025 | Meta and state and local officials announce the $1 billion Beaver Dam data center campus Wisconsin Economic Development Corporation | Meta Beaver Dam Data Center Beaver Dam, Dodge County, WI · Under construction |
| Nov 12, 2025 | Microsoft publicly unveils Fairwater Atlanta as part of its AI superfactory Microsoft | Microsoft Fairwater Atlanta Fayetteville, Fayette County, GA · Operating |
| Nov 10, 2025 | City approves the project via Ordinance No. 2025-78 United City of Yorkville Approval | Project Cardinal Data Center Campus Yorkville, Kendall County, IL · Approved |
| Nov 10, 2025 | Pecos County Commissioners Court agenda includes a tax abatement agreement with Poolside Inc. Pecos County, Texas | Project Horizon Fort Stockton, Pecos County, TX · Proposed |
| Nov 5, 2025 | Amazon Data Services closes purchase of land in the park from Stanley Martin Homes Virginia Business | Devlin Technology Park Bristow, Prince William County, VA · Approved |
| Nov 5, 2025 | MCEA and Stop the Hermantown Data Center appeal the City of Hermantown's environmental study Minnesota Center for Environmental Advocacy | Google Hermantown Data Center Hermantown, St. Louis County, MN · Proposed |
| Nov 3, 2025 | Halifax County Board of Commissioners holds the required public hearing before authorizing the economic development and land purchase agreements Halifax County Board of Commissioners, via RRSpin | Quiet Data Centers, Trestle Road Enfield, Halifax County, NC · Proposed |
| Nov 2025 | City annexes 240 acres; Planning & Zoning recommends and council approves rezoning ~370 acres to I-1 industrial Jefferson County Leader Approval | CRG Festus Data Center Festus, Jefferson County, MO · Approved |
| Nov 2025 | Tensions over the proposal grow in Tompkins County as opponents threaten litigation The Cornell Daily Sun | Lake Hawkeye Lansing, Tompkins County, NY · Proposed |
| Nov 2025 | Port Washington Common Council unanimously approves creation of Tax Incremental District No. 5 for the data center campus WPR Approval | Port Washington (Lighthouse) Data Center Campus Port Washington, Ozaukee County, WI · Under construction |
| Nov 2025 | Cloverleaf presents the proposal at a public meeting; residents raise water, power and noise concerns FOX 2 Detroit | Project Cherry Blossom Frenchtown Township, Monroe County, MI · Proposed |
| Nov 2025 | Trenton City Council votes to create an I-T zoning district, which the city manager says anticipated the data center WVXU | Project Mila Trenton, Butler County, OH · Under construction |
| Nov 2025 | Construction begins Fortune Construction or operations start | Saline Township Stargate Data Center Saline Township, Washtenaw County, MI · Under construction |
| Nov 2025 | Crusoe tops out final (eighth) building DatacenterDynamics | Stargate Abilene Abilene, Taylor County, TX · Operating |
| Nov 2025 | Janesville City Council approves a letter of intent with Viridian 5-2 WPR Approval | Viridian Data Center Campus (former GM/JATCO site) Janesville, Rock County, WI · Cancelled |
Moratorium actions
| Jurisdiction | Action | Date | Source |
|---|---|---|---|
| Howell Township Michigan · six months | Adopted | Nov 2025 | WHMI |
How this report is made
Generated from the Census records at build time. It lists dated timeline events, hearings, lawsuit filing dates and moratorium actions that fall in the month; each links to its project record and source. A month-only date belongs to its month. Entries dated only to a year are not placed in a month. Approval, denial, cancellation and construction counts are made by reading the wording of each dated event, so one event can count in more than one group, and a vote on a related item can be miscounted; open the linked record to read the source. Nothing is estimated.
The same data is behind the statistics page, the charts and the downloads.
Cite this page
Last updated Oct 14, 2026. Figures may change as records are updated — include the date you retrieved them.
| APA | Data Center Census. (2026). U.S. data centers in November 2025. Retrieved from https://datacentercensus.com/reports/2025-11 |
|---|---|
| MLA | “U.S. data centers in November 2025.” Data Center Census, Oct 14, 2026, https://datacentercensus.com/reports/2025-11. |